Comparing Investment Criteria Consider the following cash flows of two mutually exclusive projects for Tokyo Rubber Company. Assume the discount rate for both projects is 8 percent.
Year | Dry Prepreg | Solvent Prepreg |
0 | –$1,700,000 | –$750,000 |
1 | 1,100,000 | 375,000 |
2 | 900,000 | 600,000 |
3 | 750,000 | 390,000 |
- a. Based on the payback period, which project should be taken?
- b. Based on the
NPV , which project should be taken? - c. Based on the JRR, which project should be taken?
- d. Based on this analysis, is incremental
IRR analysis necessary? If yes, please conduct the analysis.
Expert Solution & Answer
Want to see the full answer?
Check out a sample textbook solutionStudents have asked these similar questions
Consider the cash flows for the investment projects given in Table. Assume that the
MARR = 10%.
(a) Suppose A, B, and C are mutually exclusive projects. Which project would be selected
on the basis of the IRR criterion?
(b) Assume that projects C and E are mutually exclusive. Using the IRR criterion, which
Project would you select?.
Net Cash Flow
B
D.
E
-4,850
2,100
2,100
2,500
4,250
3,200
2,850
800
300
4,250
4,250
2,850
2,900
1,050
500
-835
-835
-835
-835
1,500
3.250
1,600
1,200
2,100
2,100
Consider the cash flows for the investment projects given in Table. Assume that the
MARR = 10%.
(a) Suppose A, B, and C are mutually exclusive projects. Which project would be selected
on the basis of the IRR criterion
(b) Assume that projects C and È are mutually exclusive. Using the IRR criterion, which
Project would you select?
Net Cash Flow
A
В
C
D
E
-4,250
3,200
2,850
-4,250
1,500
3,250
1,600
1,200
-4,250
2,850
-4,850
2,100
2,100
2,100
2,100
2,500
1
-835
2,900
1,050
500
2
-835
3
800
-835
4
300
-835
18. Comparing Investment Criteria Consider the following cash flows of two mutually exclusive projects for Tokyo Rubber Company.
Assume the discount rate for both projects is 8 percent.
Year
0
1
2
3
Dry Prepreg
-$1,800,000
1,080,000
840,000
870,000
Solvent Prepreg
-$715,000
380,000
627,000
396,000
a. Based on the payback period, which project should be taken?
b. Based on the NPV, which project should be taken?
c. Based on the IRR, which project should be taken?
d. Based on this analysis, is incremental IRR analysis necessary? If yes, please conduct the analysis.
Chapter 5 Solutions
EBK CORPORATE FINANCE
Ch. 5 - Payback Period and Net Present Value If a project...Ch. 5 - Net Present Value Suppose a project has...Ch. 5 - Comparing Investment Criteria Define each of the...Ch. 5 - Payback and Internal Rate of Return A project has...Ch. 5 - International Investment Projects In March 2014,...Ch. 5 - Capital Budgeting Problems What are some of the...Ch. 5 - Prob. 7CQCh. 5 - Prob. 8CQCh. 5 - Net Present Value versus Profitability Index...Ch. 5 - Internal Rate of Return Projects A and B have the...
Ch. 5 - Net Present Value You are evaluating Project A and...Ch. 5 - Modified Internal Rate of Return One of the less...Ch. 5 - Net Present Value It is sometimes stated that the...Ch. 5 - Prob. 14CQCh. 5 - Calculating Payback Period and NPV Maxwell...Ch. 5 - Calculating Payback An investment project provides...Ch. 5 - Calculating Discounted Payback An investment...Ch. 5 - Calculating Discounted Payback An investment...Ch. 5 - Prob. 5QPCh. 5 - Calculating IRR Compute the internal rate of...Ch. 5 - Calculating Profitability Index Bill plans to open...Ch. 5 - Calculating Profitability Index Suppose the...Ch. 5 - Cash Flow Intuition A project has an initial cost...Ch. 5 - Prob. 10QPCh. 5 - NPV versus IRR Consider the following cash flows...Ch. 5 - Problems with Profitability Index The Coris...Ch. 5 - Prob. 13QPCh. 5 - Comparing Investment Criteria Wii Brothers, a game...Ch. 5 - Profitability Index versus NPV Hanmi Group, a...Ch. 5 - Comparing Investment Criteria Consider the...Ch. 5 - Comparing Investment Criteria The treasurer of...Ch. 5 - Comparing Investment Criteria Consider the...Ch. 5 - Prob. 19QPCh. 5 - NPV and Multiple IRRs You are evaluating a project...Ch. 5 - Payback and NPV An investment under consideration...Ch. 5 - Multiple IRRs This problem is useful for testing...Ch. 5 - NPV Valuation The Yurdone Corporation wants to set...Ch. 5 - Calculating IRR The Utah Mining Corporation is set...Ch. 5 - Prob. 25QPCh. 5 - Calculating IRR Consider two streams of cash...Ch. 5 - Calculating Incremental Cash Flows Darin Clay, the...Ch. 5 - Prob. 28QPCh. 5 - Prob. 1MCCh. 5 - Seth Bullock, the owner of Bullock Gold Mining, is...
Knowledge Booster
Learn more about
Need a deep-dive on the concept behind this application? Look no further. Learn more about this topic, finance and related others by exploring similar questions and additional content below.Similar questions
- Project S has a cost of $10,000 and is expected to produce benefits (cash flows) of $3,000 per year for 5 years. Project L costs $25,000 and is expected to produce cash flows of $7,400 per year for 5 years. Calculate the two projects’ NPVs, IRRs, MIRRs, and PIs, assuming a cost of capital of 12%. Which project would be selected, assuming they are mutually exclusive, using each ranking method? Which should actually be selected?arrow_forwardConsider the following cash flows of two mutually exclusive projects for Tokyo Rubber Company. Assume the discount rate for both projects is 9 percent. Year Dry Prepreg Solvent Prepreg 0 −$ 1,770,000 −$ 785,000 1 1,107,000 410,000 2 914,000 670,000 3 757,000 404,000 a. What is the payback period for both projects? b. What is the NPV for both projects? c. What is the IRR for both projects? d. Calculate the incremental IRR for the cash flows.arrow_forwardConsider the following two mutually exclusive projects: Year Cash Flow (A) Cash Flow (B) 0 −$29,000 −$29000 1 14,400 4,300 2 12,300 9,800 3 9,200 15,200 4 5,100 16,800 a) What is the Internal Rate of Return (IRR) for each of these projects? b) Using the IRR decision rule, which project should the company accept? c) If the required return is 11 percent, what is the Net Present Value (NV) for each of these projects? d) Using the NPV decision rule, which project should the company accept? e) Why do you think the NPV and IRR rules do not agree on same project approval/rejection direction?arrow_forward
- . Consider the following cash flows of two mutually exclusive projects for Tokyo Rubber Company. Assume the discount rate for both projects is 9 percent. Year Dry Prepreg Solvent Prepreg 0 −$ 1,770,000 −$ 785,000 1 1,107,000 410,000 2 914,000 670,000 3 757,000 404,000 . What is the payback period for both projects? b. What is the NPV for both projects? c. What is the IRR for both projects? (Do not round intermediate calculations and enter your answers as a percent rounded to 2 decimal places, e.g., 32.16.) d. Calculate the incremental IRR for the cash flows. b. What is the NPV for both projects? c. What is the IRR for both projects? (Do not round intermediate calculations and enter your answers as a percent rounded to 2 decimal places, e.g., 32.16.) d. Calculate the incremental IRR for the cash flows.arrow_forwardConsider the following cash flows of two mutually exclusive projects for Dubai Company. Assume the discount rate for Dubai Company is 10 percent. Required: Based on the payback period, which project should be taken? Based on the NPV, which project should be taken? Based on the IRR, which project should be taken? Based on this analysis, is incremental IRR analysis necessary? If yes, conduct the analysis.arrow_forwardAll techniques: Decision among mutually exclusive investments Pound Industries is attempting to select the best of three mutually exclusive projects. The initial investment and subsequent cash inflows associated with these projects are shown in the following table. Cash flows Initial investment (CF) Cash inflows (CF), t= 1 to 5 OA. Project A a. Calculate the payback period for each project. b. Calculate the net present value (NPV) of each project, assuming that the firm has a cost of capital equal to 11%. c. Calculate the internal rate of return (IRR) for each project. d. Indicate which project you would recommend. a. The payback period of project A is The payback period of project B is The payback period of project C is b. The NPV of project A is $ The NPV of project B is $ (Round to the nearest cent.) The NPV of project C is $. (Round to the nearest cent.) c. The IRR of project A is%. (Round to two decimal places.) The IRR of project B is %. (Round to two decimal places.) The IRR of…arrow_forward
- Calculate the payback period, net present value, and internal rate of return for Project A. Assume a discount rate of 10%. Should the firm accept or reject Project A? Explain. If Project A and Project B are mutually exclusive, which is the better choice? Explain. What are “non-conventional” cash flows? What issues arise when evaluating projects with “non-conventional” cash flows? Project A Project B Year Cash Flow Year Cash Flow 0 -$100,000 0 -$1 1 $70,000 1 $0 2 $0 2 $0 3 $50,000 3 $10arrow_forwardCase 1: Assume you are evaluating two mutually exclusive projects,the cash flows of which appear below, and that your company uses a cost of capital of 8 percent to evaluate projects such as these. Time Project A Cash Flow Project B Cash Flow 0 -$650 -$700 1 100 300 2 250 -200 3 250 550 4 200 200 5 100 80 a. Calculate the payback of Project A. b. Calculate the discounted payback of Project A. c. Calculate the IRR of Project A. d. Using the NPV method and assuming a cost of capital of 8 percent, which of these projects should be accepted?arrow_forwardOrg Pvt. Ltd. is considering two mutually exclusive capital investments. The project’s expected net cash flows are as follows: Expected cash flows year Project A Project B 0 -400 -575 1 95 150 2 110 200 3 118 250 4 125 275 5 140 230 6 150 180 a. What is each project’s IRR? b. What is the regular payback period for these two projects? c. What is the profitability index for each project if the cost of capital is 12%?arrow_forward
- You are analyzing two proposed capital investments with the following cash flows: Year Project X Project Y 0 - $20,000 - $20,000 1 12,630 7,470 2 5,660 7,470 3 6,360 7,470 4 1,920 7,470 The cost of capital for both projects is 10 percent.Calculate the profitability index (PI) for each project. (Do not round discount factors. Round intermediate calculations to 2 decimal places, e.g. 15.25 and final answer to 4 decimal places, e.g. 1.2527.) - The PI for project X is and the PI for project Y is . - Which project or projects should be accepted if you have unlimited funds to invest? ( Project x, Project Y, Neither Project, Both Projects) - Whch project should be accepted if they are mutually exclusive? (Project X, Project Y, or neither project)arrow_forwardConsider the following two mutually exclusive projects: Year Cash flow project A (RM) 0 1 2 3 4 -54,000 12,700 23,200 27,600 46,500 Cash flow Project B (RM) -23,000 11,600 11,200 12,500 6,000 Whichever project you choose, if you require a 14 percent return on your investment i) Compute the payback period for both project ii) Compute the Net Present Value (NPV) for both projects. iii) Which project do you prefer and which? Fully explain the result of your analysisarrow_forwardAssume two mutually exclusive projects have the estimated net incremental after-tax cash flows shown below. The company's required rate of retun is 12%. For each project, compute a) the net present value, b) intemal rate of return, c) profitability index and d) the payback period. e) State which project should be chosen and why Project A Initial investment Annual after-tax cash flows Year 1 Year 2 Year 3 Year 4 Year 5 $100,000 $150,000 39,000 39,000 39,000 39,000 39,000 39,000 20,000 30,000 40,000 50,000 60,000 Year 6arrow_forward
arrow_back_ios
SEE MORE QUESTIONS
arrow_forward_ios
Recommended textbooks for you
- Intermediate Financial Management (MindTap Course...FinanceISBN:9781337395083Author:Eugene F. Brigham, Phillip R. DavesPublisher:Cengage LearningEBK CONTEMPORARY FINANCIAL MANAGEMENTFinanceISBN:9781337514835Author:MOYERPublisher:CENGAGE LEARNING - CONSIGNMENT
Intermediate Financial Management (MindTap Course...
Finance
ISBN:9781337395083
Author:Eugene F. Brigham, Phillip R. Daves
Publisher:Cengage Learning
EBK CONTEMPORARY FINANCIAL MANAGEMENT
Finance
ISBN:9781337514835
Author:MOYER
Publisher:CENGAGE LEARNING - CONSIGNMENT
Profitability index; Author: The Finance Storyteller;https://www.youtube.com/watch?v=Md5ocNqKHq8;License: Standard Youtube License