A paced assembly line has been devised to manufacture calculators, as the following data show:

Chapter 5, Problem 19P, A paced assembly line has been devised to manufacture calculators, as the following data show: What

  1. What is the maximum hourly output rate from this line? (Hint: The line can go only as fast as its slowest workstation.)
  2. What cycle time corresponds to this maximum output rate?
  3. If a worker is at each station and the line operates at this maximum output rate, how much idle time is lost during each 10-hour shift?
  4. What is the line’s efficiency?

Blurred answer
Students have asked these similar questions
A single model manual assembly line produces a product whose work content time = 47.8 min. The line has 24 workstations with a manning level =1.25. Available shift time per day = 8 hr, but downtime during the shift reduces actual production time to 7.6 hr on average. This results in an average daily production of 256 units/day. Repositioning time per worker is 8% of cycle time. Determine (a) line efficiency, (b) balancing efficiency,and (c) repositioning time.
The Avis Company is a car rental company and is located three miles from the Los Angeles airport (LAX). Avis is dispatching a bus from its offices to the airport every 2 minutes. The average traveling time (a round trip) is 20 minutes. How many Avis buses are traveling to and from the airport?   The branch manager wants to improve the service and suggests dispatching buses every 0.5 minute. She argues that this will reduce the average traveling time (a round trip) to Avis’s offices to 2.5 minutes. Is she correct? If your answer is negative, then what will the average traveling time be?
A work cell at Chris Ellis Commercial Laundryhas a workstation with two machines, and each unit producedat the station needs to be processed by both of the machines.(The same unit cannot be worked on by both machines simultaneously.) Each machine has a production capacity of 4units per hour. What is the throughput time of the work cell?
Knowledge Booster
Background pattern image
Operations Management
Learn more about
Need a deep-dive on the concept behind this application? Look no further. Learn more about this topic, operations-management and related others by exploring similar questions and additional content below.
Similar questions
SEE MORE QUESTIONS
Recommended textbooks for you
Text book image
Practical Management Science
Operations Management
ISBN:9781337406659
Author:WINSTON, Wayne L.
Publisher:Cengage,
Text book image
Operations Management
Operations Management
ISBN:9781259667473
Author:William J Stevenson
Publisher:McGraw-Hill Education
Text book image
Operations and Supply Chain Management (Mcgraw-hi...
Operations Management
ISBN:9781259666100
Author:F. Robert Jacobs, Richard B Chase
Publisher:McGraw-Hill Education
Text book image
Business in Action
Operations Management
ISBN:9780135198100
Author:BOVEE
Publisher:PEARSON CO
Text book image
Purchasing and Supply Chain Management
Operations Management
ISBN:9781285869681
Author:Robert M. Monczka, Robert B. Handfield, Larry C. Giunipero, James L. Patterson
Publisher:Cengage Learning
Text book image
Production and Operations Analysis, Seventh Editi...
Operations Management
ISBN:9781478623069
Author:Steven Nahmias, Tava Lennon Olsen
Publisher:Waveland Press, Inc.
Inventory Management | Concepts, Examples and Solved Problems; Author: Dr. Bharatendra Rai;https://www.youtube.com/watch?v=2n9NLZTIlz8;License: Standard YouTube License, CC-BY