Requirement – 1
International Financial Reporting Standards
They are commonly known as IFRS. These are set of accounting standards which are developed by independent (Non-profit) organization called as International Accounting Standards Board (IASB). These are universally accepted set of standards which state the rules and standards for accounting at global level.
Revenue recognized point of long term contract
A long-term contract qualifies for revenue recognition over time. The seller can recognize the revenue as per percentage of the completion of the project, which is recognized as revenue minus cost of completion until date.
If a contract does not meet the performance obligation norm, then the seller cannot recognize the revenue till the project is complete.
The revenue recognition principle
The revenue recognition principle refers to the revenue that should be recognized in the time period, when the performance obligation (sales or services) of the company is completed.
Rules of Debit and Credit:
Following rules are followed for debiting and crediting different accounts while they occur in business transactions:
- Debit, all increase in assets, expenses and dividends, all decrease in liabilities, revenues and stockholders’ equities.
- Credit, all increase in liabilities, revenues, and stockholders’ equities, all decrease in assets, expenses.
To determine: The amount of gross profit or loss to be recognized in 2018, 2019, and 2020.
Requirement – 1
Explanation of Solution
Here,
2018 gross profit recognized is $0
2019 gross profit recognized is $0
2020 gross profit recognized is $1,800,000
Now, calculate the total gross profit:
Hence, the calculated total gross profit is $1,800,000.
Requirement – 2
To prepare: The
Requirement – 2
Explanation of Solution
In the year 2018:
Date | Account Title and Explanation | Post Ref. | Debit | Credit |
Construction in progress | $2,400,000 | |||
Various accounts | $2,400,000 | |||
(To record construction cost) |
Table (1)
- Construction in progress is an asset. There is an increase in asset value. Therefore, it is debited.
- Various accounts are revenue. There is an increase in liability value. Therefore, it is credited.
Date | Account Title and Explanation | Post Ref. | Debit | Credit |
$2,000,000 | ||||
Billings on construction contract | $2,000,000 | |||
(To record progress billings) |
Table (2)
- Account receivable is an asset. There is an increase in asset value. Therefore, it is debited.
- Billings on construction contract is revenue. There is an increase in revenue value. Therefore, it is credited.
Date | Account Title and Explanation | Post Ref. | Debit | Credit |
Cash | $1,800,000 | |||
Account receivable | $1,800,000 | |||
(To record cash collection) |
Table (3)
- Cash is an asset. There is an increase in asset value. Therefore, it is debited.
- Account receivable is an asset. There is a decrease in asset value. Therefore, it is credited.
Date | Account Title and Explanation | Post Ref. | Debit | Credit |
Cost of construction | $2,400,000 | |||
Revenue from long-term contracts | $2,400,000 | |||
(To record gross profit) |
Table (4)
- Cost of construction is an expense. There is a decrease in stockholders’ equity value. Therefore, it is debited.
- Revenue from long-term contracts is revenue. There is an increase in stockholders’ equity value. Therefore, it is credited.
In the year 2019:
Date | Account Title and Explanation | Post Ref. | Debit | Credit |
Construction in progress | $3,600,000 | |||
Various accounts | $3,600,000 | |||
(To record construction cost) |
Table (5)
- Construction in progress is an asset. There is an increase in asset value. Therefore, it is debited.
- Various accounts are revenue. There is an increase in stockholders’ equity value. Therefore, it is credited.
Date | Account Title and Explanation | Post Ref. | Debit | Credit |
Account receivable | $4,000,000 | |||
Billings on construction contract | $4,000,000 | |||
(To record progress billings) |
Table (6)
- Account receivable is an asset. There is an increase in asset value. Therefore, it is debited.
- Billings on construction contract is revenue. There is an increase in stockholders’ equity value. Therefore, it is credited.
Date | Account Title and Explanation | Post Ref. | Debit | Credit |
Cash | $3,600,000 | |||
Account receivable | $3,600,000 | |||
(To record cash collection) |
Table (7)
- Cash is an asset. There is an increase in asset value. Therefore, it is debited.
- Account receivable is an asset. There is a decrease in asset value. Therefore, it is credited.
Date | Account Title and Explanation | Post Ref. | Debit | Credit |
Cost of construction | $3,600,000 | |||
Revenue from long-term contracts | $3,600,000 | |||
(To record gross profit) |
Table (8)
- Cost of construction is an expense. There is a decrease in liability value. Therefore, it is debited.
- Revenue from long-term contracts is revenue. There is an increase in stockholders’ equity value. Therefore, it is credited.
In the year 2020:
Date | Account Title and Explanation | Post Ref. | Debit | Credit |
Construction in progress | $2,200,000 | |||
Various accounts | $2,200,000 | |||
(To record construction cost) |
Table (9)
- Construction in progress is an asset. There is an increase in asset value. Therefore, it is debited.
- Various accounts are revenue. There is an increase in stockholders’ equity value. Therefore, it is credited.
Date | Account Title and Explanation | Post Ref. | Debit | Credit |
Account receivable | $4,000,000 | |||
Billings on construction contract | $4,000,000 | |||
(To record progress billings) |
Table (10)
- Account receivable is an asset. There is an increase in asset value. Therefore, it is debited.
- Billings on construction contract is revenue. There is a decrease in
stockholders equity value. Therefore, it is credited.
Date | Account Title and Explanation | Post Ref. | Debit | Credit |
Cash | $4,600,000 | |||
Account receivable | $4,600,000 | |||
(To record cash collection) |
Table (11)
- Cash is an asset. There is an increase in asset value. Therefore, it is debited.
- Account receivable is an asset. There is a decrease in asset value. Therefore, it is credited.
Date | Account Title and Explanation | Post Ref. | Debit | Credit |
Construction in progress | $1,800,000 | |||
Cost of construction | $2,400,000 | |||
Revenue from long-term contracts | $4,000,000 | |||
(To record gross profit) |
Table (12)
- Construction in progress is an asset. There is an increase in asset value. Therefore, it is debited.
- Cost of construction is an expense. There is a decrease in liability value. Therefore, it is debited.
- Revenue from long-term contracts is revenue. There is an increase in stockholders’ equity value. Therefore, it is credited.
Requirement – 3
To prepare: The partial balance sheet for 2018 and 2019.
Requirement – 3
Explanation of Solution
Partial balance sheet of W Construction Company is as follows:
In the year 2018:
Assets | 2018 | |
Account receivables | $400,000 | |
Construction in progress | $2,400,000 | |
Less: Billings | ($2,000,000) | |
Costs in excess of billings | $400,000 |
Table (13)
In the year 2019:
Assets | 2019 | |
Account receivables | $600,000 | |
Construction in progress | $6,000,000 | |
Less: Billings | ($6,000,000) | |
Costs in excess of billings | $0 |
Table (14)
Requirement – 4
The total amount of gross profit or loss to be recognized in 2018, 2019, and 2020.
Requirement – 4
Explanation of Solution
Here,
2018 gross profit recognized is $0
2019 gross profit recognized is $0
2020 gross profit recognized is $600,000
Now, calculate the total gross profit:
Hence, the calculated total gross profit is $600,000.
Note:
Details for cost incurred and estimated cost to complete.
Particulars | 2018 | 2019 | 2020 |
Costs incurred during the year | $2,400,000 | $3,800,000 | $3,200,000 |
Estimated costs to complete as of year-end | $5,600,000 | $3,100,000 |
Table (15)
Requirement – 5
The amount of revenue and gross profit or loss to be recognized in 2018, 2019, and 2020.
Requirement – 5
Explanation of Solution
Here,
2018 gross profit recognized is $0
2019 gross profit recognized is ($300,000)
2020 gross profit recognized is $200,000
Now, calculate the total gross profit:
Hence, the calculated total gross profit is ($100,000).
Note:
Details for cost incurred and estimated cost to complete.
Particulars | 2018 | 2019 | 2020 |
Costs incurred during the year | $2,400,000 | $3,800,000 | $3,900,000 |
Estimated costs to complete as of year-end | $5,600,000 | $4,100,000 |
Table (16)
Want to see more full solutions like this?
Chapter 5 Solutions
SPICELAND GEN CMB LL INTRM ACCTG; CNCT
- ( Appendix 7A) Impairment Listed below is information related to three assets reported in the financial statements of Grant Company: Required: For each scenario, indicate whether the asset has been impaired and, if so, the amount of the impairment loss that should recorded.arrow_forwardAccounting policies for exploration and evaluation costs should be determined in accordance with which accounting standard? Select one: a. AASB 8 b. AASB 108. c. AASB 106. d. AASB 6arrow_forwardDavid Mendez Under the percentage-of-completion method, how should the balances of progress billings and construction in process be disclosed in the financial statements prior to the completion of the contract? net, as income from construction if a credit balance, and loss from construction if a debit balance progress billings as deferred income, construction in progress as a deferred expense net, as a current asset if a debit balance, and a current liability if a credit balance progress billings as income, construction in process as inventoryarrow_forward
- All of the following accounts are impliedly contained in the account "Construction in Progress” except: A. Progress Billings to date B. Costs incurred to date C. Contract Revenue to date D. Gross Profit to date S1: Zero Profit Method in revenue recognition principle recognized income upon the completion a construction contract S2: A contract asset exists when Contract revenue to date is less than progress billings to date A. Both are true B. Both are false C. s1 True D. S2 Truearrow_forwardAccess the FASB’s Codification Research System® at the FASB website (www.fasb.org) and select Basic View. Determine the specific seven-digit (XXX-XX-XX) or eight-digit Codification citation (XXX-XX-XX-X) for accounting for each of the following items: Definition of initial direct costs. When a modification to a contract is reported as a separate contract (that is, separate from the original contract). The disclosures required in the notes to the financial statements for a lessor. The classification criteria for when a lessee classifies a lease as a finance lease and a lessor classifies a lease as a sales-type lease.arrow_forwardWhen the outcome of a construction contract cannot be estimated reliably, how shall contract revenue and contract costs associated with the construction contract be recognized? Group of answer choices They shall be recognized as revenue and expenses respectively by reference to the state of completion of the contract activity at the end of the reporting period also known as by percentage of completion method. They shall be recognized as revenue and expenses respectively by the date of earning of revenue or incurring of expenses also known as accrual method. They shall be recognized as revenue and expenses respectively by reference to the percentage of collection of receivables from customers also known as by installment method. Revenue shall be recognized only to the extent of contract cost incurred that is probable will be recoverable and the contract cost shall be recognized as an expense in the period in which there are incurred also known as cost recovery or zero-profit…arrow_forward
- 1. What type of events are needed to be disclosed if identified as materials and those are indicative of conditions that arose after the reporting period? 2. These two are defined as the positive and negative effects of event to an entity. Please answer this two questions. This are under IAS 10.arrow_forward1. All of the following accounts are impliedly contained in the account Construction in Progress except: A. Costs incurred to date B. Contract Revenue to date C. Gross Profit to date D. Progress Billings to date 2. S1: Zero Profit Method in revenue recognition principle recognizes income upon the completion a construction contractS2: A contract asset exists when Contract revenue to date is less than progress billings to date. A. Both are true B. Both are false C. S1 True D. S2 Truearrow_forward7. Which of the following must be done when accounting for depreciation under IFRS GAAP but can be done under U.S. GAAP? a. Depreciate by function b. Depreciate by nature c. Depreciate by components d. All of these 8. When accounting for contingent liabilities IFRS GAAP defines ‘probable’ as a. likely b. more likely than not c. possible d. none of these 9. When accounting for contingent liabilities U.S. GAAP defines ‘probable’ as a. likely b. more likely than not c. possible d. none of thesearrow_forward
- List and discuss Impairment measurements, Testing for Impairment, Asset Grouping, and Accounting for Impairments. Briefly describe any differences between GAAP and IFRS regulations.arrow_forwardWhen percentage-of-completion accounting is not appropriate, U.S. GAAP requires the use of the completedcontract method, while IFRS requires the use of the cost recovery method. Explain how the two methods affectrecognition of revenue, cost of construction, and gross profit over the life of a profitable contract.arrow_forwardWhich of the following is not an accepted basis for recognition of revenue?A. Passage of timeB. Completion of percentage of a projectC. Performance of serviceD. Upon signing of contractarrow_forward
- Cornerstones of Financial AccountingAccountingISBN:9781337690881Author:Jay Rich, Jeff JonesPublisher:Cengage LearningAuditing: A Risk Based-Approach (MindTap Course L...AccountingISBN:9781337619455Author:Karla M Johnstone, Audrey A. Gramling, Larry E. RittenbergPublisher:Cengage Learning