a)

Summary Introduction

To determine: The last unit cost to build.

a)

Expert Solution
Check Mark

Explanation of Solution

Given information:

It is given that first unit took 4,000 hours to complete and the cost for materials and equipment usage is $30,000. Second unit took 3,200 hours to complete and the cost for materials and equipment usage is $21,000. Labor cost is given as $18 per hour.

Determine the last unit (22nd unit) cost to build:

Labor learning rate=3,2004,000=80%

Material learning rate=21,00030,000=70%

Labor cost for 22nd unit=4,000×0.3697×$18=$26,618.40

Machine cost for 22nd unit=30,000×0.2038=$6,114.00

Total amount for 22nd unit=$26,618.40+$6,114.00=$32,732.40

Hence, the last unit cost is $32,732.40.

b)

Summary Introduction

To determine: The average time for the 20 missile guidance controls.

b)

Expert Solution
Check Mark

Explanation of Solution

Given information:

It is given that first unit took 4,000 hours to complete and the cost for materials and equipment usage is $30,000. Second unit took 3,200 hours to complete and the cost for materials and equipment usage is $21,000. Labor cost is given as $18 per hour.

Determine the average time for the 20 missile guidance controls:

Labor cost for20 more units}=(Cumulative value for 22 unitsCumulative value for 2 units)×(Time to producefirst unit)=(11.2301.800)×4,000=37,720

Average labor time=Labor time for 20 more units20=37,72020=1,886 hours

c)

Summary Introduction

To determine: The average cost for guidance control for the 20 in the contract.

c)

Expert Solution
Check Mark

Explanation of Solution

Given information:

It is given that first unit took 4,000 hours to complete and the cost for materials and equipment usage is $30,000. Second unit took 3,200 hours to complete and the cost for materials and equipment usage is $21,000. Labor cost is given as $18 per hour.

Determine average cost for guidance control for the 20 in the contract:

Labor cost for20 more units}=(Cumulative value for 22 unitsCumulative value for 2 units)×(Time to producefirst unit)=(11.2301.800)×4,000=37,720

Average labor cost=Labor time for 20 more units20×$18=37,72020×$18=$33,948

Material cost for20 more units}=(Cumulative value for 22 unitsCumulative value for 2 units)×(Material cost forfirst unit)=(7.8191.700)×$30,000=$183,570

Average cost=Material cost for 20 more units20=$183,57020=$9,178.50

Determine the average total cost:

Average total cost=Average labor cost+Average material cost=$33,948+$9,178.50=$43,126.50

Want to see more full solutions like this?

Subscribe now to access step-by-step solutions to millions of textbook problems written by subject matter experts!
Knowledge Booster
Background pattern image
Recommended textbooks for you
Text book image
Practical Management Science
Operations Management
ISBN:9781337406659
Author:WINSTON, Wayne L.
Publisher:Cengage,
Text book image
Operations Management
Operations Management
ISBN:9781259667473
Author:William J Stevenson
Publisher:McGraw-Hill Education
Text book image
Operations and Supply Chain Management (Mcgraw-hi...
Operations Management
ISBN:9781259666100
Author:F. Robert Jacobs, Richard B Chase
Publisher:McGraw-Hill Education
Text book image
Business in Action
Operations Management
ISBN:9780135198100
Author:BOVEE
Publisher:PEARSON CO
Text book image
Purchasing and Supply Chain Management
Operations Management
ISBN:9781285869681
Author:Robert M. Monczka, Robert B. Handfield, Larry C. Giunipero, James L. Patterson
Publisher:Cengage Learning
Text book image
Production and Operations Analysis, Seventh Editi...
Operations Management
ISBN:9781478623069
Author:Steven Nahmias, Tava Lennon Olsen
Publisher:Waveland Press, Inc.