a. AOA network diagram:
Explanation of Solution
Draw an Activity on Arrow (AOA) network diagram representing the project given in Table 6.2 of the book. To accomplish the network diagram, follow the following steps:-
1. Put the node numbers 1 to 9 in circles.
2. Find all of the activities that start at node 1. Draw arrows between node 1 and those finish nodes. Put the activity letter and duration estimate on the associated arrow. In this case, Draw an edge from node 1 to 2 and label it as A=2. Label A=2 means activity A has a duration of 2 days.
3. Continue drawing the project network diagram until all activities are included on the diagrams that have dependencies.
4. Label each arrow with the activity letter and estimated time. The below network diagram has 11 arrows corresponding to 11 rows in the table.
- Draw second edge from node 2 to 3 and label it as B=2...
b. All paths on the network diagram:
Explanation of Solution
To identify all the paths on the network diagram, just follow the arrows to identify distinct routes from node 1 to node 9.
To find out length of each path, just add the duration for all activities on that path.
Path No | Route | Length / Total Duration |
c. Critical path for this project
Explanation of Solution
The longest path in the network diagram is the critical path...
d. Shortest possible time needed to complete this project:
Explanation of Solution
The critical path represents the shortest time requir...
Trending nowThis is a popular solution!
Chapter 6 Solutions
EBK INFORMATION TECHNOLOGY PROJECT MANA
- emaining Time: 1 hour, 23 minutes, 24 seconds. euestion Completion Status: QUESTION 13 Identify the critical path in the following Network diagram and write the total duration required to complete the project. Note: The numbers given in the diagram are days. 11 12 13 10 6. T TTArial 3 (12pt) v T- Click Save and Submit to save and submit. Click Save All Answers to save all answers. Save All Answer 道 F3 F4 F5 F6 F7 F8 14 F9 F10 Pause $ & %23arrow_forwardYour task for this assignment is to create a network diagram for two projects. The activity, immediate predecessor and duration are given. You are to layout-long-hand or using some software-a network diagram for each project. For each diagram conduct a forward and backward pass, calculate the slack, and identify the critical path. When noting your early start, early finish, late start, late finish and slack, please use the format provided. Project 1 Activity Immediate Predecessor Duration A none 3 В A 4 none 6 D none 2 D 5 F В, С, Е 2 Project 2 Activity Immediate Predecessor Duration A none 6 B none 3 A 9 B E в 4 D 2 G E 8. *Note: please use this format. Early Start Duration Early Finish Activity Float Late Start Late Finisharrow_forwardSuppose you are the project manager for the following project: First,draw a network diagram for the project. Determine the critical path andslack times for all of the tasks. This completes your plan for the projectschedule. During project execution, you become aware of the need tochange the duration of Task 4 to five days.Meanwhile, Task 3 has been finished one day early, so it only took one day to do. What, ifany, effects do these changes have on your project? What would have happened if you had notbeen monitoring the status of the project?arrow_forward
- Below is the activity table for a "Build a Commercial Airplane" project: Draw Gantt, Network diagram and identify critical path for the chart below:I also added a second image please follow that format while completing this question.arrow_forwardUsing an application of your choice: Draw a network diagram for this project, clearly showing the Activity ID and Activity durationarrow_forwardset of concurrent activities are meant to pass a course. The process is as the following: 1- Student has to attend all classes and not to miss more than 25% of the classes. 2- Students selects a paper for presentation and gives a presentation on an assigned date. 3- Student has to choose a project topic and submits at the end of the course Draw a State Machine Diagram. Make sure to define events, conditions, actions for transitions in your diagram, where appropriate.arrow_forward
- Draw Activity diagram for this scenario When the employee ( customer to us ) encounters an issue he cant solve he goes to tawasol ( the company ticketing system ) and open a ticket for the issue in the correct section and select the issue genre, explain it and add his contact info then the ticket get assigned automatically by the system to the right IT support team, from there the team in head quarter office in Riyadh assign the task to specific member based on geographic location of the issue and the nature of the issue and the competence needed. After that the team member can see it in his/her ticketing system and can assign the status of the process is it active, pending for some reason or resolved . Then the assigned member will contact the customer to further understand the issue and decide if it could be done remotely or physically, if remotely then the assigned member need to contact the network team to allow access for remote applications on that network. Then when the issue is…arrow_forwardDraw an Activity-On-Arrow (AOA) network diagram representing the project. Put the node numbers in circles and draw arrows from node to node, labelling each arrow with the activity letter and estimated durationarrow_forward1-Draw the network diagram of the activities listed in the table below using Activity on Node. 2-Find the critical path and the duration of the project. 3-Find the values of ES, EC, LS, and LC of the events 4- Find the values of TF and FF for the activitiesarrow_forward
- Take a project into consideration and map it both with and without architecture. how it will impact the result.arrow_forwardThe decision tree structure that you built suggests three possible outcomes for a project. Which of these three outcomes would you recommend for implementation in the project? How do you think the most successful technique is for obtaining information and analyzing alternatives is from your perspective?arrow_forwardHeading 3 Title Homework 2 Consider Table 6-2 on P263 in the textbook. All duration estimates or estimated times are in days, and the network proceeds from Node 1 to Node 9 Draw an AOA network diagram representing the project. Put the node numbers in circles and draw arrows from node to node, labeling each arrow with the activity letter and estimated time. Draw an PDM network diagram representing the the early start,early finish,late start activity and mark th 1. 2. 3. ldarrow_forward
- Information Technology Project ManagementComputer ScienceISBN:9781337101356Author:Kathy SchwalbePublisher:Cengage Learning