Chapter 6, Problem 6.33BE
Long-term contract; revenue recognition over time; profit recognition
• LO5–9
A construction company entered into a fixed-price contract to build an office building for $20 million. Construction costs incurred during the first year were $6 million and estimated costs to complete at the end of the year were $9 million. The company recognizes revenue over time according to percentage of completion. How much revenue and gross profit or loss will appear in the company’s income statement in the first year of the contract?
Expert Solution & Answer
Want to see the full answer?
Check out a sample textbook solutionStudents have asked these similar questions
Chapter 6-Long-Term Construction Contracts
Allbright Builders, Inc. is constructing a new business building for the local university. The contract
price is S6,000,000 and estimated costs are $5,100,000. The project is expected to take three years.
Allbright is able to reasonable estimate costs throughout the contract. Presented below is a
summary of costs, billings, and collections for the three years.
Year 1
Year2
Year3
Actual Costs per Year
$1,700,000
$1,600,000
$2,000,000
Estimated Costs to
$3,400,000
$1,900,000
Complete
Billings
Collections
$2,100,000
$1,900,000
$2,200,000
$2,000,000
$1,700,000
$2,100,000
a. Prepare the journal entries to record costs, billings and collections for Years 1, 2, and 3.
b. Compute the gross profit for each year and record the journal entry to reflect revenues, expenses
and gross profit.
c. Prepare the balance sheet disclosures for Years 1 and 2.
d. Assume that it is not possible to make reasonable estimates of progress during the contract. How
would…
Exercise 6-20 (Algo) Long-term contract; revenue recognition over time vs. upon project completion
[LO6-9]
On June 15, 2024, Sanderson Construction entered into a long-term construction contract to build a baseball stadium in Washington,
D.C., for $320 million. The expected completion date is April 1, 2026, just in time for the 2026 baseball season. Costs incurred and
estimated costs to complete at year-end for the life of the contract are as follows ($ in millions):
Costs incurred during the year
Estimated costs to complete as of December 31
Required:
Required 1 Required 2 Required 3
2024
2025
2026
Construction revenue
Construction expense
Gross profit (loss)
1. Compute the revenue and gross profit that Sanderson will report in its 2024, 2025, and 2026 income statements related to this
contract, assuming Sanderson recognizes revenue over time according to percentage of completion.
2. Compute the revenue and gross profit that Sanderson will report in its 2024, 2025, and 2026 income…
Exercise 6-20 (Algo) Long-term contract; revenue recognition over time vs. upon project completion
[LO6-9]
On June 15, 2024, Sanderson Construction entered into a long-term construction contract to build a baseball stadium in Washington,
D.C., for $410 million. The expected completion date is April 1, 2026, just in time for the 2026 baseball season. Costs incurred and
estimated costs to complete at year-end for the life of the contract are as follows ($ in millions):
Costs incurred during the year
Estimated costs to complete as of December
2024
$ 50
200
2025
$ 150
2026
$ 45
50
31
Required:
1. Compute the revenue and gross profit that Sanderson will report in its 2024, 2025, and 2026 income statements related to this
contract, assuming Sanderson recognizes revenue over time according to percentage of completion.
2. Compute the revenue and gross profit that Sanderson will report in its 2024, 2025, and 2026 income statements related to this
contract, assuming this project does not qualify…
Chapter 6 Solutions
INTERMEDIATE ACCT.CUSTOM W/CONNECT
Ch. 6 - What are the five key steps a company follows to...Ch. 6 - What indicators suggest that a performance...Ch. 6 - What criteria determine whether a company can...Ch. 6 - We recognize service revenue either at one point...Ch. 6 - What characteristics make a good or service a...Ch. 6 - Prob. 6.6QCh. 6 - What must a contract include for the contract to...Ch. 6 - How might the definition of probable affect...Ch. 6 - When a contract includes an option to buy...Ch. 6 - Prob. 6.10Q
Ch. 6 - Prob. 6.11QCh. 6 - Is a customers right to return merchandise a...Ch. 6 - Prob. 6.13QCh. 6 - Under what circumstances should sellers consider...Ch. 6 - When should a seller view a payment to its...Ch. 6 - What are three methods for estimating stand-alone...Ch. 6 - When is revenue recognized with respect to...Ch. 6 - In a franchise arrangement, what are a franchisors...Ch. 6 - When does a company typically recognize revenue...Ch. 6 - Prob. 6.20QCh. 6 - Prob. 6.21QCh. 6 - Prob. 6.22QCh. 6 - Must bad debt expense be reported on its own line...Ch. 6 - Explain the difference between contract assets,...Ch. 6 - Explain how to account for revenue on a long-term...Ch. 6 - Prob. 6.26QCh. 6 - Prob. 6.27QCh. 6 - Timing of revenue recognition LO53 Estate...Ch. 6 - Allocating the transaction price LO54 Sarjit...Ch. 6 - Existence of a contract LO5-5 Tulane Tires wrote...Ch. 6 - Prob. 6.6BECh. 6 - Prob. 6.7BECh. 6 - Performance obligations; warranties LO55 Vroom...Ch. 6 - Prob. 6.9BECh. 6 - Prob. 6.10BECh. 6 - Variable consideration LO56 Leo Consulting enters...Ch. 6 - Prob. 6.16BECh. 6 - Prob. 6.17BECh. 6 - Prob. 6.18BECh. 6 - Prob. 6.19BECh. 6 - Prob. 6.20BECh. 6 - Prob. 6.21BECh. 6 - Estimating stand-alone selling prices: expected...Ch. 6 - Estimating stand-alone selling prices; residual...Ch. 6 - Prob. 6.24BECh. 6 - Prob. 6.25BECh. 6 - Contract assets and contract liabilities LO58...Ch. 6 - Long-term contract; revenue recognition over time;...Ch. 6 - Prob. 6.34BECh. 6 - Long-term contract; revenue recognition upon...Ch. 6 - Long-term contract; revenue recognition; loss on...Ch. 6 - Prob. 6.1ECh. 6 - Allocating transaction price LO54 Video Planet...Ch. 6 - Prob. 6.4ECh. 6 - Prob. 6.6ECh. 6 - Prob. 6.7ECh. 6 - Prob. 6.9ECh. 6 - Variable considerationmost likely amount; change...Ch. 6 - Variable considerationexpected value; change in...Ch. 6 - Prob. 6.12ECh. 6 - Prob. 6.13ECh. 6 - Prob. 6.14ECh. 6 - Approaches for estimating stand-alone selling...Ch. 6 - FASB codification research LO56, LO57 Access the...Ch. 6 - FASB codification research LO58 Access the FASB...Ch. 6 - Long-term contract; revenue recognition over time;...Ch. 6 - Prob. 6.1PCh. 6 - Prob. 6.2PCh. 6 - Prob. 6.3PCh. 6 - Prob. 6.5PCh. 6 - Variable consideration; change of estimate LO53,...Ch. 6 - Prob. 6.7PCh. 6 - Prob. 6.8PCh. 6 - Prob. 6.10PCh. 6 - Long-term contract; revenue recognition over time...Ch. 6 - Prob. 6.1DMPCh. 6 - Judgment Case 52 Satisfaction of performance...Ch. 6 - Judgment Case 53 Satisfaction of performance...Ch. 6 - Prob. 6.5DMPCh. 6 - Prob. 6.7DMPCh. 6 - Prob. 6.9DMPCh. 6 - Prob. 6.10DMPCh. 6 - Prob. 6.12DMPCh. 6 - Prob. 6.13DMPCh. 6 - Prob. 6.14DMPCh. 6 - Prob. 6.15DMPCh. 6 - Prob. 1CCTC
Knowledge Booster
Learn more about
Need a deep-dive on the concept behind this application? Look no further. Learn more about this topic, accounting and related others by exploring similar questions and additional content below.Similar questions
- Exercise 6-24 (Algo) Long-term contract; revenue recognition over time; solve for unknowns [LO6-9] In 2021, Long Construction Corporation began construction work under a three-year contract. The contract price is $2,200,000. Long recognizes revenue over time according to percentage of completion for financial reporting purposes. The financial statement presentation relating to this contract at December 31, 2021, is as follows: Balance Sheet Accounts receivable (from construction progress billings) Construction in progress. Less: Billings on construction contract Cost and profit of uncompleted contracts in excess of billings Income Statement Income (before tax) on the contract recognized in 2021 Required: 1. What was the cost of construction actually incurred in 2021? $ 160,000 (152,000) 1. Actual costs incurred in 2021 2. Cash collections in 2021 3. Estimated cost to complete 4. Estimated percentage $26,000 $36,000 8,000 2. How much cash was collected in 2021 on this contract? 3. What…arrow_forwardExercise 6-20 (Algo) Long-term contract; revenue recognition over time vs. upon project completion [LO6-9] On June 15, 2024, Sanderson Construction entered into a long-term construction contract to build a baseball stadium in Washington, D.C., for $230 million. The expected completion date is April 1, 2026, just in time for the 2026 baseball season. Costs incurred and estimated costs to complete at year-end for the life of the contract are as follows ($ in millions): Costs incurred during the year Estimated costs to complete as of December 31 Required: Required 1 Required 2 Required 3 Year 1. Compute the revenue and gross profit that Sanderson will report in its 2024, 2025, and 2026 income statements related to this contract, assuming Sanderson recognizes revenue over time according to percentage of completion. 2. Compute the revenue and gross profit that Sanderson will report in its 2024, 2025, and 2026 income statements related to this contract, assuming this project does not qualify…arrow_forwardProblem 6-11 (Algo) Long-term contract; revenue recognition upon completion [LO6-9] In 2024, the Westgate Construction Company entered into a contract to construct a road for Santa Clara County for $10,000,000. The road was completed in 2026. Information related to the contract is as follows: Cost incurred during the year Estimated costs to complete as of year-end Cost incurred during the year Estimated costs to complete as of year-end Billings during the year Cash collections during the year Assume that Westgate Construction's contract with Santa Clara County does not qualify for revenue recognition over time. Required: 3. Complete the information required below to prepare a partial balance sheet for 2024 and 2025 showing any items related to the contract. 4. Calculate the amount of revenue and gross profit (loss) to be recognized in each of the three years, assuming the following costs incurred and costs to complete information. Cost incurred during the year Estimated costs to…arrow_forward
- Problem 6-11 (Algo) Long-term contract; revenue recognition upon completion [LO6-9] In 2024, the Westgate Construction Company entered into a contract to construct a road for Santa Clara County for $10,000,000. The road was completed in 2026. Information related to the contract is as follows: Cost incurred during the year Estimated costs to complete as of year- end Cost incurred during the year Estimated costs to complete as of year-end Billings during the year Cash collections during the year Assume that Westgate Construction's contract with Santa Clara County does not qualify for revenue recognition over time. Cost incurred during the year Estimated costs to complete as of year- end Required: 1. Calculate the amount of revenue and gross profit (loss) to be recognized in each of the three years. 2-a. In the journal below, complete the necessary journal entries for the year 2024 (credit "Cash, Materials, etc." for construction costs incurred). 2-b. In the journal below, complete the…arrow_forwardProblem 6-11 (Algo) Long-term contract; revenue recognition upon completion [LO6-9] In 2024, the Westgate Construction Company entered into a contract to construct a road for Santa Clara County for $10,000,000. The road was completed in 2026. Information related to the contract is as follows: Cost incurred during the year Estimated costs to complete as of year-end Cost incurred during the year Estimated costs to complete as of year-end Billings during the year Cash collections during the year Assume that Westgate Construction's contract with Santa Clara County does not qualify for revenue recognition over time. Required: 1. Calculate the amount of revenue and gross profit (loss) to be recognized in each of the three years. 2-a. In the journal below, complete the necessary journal entries for the year 2024 (credit "Cash, Materials, etc." for construction costs incurred). 2-b. In the journal below, complete the necessary journal entries for the year 2025 (credit "Cash, Materials, etc."…arrow_forward56 On February 20, 2022, ABC Construction Company entered into a fixed-price contract to construct a commercial building for P9,000,000. ABC determined that the performance obligation is satisfied over time. Information relating to the contract is as follows: 2022 2023 Percentage of completion 25% 75% Estimated costs at completion P6,750,000 P7,200,000 How much is the contract costs charged to profit or loss in 2022? On February 20, 2022, ABC Construction Company entered into a fixed-price contract to construct a commercial building for P9,000,000. ABC determined that the performance obligation is satisfied over time. Information relating to the contract is as follows: 2022 2023 Percentage of completion 25% 75% Estimated costs at completion P6,750,000 P7,200,000 How much is the contract costs charged to profit or loss in 2022?arrow_forward
- Current Attempt in Progress $103200 Marigold Company enters into a contract with a customer to build a warehouse for $400700, with a performance bonus of that will be paid based on the timing of completion. The amount of the performance bonus decreases by 20% per week for every week beyond the agreed-upon completion date. The contract requirements are similar to contracts that Marigold has performed previously and management believes that such experience is predictive for this contract. Management estimates that there is a 50% probability that the contract will be completed by the agreed-upon completion date, a 30% probability that it will be completed 1 week late, and a 20% probability that it will be completed 2 weeks late. What is the total transaction price for this revenue arrangement? O $462620 O $483260 O $489452 $503900arrow_forwardProblem 6-11 (Algo) Long-term contract; revenue recognition upon completion [LO6-9] In 2021, the Westgate Construction Company entered into a contract to construct a road for Santa Clara County for $10,000,000. The road was completed in 2023. Information related to the contract is as follows: Cost incurred during the year Estimated costs to complete as of year-end Billings during the year Cash collections during the year. 2021 $1,584,000 5,616,000 1,200,000 1,000,000 Cost incurred during the year Estimated costs to complete as of year-end) 2022 $3,240,000 2,376,000 3,624,000 2,800,000 Assume that Westgate Construction's contract with Santa Clara County does not qualify for revenue recognition over time. Required: 1. Calculate the amount of revenue and gross profit (loss) to be recognized in each of the three years. 2-a. In the journal below, complete the necessary journal entries for the year 2021 (credit "Various accounts" for construction costs incurred). Cost incurred during the…arrow_forwardProblem 6-11 (Algo) Long-term contract; revenue recognition upon completion [LO6-9] In 2021, the Westgate Construction Company entered into a contract to construct a road for Santa Clara County for $10,000,000. The road was completed in 2023. Information related to the contract is as follows: Cost incurred during the year Estimated costs to complete as of year-end Billings during the year Cash collections during the year Cost incurred during the year Estimated costs to complete as of year-end 2021 $1,584,000 5,616,000 1,200,000 1,000,000 Cost incurred during the year Estimated costs to complete as of year-end Assume that Westgate Construction's contract with Santa Clara County does not qualify for revenue recognition over time. Required: 1. Calculate the amount of revenue and gross profit (loss) to be recognized in each of the three years. 2-a. In the journal below, complete the necessary journal entries for the year 2021 (credit "Various accounts" for construction costs incurred).…arrow_forward
- PROBLEM 1 SE-HOON COMPANY sells equipment service contracts that cover a two-year period. The sale price of each contract is P600. The past experience is that, of the total pesos spent for repairs on service contracts, 40% is incurred evenly during the first contract year and 60% evenly during the second contract year. The entity sold 1,000 contracts evenly throughout 2019. 1. What is the contract revenue for 2019? a. 120,000 b. 240,000 c. 300,000 d. 150,000 2. What amount should be reported as deferred service revenue on December 31, 2019? a. 540,000 b. 480,000 c. 360,000 d. 300,000 3. What is the contract revenue for 2020? a. 180,000 b. 360,000 c. 300,000 d. 120,000 4. What is the contract revenue for 2021? a. 240,000 b. 360,000 c. 180,000 d. 0arrow_forward16 A contractor enters into a contract for the expansion of an existing two-lane highway to a three-lane highway. The contract price is P65 million plus a P5 million award fee if the expansion is complete before the holiday travel season. The contract is expected to take one year to complete. The contractor has a long history of performing this type of highway work. The award fee is binary; that is, if the job is finished before the holiday travel season, the contractor receives the full award fee. The contractor does not receive any award fee if the highway is not finished before the holiday season. The contractor believes, based on its significant past experience, that it is 95 percent likely that the contract will be completed in advance of the holiday travel season. How much should the contractor account for the award fee?arrow_forwardCLTV Section A company secured a contract that will result in income payments received of $280,000 today, $400,000 in 2 years and $600,000 in 5 years (these are single or lump sum payments they get). The expenses or outflows will include payments of $10,000 at the beginning of every month for 6 years and a one-time payment (expense) of $50,000 in one year from today. If the cost of money is 17% compounded annually, determine the Net Present Value (NPV) of the contract. a)What is the PV of the inflows? b) What is the PV of the outflows? c) What is the Net Present Value (NPV)?arrow_forward
arrow_back_ios
SEE MORE QUESTIONS
arrow_forward_ios
Recommended textbooks for you
- AccountingAccountingISBN:9781337272094Author:WARREN, Carl S., Reeve, James M., Duchac, Jonathan E.Publisher:Cengage Learning,Accounting Information SystemsAccountingISBN:9781337619202Author:Hall, James A.Publisher:Cengage Learning,
- Horngren's Cost Accounting: A Managerial Emphasis...AccountingISBN:9780134475585Author:Srikant M. Datar, Madhav V. RajanPublisher:PEARSONIntermediate AccountingAccountingISBN:9781259722660Author:J. David Spiceland, Mark W. Nelson, Wayne M ThomasPublisher:McGraw-Hill EducationFinancial and Managerial AccountingAccountingISBN:9781259726705Author:John J Wild, Ken W. Shaw, Barbara Chiappetta Fundamental Accounting PrinciplesPublisher:McGraw-Hill Education
Accounting
Accounting
ISBN:9781337272094
Author:WARREN, Carl S., Reeve, James M., Duchac, Jonathan E.
Publisher:Cengage Learning,
Accounting Information Systems
Accounting
ISBN:9781337619202
Author:Hall, James A.
Publisher:Cengage Learning,
Horngren's Cost Accounting: A Managerial Emphasis...
Accounting
ISBN:9780134475585
Author:Srikant M. Datar, Madhav V. Rajan
Publisher:PEARSON
Intermediate Accounting
Accounting
ISBN:9781259722660
Author:J. David Spiceland, Mark W. Nelson, Wayne M Thomas
Publisher:McGraw-Hill Education
Financial and Managerial Accounting
Accounting
ISBN:9781259726705
Author:John J Wild, Ken W. Shaw, Barbara Chiappetta Fundamental Accounting Principles
Publisher:McGraw-Hill Education
Depreciation -MACRS; Author: Ronald Moy, Ph.D., CFA, CFP;https://www.youtube.com/watch?v=jsf7NCnkAmk;License: Standard Youtube License