Chapter 6.S, Problem 33P
Summary Introduction
To determine: The average outgoing quality
Introduction: Statistical process control is the method that helps to measure and control the quality during the process of production.
Expert Solution & Answer
Want to see the full answer?
Check out a sample textbook solutionStudents have asked these similar questions
An acceptance sampling plan has lots of 500pieces and a sample size of 60. The number of defects in thesample may not exceed 2. This plan, based on an OC curve,has a probability of .57 of accepting lots when the incominglots have a defective rate of 4%, which is the historical averagefor this process. What do you tell your customer the averageoutgoing quality is?
At Webster Chemical Company, lumps in the caulking compound could cause difficulties in dispensing a smooth bead from the tube. Even when the process is in control, an average of four lumps per tube of caulk will remain. Testing for the presence of lumps destroys the product, so an analyst takes random samples. The following results are obtained:
Tube No.
Lumps
Tube No.
Lumps
Tube No.
Lumps
1
6
5
6
9
5
2
5
6
4
10
0
3
0
7
1
11
9
4
4
8
6
12
2
Determine the c-chart two-sigma upper and lower control limits for this process. Is the process in statistical control?
50 motor generators are inspected per day from a stable process. The best estimate of the fraction of nonconforming is 0.076. Determine the centeral line and control limits. On a particular day, 5 nonconforming generators were discovered. Is this process in or out of control? For the information given in the problem, construct a np-chart
Chapter 6 Solutions
New Myomlab With Pearson Etext -- Access Card -- For Operations Management
Ch. 6.S - Prob. 1DQCh. 6.S - Define in statistical control.Ch. 6.S - Prob. 3DQCh. 6.S - Prob. 4DQCh. 6.S - Prob. 5DQCh. 6.S - Prob. 6DQCh. 6.S - Prob. 7DQCh. 6.S - Prob. 8DQCh. 6.S - Prob. 9DQCh. 6.S - Prob. 10DQ
Ch. 6.S - Prob. 11DQCh. 6.S - Prob. 12DQCh. 6.S - Prob. 13DQCh. 6.S - Prob. 14DQCh. 6.S - Prob. 15DQCh. 6.S - Prob. 16DQCh. 6.S - Prob. 17DQCh. 6.S - What does the formula L = D2C mean?Ch. 6.S - Prob. 19DQCh. 6.S - An avant-garde clothing manufacturer runs a series...Ch. 6.S - Prob. 2PCh. 6.S - Prob. 3PCh. 6.S - Prob. 4PCh. 6.S - Kathleen McFaddens restaurant in Boston has...Ch. 6.S - Develop a flowchart [as in Figure 6.6 (e) and...Ch. 6.S - Prob. 7PCh. 6.S - Prob. 8PCh. 6.S - Prob. 9PCh. 6.S - Prob. 10PCh. 6.S - Prob. 11PCh. 6.S - Prob. 12PCh. 6.S - Prob. 13PCh. 6.S - Prob. 14PCh. 6.S - Prob. 15PCh. 6.S - Prob. 16PCh. 6.S - Prob. 17PCh. 6.S - Prob. 18PCh. 6.S - Prob. 19PCh. 6.S - Prob. 20PCh. 6.S - Prob. 21PCh. 6.S - Prob. 22PCh. 6.S - Prob. 23PCh. 6.S - Prob. 24PCh. 6.S - Prob. 25PCh. 6.S - Prob. 26PCh. 6.S - Prob. 27PCh. 6.S - Prob. 28PCh. 6.S - Prob. 29PCh. 6.S - Prob. 30PCh. 6.S - Prob. 31PCh. 6.S - Prob. 32PCh. 6.S - Prob. 33PCh. 6.S - Prob. 34PCh. 6.S - Prob. 35PCh. 6.S - Prob. 1CSCh. 6.S - Prob. 2CSCh. 6.S - Prob. 1.1VCCh. 6.S - Prob. 1.2VCCh. 6.S - Prob. 1.3VCCh. 6.S - Prob. 2.1VCCh. 6.S - Prob. 2.2VCCh. 6.S - Prob. 2.3VCCh. 6.S - Prob. 2.4VCCh. 6 - Prob. 1DQCh. 6 - Prob. 2DQCh. 6 - Prob. 3DQCh. 6 - Prob. 4DQCh. 6 - Prob. 5DQCh. 6 - Prob. 6DQCh. 6 - Prob. 7DQCh. 6 - Prob. 8DQCh. 6 - Prob. 9DQCh. 6 - Prob. 10DQCh. 6 - Prob. 11DQCh. 6 - Prob. 12DQCh. 6 - Prob. 13DQCh. 6 - Prob. 14DQCh. 6 - Prob. 15DQCh. 6 - Prob. 16DQCh. 6 - Prob. 17DQCh. 6 - What does the formula L = D2C mean?Ch. 6 - Prob. 19DQCh. 6 - An avant-garde clothing manufacturer runs a series...Ch. 6 - Prob. 2PCh. 6 - Prob. 3PCh. 6 - Prob. 4PCh. 6 - Kathleen McFaddens restaurant in Boston has...Ch. 6 - Develop a flowchart [as in Figure 6.6 (e) and...Ch. 6 - Prob. 7PCh. 6 - Prob. 8PCh. 6 - Prob. 9PCh. 6 - Prob. 10PCh. 6 - Prob. 11PCh. 6 - Prob. 12PCh. 6 - Prob. 13PCh. 6 - Prob. 14PCh. 6 - Prob. 15PCh. 6 - Prob. 16PCh. 6 - Prob. 17PCh. 6 - Prob. 1CSCh. 6 - How could the survey have been more useful?Ch. 6 - Prob. 3CSCh. 6 - Prob. 1.1VCCh. 6 - Prob. 1.2VCCh. 6 - Prob. 1.3VCCh. 6 - Prob. 1.4VCCh. 6 - Prob. 2.1VCCh. 6 - Prob. 2.2VCCh. 6 - Prob. 2.3VCCh. 6 - Prob. 2.4VCCh. 6 - Prob. 2.5VC
Knowledge Booster
Learn more about
Need a deep-dive on the concept behind this application? Look no further. Learn more about this topic, operations-management and related others by exploring similar questions and additional content below.Similar questions
- A Six Sigma process that is running at the center of its control limits would expect this defect rate.arrow_forwardA metal fabricator produces connecting rods with an outer diameter that has a 1 ± 0.04 inch specification. A machine operator takes several sample measurements over time and determines the sample mean outer diameter to be 1.003 inches with a standard deviation of 0.020 inch. Calculate the process capability index.arrow_forwardA researcher wishes to estimate the proportion of fish in a certain lake that is inedible due to pollution of the lake. How large a sample should be tested in order to be 99% confident that the true proportion of inedible fish is estimated to within 8%?arrow_forward
- A pharmaceutical company producing vitamin capsules desires a proportion of calcium content between 40 and 55 ppm. A random sample of 20 capsules chosen from the output yields a sample mean calcium content of 44 ppm with a standard deviation of 3 ppm. Find the natural tolerance limits of the process. If the process is in control at the present values of its parameters, what proportion of the output will be nonconforming, assuming a normal distribution of the characteristic? Answer letters a, b, and c. a. Find the Cp index. Comment on the ability of the process to meet specifications. b. What proportion of the specification range is used up by the process? c. If it is easier to change the process mean than to change its variability, to what value should the process mean be set to minimize the proportion of nonconforming product?arrow_forwardStudies on a machine that molds plastic water pipe indicate that when it is injecting1-inch diameter pipe, the process standard deviation is 0.05 inches. The one-inchpipe has a specification of 1-inch plus or minus 0.10 inch. What is the processcapability index (Cp) if the long-run process mean is 1 inch?arrow_forwardThe output of a certain integrated-circuit productionline is checked daily by inspecting a sample of 100 units.Over a long period of time, the process has maintaineda yield of 80 percent, that is, a proportion defective of 20 percent, and the variation of the proportion defec-tive from day to day is measured by a standard devi-ation of 0.04. If on a certain day the sample contains 38 defectives, find the mean of the posterior distribu-tion of as an estimate of that day’s proportion defec-tive. Assume that the prior distribution of Θ is a beta distribution.arrow_forward
- A metal fabricator produces connecting rods with an outer diameter that has a 1 ± .01–inch specification. A machine operator takes several sample measurements over time and determines the sample mean outer diameter to be 1.002 inches with a standard deviation of .003 inch.a. Calculate the process capability index for this example.b. What does this figure tell you about the process?arrow_forwardWith Six Sigma the goal is to reduce process variation to 10% of the design tolerance. True Falsearrow_forwardIn an acceptance sampling plan developed for lots containing 1,000 units, the sample size n is 85. The percent defec-tive of the incoming lots is 2%, and the probability of acceptance is 0.64. What is the average outgoing quality?arrow_forward
- A woodworker is concerned about the quality of the finished appearance of her work. She has finished a total of 50 unit split-willow hand-woven baskets. However, she has found the following number of finish defects in ten units sampled: 4,0,3,1,2,0,1,2,0,2. Calculate the average number of defects per basket. If 3-sigma control limits are used, calculate the lower control limit and upper control limit.arrow_forwardpoint on a control chart falls outside one of the controllimits, this suggests that the process variation is non random and should be investigated . a FALSE b TRUEarrow_forwardA new process is started, and the sum of the sample standard deviations for 25 subgroups of size 4 is 750. If the specifications are 700 +_ 80, what is the process capability index? What action would you recommend?arrow_forward
arrow_back_ios
SEE MORE QUESTIONS
arrow_forward_ios
Recommended textbooks for you
- Practical Management ScienceOperations ManagementISBN:9781337406659Author:WINSTON, Wayne L.Publisher:Cengage,Operations ManagementOperations ManagementISBN:9781259667473Author:William J StevensonPublisher:McGraw-Hill EducationOperations and Supply Chain Management (Mcgraw-hi...Operations ManagementISBN:9781259666100Author:F. Robert Jacobs, Richard B ChasePublisher:McGraw-Hill Education
- Purchasing and Supply Chain ManagementOperations ManagementISBN:9781285869681Author:Robert M. Monczka, Robert B. Handfield, Larry C. Giunipero, James L. PattersonPublisher:Cengage LearningProduction and Operations Analysis, Seventh Editi...Operations ManagementISBN:9781478623069Author:Steven Nahmias, Tava Lennon OlsenPublisher:Waveland Press, Inc.
Practical Management Science
Operations Management
ISBN:9781337406659
Author:WINSTON, Wayne L.
Publisher:Cengage,
Operations Management
Operations Management
ISBN:9781259667473
Author:William J Stevenson
Publisher:McGraw-Hill Education
Operations and Supply Chain Management (Mcgraw-hi...
Operations Management
ISBN:9781259666100
Author:F. Robert Jacobs, Richard B Chase
Publisher:McGraw-Hill Education
Purchasing and Supply Chain Management
Operations Management
ISBN:9781285869681
Author:Robert M. Monczka, Robert B. Handfield, Larry C. Giunipero, James L. Patterson
Publisher:Cengage Learning
Production and Operations Analysis, Seventh Editi...
Operations Management
ISBN:9781478623069
Author:Steven Nahmias, Tava Lennon Olsen
Publisher:Waveland Press, Inc.