Question
Chapter 7, Problem 1CQ
Summary Introduction
To determine: The setup time of the process.
Expert Solution & Answer
Explanation of Solution
Correct option: (c)
Correct answer:
100 minutes.
Justification:
The amount of agent added to the vat determines the setup time of the process. The reaction time of 85 minutes does not depend on the volume present in the batch and so it will be the setup time. In addition to that, 15 minutes is required to perform the cleaning process and it is also not dependent on the amount added to the vat. Therefore, the total setup time would be:
The total setup time is 100 minutes.
Want to see more full solutions like this?
Subscribe now to access step-by-step solutions to millions of textbook problems written by subject matter experts!
Students have asked these similar questions
The Flip Chip Company manufactures nacho chips, potato chips, and related products. There has been a problem in the manufacture of nacho chips. The process begins with the mixing of water, corn and lime (called the MASA). A mixer can produce a batch of 300 lbs of MASA in 2 minutes. The MASA is then cooked. This takes 30 minutes. Only 95% of the MASA makes it to the ovens and of that only 75% is transferred to the next step. There are four ovens. The next step is chip making. The MASA is extruded into the chip itself and the chips are baked. There are 2 chip machines. A total of 950 chips/minute are produced (each chip weighs approximately .5oz). The yield from this process is 72%. The chips are then placed in 20 oz bags. This step takes 2 seconds for each bag.
Where is the bottleneck?
What recommendation would you make?
Consider the mixing process shown in the figure. A mixing chamber initially contains 4 liters of a clear liquid. Clear liquid flows into the chamber at a rate of 10 liters per minute. A dye solution having a concentration of 0.25 kilograms per liter is injected into the mixing chamber at a constant rate of liters per minute. When the mixing process is started, the well-stirred mixture is pumped from the chamber at a rate of 10 + r liters per minute.
(a) Develop a mathematical model for the mixing process. Let Q represent the amount of dye in kilograms in the mixture.
(dQ/dt)=?
(b) The objective is to obtain a dye concentration in the outflow mixture of 0.1 kilograms per liter. What injection rate r is required to achieve this equilibrium solution?
r = ?
Would this equilibrium value of r be different if the fluid in the chamber at time t=0 contained some dye? yes, no or maybe?
(c) Assume the mixing chamber contains 4 liters of clear liquid at time t. How many minutes will it take…
Blue Lotus is a bike shop located near a beach resort, which rents its bikes to
guests staying in the resort. When a customer requests to rent a bike and no
bikes are available (they are either with another customers or being cleaned for
rental), customer waits until a bike is available. Once a bike rented out to a
customer, the customer keeps it for an average of 1 day. Upon return, the bike is
cleaned and tuned-up, which takes half a day (0.5 day).
Suppose Blue Lotus has 7 bikes, and demand for bike rental is 4.1 per day. What
is the average amount of time a customer waits to receive a bike?
(Hint: From the perspective of customer waiting time, 0.5 day of cleaning time would
be part of the processing time" so, p = 1+0.5 =1.5 days. Assume CVa = CVp = 1 in
your calculations).
O 1.197 days
O2.134 days
O 0.761 days
O 5.380 days
Chapter 7 Solutions
OPERATIONS MANAGEMENT LL W/CONNECT CODE
Ch. 7 - Prob. 1CQCh. 7 - Prob. 2CQCh. 7 - Prob. 3CQCh. 7 - Prob. 4CQCh. 7 - Prob. 5CQCh. 7 - Prob. 6CQCh. 7 - Prob. 7CQCh. 7 - Prob. 8CQCh. 7 - Prob. 9CQCh. 7 - Prob. 10CQ
Ch. 7 - Prob. 11CQCh. 7 - Prob. 12CQCh. 7 - Prob. 13CQCh. 7 - Prob. 14CQCh. 7 - Prob. 1PACh. 7 - Prob. 2PACh. 7 - Prob. 3PACh. 7 - Prob. 4PACh. 7 - Prob. 5PACh. 7 - Sarahs Organic Soap Company makes four kinds of...Ch. 7 - Prob. 7PACh. 7 - Prob. 8PACh. 7 - Bruno Fruscalzo decided to set up a small...Ch. 7 - Prob. 10PACh. 7 - Prob. 11PACh. 7 - Prob. 1CCh. 7 - Prob. 2CCh. 7 - Prob. 3CCh. 7 - Prob. 4C
Knowledge Booster
Learn more about
Need a deep-dive on the concept behind this application? Look no further. Learn more about this topic, operations-management and related others by exploring similar questions and additional content below.Similar questions
- A rigid tank whose volume is 10 L contains 1 kg of water at 0.1 MPa pressure. The tank is now heated until the pressure is 20 MPa. Determine the amount of heat transfer for this process. Neglect kinetic and potential energy changes.arrow_forwardLet's work together to reunite the cards with their owners North Africa is a country with a population of 100 million citizens and all residing within 20 provinces. It is the government's responsibility to make sure that every citizen of the country has a valid form of identity. The country was using a "Bar- Coded ID Book" as a form of citizen's identification. Two years ago they replaced "Bar-Coded ID Book" by "Smart ID Card". Citizens owning a Bar- Coded ID Book can apply for a Smart ID Card at no cost, new applicants are also issued ID cards at no cost. About 50% of the population holds "Smart ID Cards". Transiting from bar-coded ID book to "Smart ID Card" has been a successful project. However, there is a lot of reported cases everyday where citizens are losing their ID Cards. A Smart ID card is a small card (similar size to a bank card) with a chip that can store information about the citizen, however due to its size and flexibility compared to bar-coded book there is a high…arrow_forwardA large tank contains 50 gallons of water in which 10 lbs of salt is dissolved. Water containing 2 lbs of salt per gallon flows into the tank at the rate of 5gal/min .The mixture is kept well-stirred and flows out of the tank at the rate of 3gal/min Find: a) The amount of salt in the tank after 60 minutes. b) The amount of water in the tank after 60 minutes.arrow_forward
- There is a 4 percent error rate at a specific point in a production process. If an inspector is placed at this point, all the defects can be detected and eliminated. The inspector would cost $9 per hour and could inspect units in the process at the current production rate of 46 per hour. If no inspector is hired and defects are allowed to pass this point, there is a cost of $10 per defective unit to correct the defects later on. Assume that the line will operate at the same rate (i.e., the current production rate) regardless of whether the inspector is hired or not. a. if the inspector is hired, what will be the inspection cost per unit? b. if an inspector is not hired, what will be the defective cost per unit? c. should an inspector be hired based on costs alone?arrow_forward. A small, privately owned Asian company is producing a private-label soft drink calledYoggo. A bottling line puts the soft drinks into plastic bottles and then packagesthe bottles into boxes holding 10 bottles each. The bottling line is comprised of thefollowing four steps: (1) the bottling machine takes 1 second to fill a bottle, (2) the lidmachine takes 3 seconds to cover the bottle with a lid, (3) a labeling machine takes3 seconds per bottle, and (4) the packaging machine takes 4 seconds to place a bottleinto a box. When a box has been filled with 10 bottles, a worker tending the packagingmachine removes the filled box and replaces it with an empty box. Assume that thetime for the worker to remove a filled box and replace it with an empty box is negligibleand hence does not affect the capacity of the line. Problem data are summarized in thefollowing table. a. Draw a process flow diagram of this process. b. What is the capacity (bottles/hour) at the resource “Apply a lid”? c. What…arrow_forwardDuring a plant start-up, the operators should go through the start up sequence quickly to reduce the downtime and increase the profitability of the plant. there should be as few operators as possible near the column to ensure that any major accidents will result in lower injuries and fatalities. the operators should fully depend on the automated start up sequence without any intervention to increase the smoothness of the start up. Othere should be as many operators as possible near the column to ensure that any operational emergencies can be safely and quickly managed.arrow_forward
- How many orders of magnitude larger is the difference between a process that operates in nanoseconds and one that operates in milliseconds?arrow_forwardWhy do you need to develop the mathematical model of a process you want to control?arrow_forwardThe following is an excerpt from a conversation between two sales clerks, Tracy Rawlin and Jeff Weimer. Both Tracy and Jeff are employed by Magnum Electronics, a locally owned and operated electronics retail store. Suggest appropriate control procedures that would have prevented or detected the theft of cash.arrow_forward
- Burger Doodle is a fast-food restaurant that processes an average of 700 food orders each day. The average cost of each order is $6.05. Four percent of the orders are incorrect, and only 8% of the defective orders can be corrected with additional food items at an average cost of $1.75. The remaining defective orders have to be thrown out.arrow_forwardA bicycle component manufacturer produces hubs for bike wheels. Two processes are possible for manufacturing, and the parameters of each process are as follows: Process 1 Process 2 35 parts/ hour 4 hours/ day 15 parts/hour 7 hours/day 20% 9% Production rate Daily production time Percent of parts rejeted based on visual inspection Assume that the daily demand for hubs allows all defect-free hubs to be sold. Additionally, tested or rejected hubs cannot be sold. Find the process that maximizes profit per day if each part is made from Php 200 worth of material and can be sold for Php 1,500. Both processes are fully automated, and variable overhead cost is charged at the rate of Php 2,000 per hour.arrow_forwardA fleet repair center resets its computerized diagnostic system after every 15 trucks to help ensure there are limited major downtimes from system failure. The reset takes 22 minutes on average with a CV of 0.3. Each trucks diagnosis takes 28 minutes on average with a CV of 1.75 not considering the resets. 1. What is the effective process time and its CV? 2. If the reset system is not used, failures will occur after 57 hours on average with an average repair time of 3 hours. The CV of repair time is 0.9. What is the effective process time and its CV? Is the maintenance system beneficial if it prevents breakdowns? Just consider effective processing time parameters. 3. The maintenance program costs $10,000 annually. The average profit per car from the diagnostic service is $75. Assume the service center operates 250 days per year, 10 hours per day. Is the maintenance program economically beneficial? What assumptions are needed?arrow_forward
arrow_back_ios
SEE MORE QUESTIONS
arrow_forward_ios
Recommended textbooks for you
- Practical Management ScienceOperations ManagementISBN:9781337406659Author:WINSTON, Wayne L.Publisher:Cengage,Operations ManagementOperations ManagementISBN:9781259667473Author:William J StevensonPublisher:McGraw-Hill EducationOperations and Supply Chain Management (Mcgraw-hi...Operations ManagementISBN:9781259666100Author:F. Robert Jacobs, Richard B ChasePublisher:McGraw-Hill Education
- Purchasing and Supply Chain ManagementOperations ManagementISBN:9781285869681Author:Robert M. Monczka, Robert B. Handfield, Larry C. Giunipero, James L. PattersonPublisher:Cengage LearningProduction and Operations Analysis, Seventh Editi...Operations ManagementISBN:9781478623069Author:Steven Nahmias, Tava Lennon OlsenPublisher:Waveland Press, Inc.
Practical Management Science
Operations Management
ISBN:9781337406659
Author:WINSTON, Wayne L.
Publisher:Cengage,
Operations Management
Operations Management
ISBN:9781259667473
Author:William J Stevenson
Publisher:McGraw-Hill Education
Operations and Supply Chain Management (Mcgraw-hi...
Operations Management
ISBN:9781259666100
Author:F. Robert Jacobs, Richard B Chase
Publisher:McGraw-Hill Education
Purchasing and Supply Chain Management
Operations Management
ISBN:9781285869681
Author:Robert M. Monczka, Robert B. Handfield, Larry C. Giunipero, James L. Patterson
Publisher:Cengage Learning
Production and Operations Analysis, Seventh Editi...
Operations Management
ISBN:9781478623069
Author:Steven Nahmias, Tava Lennon Olsen
Publisher:Waveland Press, Inc.