Chapter 7, Problem 26P
Consider the office renovation project data in Table 7.16. A“zero” time estimate means that the activity could take a very small amount of time and should be treated as a numeric zero in the analysis.
- Based on the critical path, find the probability of completing the office renovation project by 39 days.
- Find the date by which you would be 90 percent sure of completing the project.
Expert Solution & Answer
Want to see the full answer?
Check out a sample textbook solutionStudents have asked these similar questions
A solved PERT problem is detailed in the table below. The expected time and variance values and the critical activities are given in the table below. Answer the following questions by filling the blanks (WRITE YOUR ANSWERS TO 2 DECIMAL PLACES. DO NOT ROUND UP OR DOWN):
a. The expected project completion time for this problem is and the standard deviation is .
b. There is a 0.95 probability that the project will be completed by weeks.
Activity
Expected time
Variance
Critical?
A
10
0.36
Yes
B
7
0.11
No
C
7
0.25
No
D
3
0.48
Yes
E
5
1.60
Yes
F
7
0.69
No
G
2
3.69
Yes
Consider the office renovation project data in Table 7.16. A“zero” time estimate means that the activity could take a verysmall amount of time and should be treated as a numericzero in the analysis.a. Based on the critical path, find the probability ofcompleting the office renovation project by 39 days.b. Find the date by which you would be 90 percent sure ofcompleting the project.
Given the following network and activity time estimates, determine:
The expected time and variance for each activity
The critical path. This must be based on your calculations of the start and finish times and not by inspection.
The expected project completion time, variance and standard deviation
The probability that the project will be completed in 20 weeks or less
Chapter 7 Solutions
Operations Management: Processes and Supply Chains, Student Value Edition Plus MyLab Operations Management with Pearson eText -- Access Card Package (11th Edition)
Ch. 7 - One of your colleagues comments that software is...Ch. 7 - Explain how to determine the slack for each...Ch. 7 - Define risk as it applies to projects. What are...Ch. 7 - Consider the following data for a project to...Ch. 7 - The following information is known about a project...Ch. 7 - A project for improving a billing process has the...Ch. 7 - Prob. 4PCh. 7 - Prob. 5PCh. 7 - Prob. 6PCh. 7 - Prob. 7P
Ch. 7 - Prob. 8PCh. 7 - Prob. 9PCh. 7 - The following information concerns a project to...Ch. 7 - Consider a project to produce custom door moldings...Ch. 7 - Table 7.5 contains information about au...Ch. 7 - The Advanced Tech Company has a project to design...Ch. 7 - Prob. 14PCh. 7 - Prob. 15PCh. 7 - Prob. 16PCh. 7 - Prob. 17PCh. 7 - Prob. 18PCh. 7 - Prob. 19PCh. 7 - Prob. 20PCh. 7 - Recently, you were assigned to manage a project to...Ch. 7 - In Solved Problem 2, estimate the probability that...Ch. 7 - The director of continuing education at Bluebird...Ch. 7 - Gabrielle Kramer, owner of Pet Paradise, is...Ch. 7 - The project manager of Good Public Relations...Ch. 7 - Consider the office renovation project data in...Ch. 7 - Activity B and activity K are critical activities....Ch. 7 - Prob. 2AMECh. 7 - Prob. 3AMECh. 7 - Prob. 4AMECh. 7 - Prob. 5AMECh. 7 - Assess the four categories of a risk-management...Ch. 7 - Prob. 2VCCh. 7 - Assume you are Denise Tower and have...Ch. 7 - Prob. 1CCh. 7 - Prob. 2CCh. 7 - Prob. 3CCh. 7 - Prob. 4C
Additional Business Textbook Solutions
Find more solutions based on key concepts
2. Identify four people who have contributed to the theory and techniques of operations management.
Operations Management: Sustainability and Supply Chain Management (12th Edition)
Many companies including Company OM tried to implement dynamic pricing in their ticketing system. The dynamic p...
Principles of Operations Management: Sustainability and Supply Chain Management (10th Edition)
There is a huge demand in the United States and elsewhere for affordable women’s clothing. Low-cost clothing re...
Loose-leaf for Operations Management (The Mcgraw-hill Series in Operations and Decision Sciences)
Feeding America Each year, the Feeding America network helps provide food to more than 46 million people facing...
Operations and Supply Chain Management 9th edition
What is precedent, and how does it affect common law?
Business in Action (8th Edition)
What is precedent, and how does it affect common law?
Business in Action
Knowledge Booster
Learn more about
Need a deep-dive on the concept behind this application? Look no further. Learn more about this topic, operations-management and related others by exploring similar questions and additional content below.Similar questions
- The following information has been computed from a project: Expected total project time = T = 62 weeks Project variance = 81 1- What is the probability that the project will be completed 18 weeks before its expected completion date? 2- Draw Normal Curve & Analysis your solution with conclusionarrow_forwardConsider the office renovation project data in Table 7.16. A “zero” time estimate means that the activity could take a very small amount of time and should be treated as a numeric zero in the analysis.a. Based on the critical path, find the probability of completing the office renovation project by 39 days.b. Find the date by which you would be 90 percent sure of completing the project.arrow_forwardWhy might a probabilistic estimate of a project’s completion time based solely on the variance of the critical path be misleading? Under what circumstances would it be acceptable?arrow_forward
- Consider the following PERT time estimates: a. Draw a network for this project and determine the critical path based on the most likely times by inspection.b. Assuming that the critical path is the one you identified in part (a), what is the probability that the project will be completed before 28weeks? Before 32 weeks?c. Assuming that the critical path is the one you identified in part (a), how many weeks are required to complete the project with probability .95?arrow_forwardA company is willing to develop their rocket before the end of current financial year which is now 28 weeks away. The chief engineer of the company has decided to use PERT technique in order to plan, schedule and control program of development for the data given in table below. What is the probability that the program will be completed by the end of the current financial year? (all durations are in weeks). (i) G) Optimum Duration Most likely duration Pesimistic duration 1 2 3 8 13 3 2 8 4 3 8 10 4 7 10 3 6. 3 8 4 9 10 4 8. 4 9. 5 7 9. 12 6. 5 11 7 9. 14 8 4. 00 2.arrow_forwardActivity E has an optimistic time of 9 days, a most likely time of 12 days, and a pessimistic time of 15 days. Estimate its expected time and standard deviation.arrow_forward
- A project being analyzed by PERT has 60 activities, 13 of which are on the critical path. If the estimated time along the critical path is 214 days with a project variance of 169, what is the probability that the project will be completed within 224 days? O 0.50 O 0.84 0.80 O 0.78arrow_forwardThe expected duration of a project is 26 weeks and the total project variance along the critical path is 11.555 Calculate the probability of completing the project in 25 weeks. Calculate the Z value which is used for finding the probability of completion of the project from the normal distribution table O a. + 0.0865 O b. + 0.2942 O C. - 0.0865 O d. - 0.2942arrow_forwardWhat is the value of the missing item labeled (a) in the table above? Round to the nearest integer. What is the value of the missing item labeled (b) in table above? Round to two decimals. Draw the network diagram for this project. Clearly label the earliest start, earliest finish, latest start, latest finish and slack for each activity. Specify the critical path and the critical activities. State the expected C.P. duration State the variance of the critical path. What is the probability that the dashboard will be delivered within 20 days?arrow_forward
- Following are the three time estimates for a task in a project: optimistic completion time = 2 weeks most likely completion time = 4 weeks pessimistic completion time = 7 weeks Compute the expected time for the task.arrow_forwardConsider the following project activities with a normal unit: (The normal unit is Day) Activity Name Immediate Predecessor (list number/ name, separated by ‘,’) Normal Time A 6 B A 2 C A 4 D B, C 3 E D 1 F D 7 G E 4 H F, G 2 I F 6 J I 1 K H, J 5 Fill the following table: Activity Name Activity Time Earliest Expected Competition Time (TE) Latest Expected Competition Time (TL) Slack (TL-TE) A 6 B 2 C 4 D 3 E 1 F 7 G 4 H 2 I 6 J 1 K 5 Project Completion Time = Days The Critical Path is=arrow_forwardA project consists of seven activities, lettered A through F below. For each activity, the estimated normal time in number of weeks, crash time, normal cost, crash cost, and its preceding activity are given. Normal Time Crash Time Normal Cost Crash Cost Immediate Activity (weeks) (weeks) (Peso) (Peso) Predecessor(s) A 4 3 2,000 2,600 2 1 2,200 2,800 3 500 500 D 8. 4 2,300 2,600 A E 6 3 900 1,200 F 3 2 3,000 4,200 G 4 2 1,400 2,000 D, E What is the maximum time that can be crashed? O Not in the choices Seven weeks Five weeks O Four weeks O Six weeksarrow_forward
arrow_back_ios
SEE MORE QUESTIONS
arrow_forward_ios
Recommended textbooks for you
- Practical Management ScienceOperations ManagementISBN:9781337406659Author:WINSTON, Wayne L.Publisher:Cengage,Operations ManagementOperations ManagementISBN:9781259667473Author:William J StevensonPublisher:McGraw-Hill EducationOperations and Supply Chain Management (Mcgraw-hi...Operations ManagementISBN:9781259666100Author:F. Robert Jacobs, Richard B ChasePublisher:McGraw-Hill Education
- Purchasing and Supply Chain ManagementOperations ManagementISBN:9781285869681Author:Robert M. Monczka, Robert B. Handfield, Larry C. Giunipero, James L. PattersonPublisher:Cengage LearningProduction and Operations Analysis, Seventh Editi...Operations ManagementISBN:9781478623069Author:Steven Nahmias, Tava Lennon OlsenPublisher:Waveland Press, Inc.
Practical Management Science
Operations Management
ISBN:9781337406659
Author:WINSTON, Wayne L.
Publisher:Cengage,
Operations Management
Operations Management
ISBN:9781259667473
Author:William J Stevenson
Publisher:McGraw-Hill Education
Operations and Supply Chain Management (Mcgraw-hi...
Operations Management
ISBN:9781259666100
Author:F. Robert Jacobs, Richard B Chase
Publisher:McGraw-Hill Education
Purchasing and Supply Chain Management
Operations Management
ISBN:9781285869681
Author:Robert M. Monczka, Robert B. Handfield, Larry C. Giunipero, James L. Patterson
Publisher:Cengage Learning
Production and Operations Analysis, Seventh Editi...
Operations Management
ISBN:9781478623069
Author:Steven Nahmias, Tava Lennon Olsen
Publisher:Waveland Press, Inc.
Inventory Management | Concepts, Examples and Solved Problems; Author: Dr. Bharatendra Rai;https://www.youtube.com/watch?v=2n9NLZTIlz8;License: Standard YouTube License, CC-BY