Chapter 7, Problem 5P
a)
Summary Introduction
To determine: The graph illustrating the crossover point.
Introduction:
Crossover point:
The crossover or the indifference point is the point at which the
b)
Summary Introduction
To determine: The number of units at which the choices have the same cost.
Expert Solution & Answer
Want to see the full answer?
Check out a sample textbook solutionStudents have asked these similar questions
Spartan Castings must implement a manufacturing process that reduces the amount of particulates emitted into the atmosphere. Two processes have been identified that provide the same level of particulate reduction. The first process is expected to incur $350,000 of fixed cost and add $50 of variable cost to each casting Spartan produces. The second process has fixed costs of $150,000 and adds $90 of variable cost per casting.a. What is the break-even quantity beyond which the first process is more attractive?b. What is the difference in total cost if the quantity produced is 10,000?
Tribal Systems, Inc., is opening a new plant and has yet todecide on the type of process to employ. A labor-intensiveprocess would cost $10,000 for tools and equipment and$14 for labor and materials per item produced. A more automated process costs $50,000 in plant and equipment buthas a labor/material cost of $8 per item produced. A fullyautomated process costs $300,000 for plant and equipmentand $2 per item produced. If process selection were basedsolely on lowest cost, for what range of production wouldeach process be chosen?
Two manufacturing processes are being considered for making a new product. Process A is less capital intensive, with fixed costs of $60,000 per year and variable costs of $700 per unit. Process B has fixed costs of $400,000 annually, with variable costs of $300 per unit.
What is the break-even quantity for the two processes? If annual sales are expected to be 700 units, which process should be selected?
Operations and Engineering have found a way to reduce the cost of Process B, such that the fixed costs for this process decrease from $400,000 to $300,000 annually. All other costs remain the same. Does this change the process selection for the annual sales volume of 700 units?
Chapter 7 Solutions
EBK OPERATIONS MGMT.
Ch. 7.S - Prob. 1DQCh. 7.S - Prob. 2DQCh. 7.S - Prob. 3DQCh. 7.S - How is actual, or expected, output computed?Ch. 7.S - Explain why doubling the capacity of a bottleneck...Ch. 7.S - Distinguish between bottleneck time and throughput...Ch. 7.S - Prob. 7DQCh. 7.S - Prob. 8DQCh. 7.S - Prob. 9DQCh. 7.S - Prob. 10DQ
Ch. 7.S - Explain how net present value is an appropriate...Ch. 7.S - Prob. 12DQCh. 7.S - What are the techniques available to operations...Ch. 7.S - Amy Xias plant was designed to produce 7,000...Ch. 7.S - For the past month, the plant in Problem S7.1,...Ch. 7.S - If a plant has an effective capacity of 6,500 and...Ch. 7.S - Prob. 4PCh. 7.S - Material delays have routinely limited production...Ch. 7.S - Prob. 6PCh. 7.S - Southeastern Oklahoma State Universitys business...Ch. 7.S - Under ideal conditions, a service bay at a Fast...Ch. 7.S - A production line at V. J. Sugumarans machine shop...Ch. 7.S - A work cell at Chris Ellis Commercial Laundry has...Ch. 7.S - The three-station work cell Illustrated in Figure...Ch. 7.S - The three-station work cell at Pullman Mfg., Inc....Ch. 7.S - The Pullman Mfg., Inc., three-station work cell...Ch. 7.S - Klassen Toy Company, Inc., assembles two parts...Ch. 7.S - Prob. 15PCh. 7.S - Prob. 16PCh. 7.S - Markland Manufacturing intends to increase...Ch. 7.S - Using the data in Problem S7.17. a. What is the...Ch. 7.S - Given the data in Problem S7.17, at what volume...Ch. 7.S - Janelle Heinke, the owner of HaPeppas!, is...Ch. 7.S - Prob. 21PCh. 7.S - Prob. 22PCh. 7.S - Prob. 23PCh. 7.S - Prob. 24PCh. 7.S - Prob. 25PCh. 7.S - As a prospective owner of a club known as the Red...Ch. 7.S - Prob. 27PCh. 7.S - James Lawsons Bed and Breakfast, in a small...Ch. 7.S - Prob. 33PCh. 7.S - Prob. 34PCh. 7.S - Prob. 35PCh. 7.S - What is the present value of 5,600 when the...Ch. 7.S - Prob. 37PCh. 7.S - Prob. 38PCh. 7.S - Bolds Gym, a health club chain, is considering...Ch. 7.S - Prob. 1VCCh. 7.S - Prob. 2VCCh. 7.S - Prob. 3VCCh. 7 - What is process strategy?Ch. 7 - Prob. 2DQCh. 7 - Prob. 3DQCh. 7 - What is process redesign?Ch. 7 - Prob. 5DQCh. 7 - Name the tour quadrants of the service process...Ch. 7 - Prob. 7DQCh. 7 - Prob. 8DQCh. 7 - Identify manufacturing firms that compete on each...Ch. 7 - Identify the competitive advantage of each of the...Ch. 7 - Prob. 11DQCh. 7 - Identify the competitive advantage of each of the...Ch. 7 - Prob. 13DQCh. 7 - Prob. 14DQCh. 7 - Prob. 15DQCh. 7 - Explain what a flexible manufacturing system (FMS)...Ch. 7 - Prob. 17DQCh. 7 - Prob. 18DQCh. 7 - Prob. 19DQCh. 7 - Prob. 1PCh. 7 - Prob. 2PCh. 7 - Prob. 3PCh. 7 - Prob. 4PCh. 7 - Prob. 5PCh. 7 - Ski Boards, Inc., wants to enter the market...Ch. 7 - Prob. 7PCh. 7 - Prob. 8PCh. 7 - Metters Cabinets, Inc., needs to choose a...Ch. 7 - Prob. 10PCh. 7 - Prob. 11PCh. 7 - Prob. 12PCh. 7 - Rochester Manufacturings Process Decision...Ch. 7 - Prob. 2CSCh. 7 - Prepare the case for an optimistic sales manager...Ch. 7 - Prob. 1.1VCCh. 7 - Prob. 1.2VCCh. 7 - Prob. 1.3VCCh. 7 - Prob. 1.4VCCh. 7 - Prob. 2.1VCCh. 7 - Prob. 2.2VCCh. 7 - Process Strategy at Wheeled Coach Video Case Video...Ch. 7 - Prob. 2.4VC
Knowledge Booster
Similar questions
- Two different manufacturing processes are being considered formaking a new product. The first process is less capital-intensive,with fixed costs of only $46,400 per year and variable costs of$720 per unit. The second process has fixed costs of $400,100but has variable costs of only $210 per unit.a. What is the break-even quantity, beyond which the sec-ond process becomes more attractive than the first?b. If the expected annual sale for the product is 840 units,which process would you choose?arrow_forwardTribal Systems, Inc., is opening a new plant and has yet todecide on the type of process to employ. A labor-intensiveprocess would cost $10,000 for tools and equipment and $14 for labor and materials per item produced. A more au-tomated process costs $50,000 in plant and equipment but has a labor/material cost of $8 per item produced. A fullyautomated process costs $300,000 for plant and equipmentand $2 per item produced. If process selection were basedsolely on lowest cost, for what range of production wouldeach process be chosen?arrow_forwardA small firm intends to increase the capacity of a bottleneck operation for producing a product by adding a new machine. Two alternatives, A and B, have been identified and the associated costs and revenues have been estimated. Annual fixed costs would be $30000 for A and $25,000 for B; variable costs per unit would be $10 for A and $12 for B; and the revenue per unit would be $25. i. Find the total cost functions for alternatives A and B, and the revenue function ii. Draw both the total cost functions and the revenue function in the same figure. iii. Find the break-even point for the alternatives A and B and show it in the figure iv. Is there any volume of output at which both the alternatives yield the same profit? If so, show it in the figure. If not, identify the volume of output at which the alternatives are indifferentarrow_forward
- Matthew Bailey, as manager of Designs by Bailey,is upgrading his CAD software. The high-performance (HP)software rents for $3,000 per month per workstation. Thestandard-performance (SP) software rents for $2,000 per monthper workstation. The productivity figures that he has availablesuggest that the HP software is faster for his kind of design.Therefore, with the HP software he will need five engineers and with the SP software he will need six. This translates into a vari-able cost of $200 per drawing for the HP system and $240 per drawing for the SP system. At his projected volume of 80 draw-ings per month, which system should he rent?arrow_forwardA firm plans to begin production of a new small appliance. The manager must decide whether to purchase the motors for the appliance from a vendor at $7 each or to produce them in-house. Either of two processes could be used for in-house production; one would have an annual fixed cost of $160,000 and a variable cost of $5 per unit, and the other would have an annual fixed costof $190,000 and a variable cost of $4 per unit. Determine the range of annual volume for which each of the alternatives would be best.arrow_forwardMop and Broom Manufacturing is evaluating whetherto produce a new type of mop. Th e company is consideringthe operations requirements for the mop as well as the marketpotential. Estimates of fi xed costs per year are $40,000, and thevariable cost for each mop produced is $20.(a) If the company sells the product at a price of $25, howmany units of product have to be sold in order to breakeven? Use both the algebraic and graphical approaches.(b) If the company sells 10,000 mops at the product price of$25, what will be the contribution to profi t?arrow_forward
- Matthew Bailey, as manager of Designs by Bailey,is upgrading his CAD software. The high-performance (HP)software rents for $3,000 per month per workstation. Thestandard-performance (SP) software rents for $2,000 permonth per workstation. The productivity figures that he hasavailable suggest that the HP software is faster for his kind ofdesign. Therefore, with the HP software he will need five engineers and with the SP software he will need six. This translatesinto a variable cost of $200 per drawing for the HP system and$240 per drawing for the SP system. At his projected volumeof 80 drawings per month, which system should he rent?arrow_forwardA manager is trying to decide whether to purchase a certain part or to have it produced internally.Internal production could use either of two processes. One would entail a variable cost of $17 perunit and an annual fixed cost of $200,000; the other would entail a variable cost of $14 per unitand an annual fixed cost of $240,000. Three vendors are willing to provide the part. Vendor A hasa price of $20 per unit for any volume up to 30,000 units. Vendor B has a price of $22 per unit for demand of 1,000 units or less, and $18 per unit for larger quantities. Vendor C offers a price of$21 per unit for the first 1,000 units, and $19 per unit for additional units.a. If the manager anticipates an annual volume of 10,000 units, which alternative would be bestfrom a cost standpoint? For 20,000 units, which alternative would be best?arrow_forwardWalton, Inc. is unsure whether to sell its product assembled or unassembled. The unit cost of the unassembled product is $32, while the cost of assembling each unit is estimated at $34. Unassembled units can be sold for $110, while assembled units could be sold for $142 per unit. What decision should Walton make?arrow_forward
- The Sail-Sea is a boat manufacturer. The assembly location is available for production of 60 boats for240 minutes per day. Given the information in the table,a) Draw the precedence diagramb) Fins the minimum number of workstations needed to produce the required daily demand.c) What is the efficiency of the assembly lined) What is the idle time per boat producede) Assign the tasks to workstations using the most follower methodf) What is the maximum theoretical capacity this line can achieve in 240 minutesarrow_forwardtwo different manufacturing processes are being considered for making a new product. the first process is less capital intensive, with fixed costs of only $50,000 per year and variable costs of $700 per unit. the second process has fixed costs of $400,00 but has variable costs of only $200 per unit a. what is the break even quantity beyond which the second process becomes more attractive than the first? b. if the expected annual sales for the product is 800 units, which process would you choose?arrow_forwardIn the following operations, isolate a system for analysis and define customers, services produced, suppliers, and the primary process flows. a. A college b. A fast-food restaurant c. A library Please select one to discuss.arrow_forward
arrow_back_ios
SEE MORE QUESTIONS
arrow_forward_ios
Recommended textbooks for you
- Practical Management ScienceOperations ManagementISBN:9781337406659Author:WINSTON, Wayne L.Publisher:Cengage,
Practical Management Science
Operations Management
ISBN:9781337406659
Author:WINSTON, Wayne L.
Publisher:Cengage,