Chapter 7, Problem 9P

a)

Summary Introduction

To determine: The standard time for the operation.

Introduction: The amount of the dependency on human effort by an organization in terms of achieving its goals is given by the work design. It is directly linked to the productivity of an organization where good work design helps in achieving high productivity.

a)

Expert Solution
Check Mark

Answer to Problem 9P

The standard time for the operation is 5.80 minutes.

Explanation of Solution

Given information:

Performance ratingObservations (minutes per cycles)Allowance
1 2 3 4 5
0.9 1.4 1.42 1.39 1.38 1.41 0.10
1.2 2.1 2.05 2 1.85 1.8 0.10
1.11 1.6 1.4 1.5 1.45 1.55 0.10

Formula:

Standardtime=Normaltime×Allowancefactor=NT×AFNT=Observedtime×PerformanceRatingAFjob=1+A

ElementPerformance ratingObservations (minutes per cycles)AllowanceObserved timeNormal timeAfjobStandard time
1 2 3 4 5
A 0.9 1.4 1.42 1.39 1.38 1.4 0.10 1.4 1.26 1.10 1.39
B 1.2 2.1 2.05 2 1.85 1.8 0.10 1.96 2.352 1.10 2.59
C 1.11 1.6 1.4 1.5 1.45 1.6 0.10 1.5 1.665 1.10 1.83
Standard time for operation 5.80

Calculation of standard time of operation:

Excel Worksheet:

OPERATIONS MANAGEMENT (LL) >CUSTOM<, Chapter 7, Problem 9P , additional homework tip  1

Element A:

Normal time is calculated by multiplying observed timing, 1.4 and performance rating, 0.9 which yields 1.26 minutes.

Allowance factor is calculated by adding 1 with the allowance factor 0.10 to give 1.10.

ST=NT×AFjob=1.26minutes×1.10=1.39minutes

Standard time for element A is calculated by multiplying normal time of 1.26 minutes with allowance factor of 1.10 which gives 1.39 minutes.

Same process applies for element B and C which yields the standard times as 2.59 and 1.83. The standard time for operation is obtained by adding 1.39, 2.59 and 1.83 minutes which gives 5.80 minutes.

Hence, the standard time for the operation is 5.80 minutes.

b)

Summary Introduction

To determine: The number of observations for element A

Introduction: The amount of the dependency on human effort by an organization in terms of achieving its goals is given by the work design. It is directly linked to the productivity of an organization where good work design helps in achieving high productivity.

b)

Expert Solution
Check Mark

Answer to Problem 9P

The number of observations for element A is 1.

Explanation of Solution

Given information:

Performance ratingObservations (minutes per cycles)Allowance
1 2 3 4 5
0.9 1.4 1.42 1.39 1.38 1.41 0.10
1.2 2.1 2.05 2 1.85 1.8 0.10
1.11 1.6 1.4 1.5 1.45 1.55 0.10

Confidence= 98%

4% of true value

Formula:

n=(zsax¯)2

z=Number ofnormalstandarddeviationsfordesiredconfidences=Samplestandarddeviationx¯=Sample meana=Desired accuracy

Calculation of number of observations for element A:

In the above formula the sample standard deviation is calculated by,

Calculation of standard deviation:

Element A Differences Square of differences Standard deviation
1.4 0 00.015811
1.42 0.02 0.0004
1.39 -0.01 0.0001
1.38 -0.02 0.0004
1.41 0.01 0.0001
Mean=1.4 SSQ=0.001

Excel worksheet:

OPERATIONS MANAGEMENT (LL) >CUSTOM<, Chapter 7, Problem 9P , additional homework tip  2

Z value for confidence interval of 98% is 2.33.

The confidence interval 0.982 gives 0.49, (z = 2.33).

Using z = 2.33:

n=(2.33×0.01580.04×1.40)2=0.4322

The number of observations from the standard z table for confidence level of 98% is calculated by dividing the product of 2.33 and 0.0158 with product of 0.04 and 1.40 and squaring the resultant which gives 0.4322. Rounding off the value it gives the number of observation as 1.

Hence, the number of observation is 1.

c)

Summary Introduction

To determine: The number of observations for element C.

Introduction: The amount of the dependency on human effort by an organization in terms of achieving its goals is given by the work design. It is directly linked to the productivity of an organization where good work design helps in achieving high productivity.

c)

Expert Solution
Check Mark

Answer to Problem 9P

The number of observations for element C is 2.

Explanation of Solution

Given information:

Performance ratingObservations (minutes per cycles)Allowance
1 2 3 4 5
0.9 1.4 1.42 1.39 1.38 1.41 0.10
1.2 2.1 2.05 2 1.85 1.8 0.10
1.11 1.6 1.4 1.5 1.45 1.55 0.10

Confidence= 90%

0.10 minute of actual value.

Formula:

n=(zse)2

z=Number ofnormalstandarddeviationsfordesiredconfidences=Samplestandarddeviatione=Maximumacceptableamountoftimeerror

Calculation of number of observations for element C:

In the above formula the sample standard deviation is calculated by,

Calculation of standard deviation:

Element C Differences Square of differences Standard deviation
1.6 0.1 0.010.0791
1.4 -0.1 0.01
1.5 0 0
1.45 -0.05 0.0025
1.55 0.05 0.0025
Mean=1.5 SSQ=0.025

Excel worksheet:

OPERATIONS MANAGEMENT (LL) >CUSTOM<, Chapter 7, Problem 9P , additional homework tip  3

Z value for confidence interval of 90% is 1.65.

The confidence interval 0.902 gives 0.45, which is in the midway of 0.4495 (z = 1.64) and 0.4505 (z = 1.65).

  • Using z = 1.64:

n=(1.64×0.07910.10)2=1.6828

The number of observations from the standard z table for confidence level of 90 is calculated by dividing the product of 1.64 and 0.0791 with 0.10 and squaring the resultant which gives 1.6828.

  • Using z = 1.65:

n=(1.65×0.07910.10)2=1.7034

The number of observations from the standard z table for confidence level of 90 is calculated by dividing the product of 1.65 and 0.0791 with 0.10 and squaring the resultant which gives 1.7034.

Hence, the number of observations for element C is 2

Want to see more full solutions like this?

Subscribe now to access step-by-step solutions to millions of textbook problems written by subject matter experts!
Students have asked these similar questions
Ergonomics problem A work measurement analyst in the Electrical Company took 10 observations (for each element) of an operation job. The operation consists of four elements of work. Result of observation was shown in a Table attached. a. Determine the standard time and standard output if the total allowance time is 12% b. Check whether number of observation is sufficient or not for a 95 percent confidence level and 5 percent significant level.
Based on a careful work study in the Hofstetter Corp., the results shown in the following table have been observed:                                                                                                                                    a) Compute the normal time for each work element.b) If the allowance for this type of work is 15%, what is the standard time?c) How many observations are needed for a 95% confidence level within ±5% accuracy?  (Hint: Calculate the sample size of each element.)
You recorded an observed time of 1 minute per unit of production. If the performance rating of the observed worker was 120 and 5% PNA was provided, what is the standard time per unit?

Chapter 7 Solutions

OPERATIONS MANAGEMENT (LL) >CUSTOM<

Knowledge Booster
Background pattern image
Operations Management
Learn more about
Need a deep-dive on the concept behind this application? Look no further. Learn more about this topic, operations-management and related others by exploring similar questions and additional content below.
Similar questions
SEE MORE QUESTIONS
Recommended textbooks for you
Text book image
Practical Management Science
Operations Management
ISBN:9781337406659
Author:WINSTON, Wayne L.
Publisher:Cengage,
Text book image
Operations Management
Operations Management
ISBN:9781259667473
Author:William J Stevenson
Publisher:McGraw-Hill Education
Text book image
Operations and Supply Chain Management (Mcgraw-hi...
Operations Management
ISBN:9781259666100
Author:F. Robert Jacobs, Richard B Chase
Publisher:McGraw-Hill Education
Text book image
Business in Action
Operations Management
ISBN:9780135198100
Author:BOVEE
Publisher:PEARSON CO
Text book image
Purchasing and Supply Chain Management
Operations Management
ISBN:9781285869681
Author:Robert M. Monczka, Robert B. Handfield, Larry C. Giunipero, James L. Patterson
Publisher:Cengage Learning
Text book image
Production and Operations Analysis, Seventh Editi...
Operations Management
ISBN:9781478623069
Author:Steven Nahmias, Tava Lennon Olsen
Publisher:Waveland Press, Inc.