Textbook Question
Chapter 7.S, Problem 18P
Using the data in Problem S7.17.
- a. What is the break-even point in dollars for proposal A 1f you add $10,000 installation to the fixed cost?
- b. What is the break-even point in dollars for proposal B if you add $10,000 installation to the fixed cost?
• S7.17 Markland Manufacturing intends to increase capacity by overcoming a bottleneck operation by adding new equipment. Two vendors have presented proposals. The fixed costs for proposal A are $50 000, and for proposal B, $70 000. The variable cost for A is $12 00, and for B, $10 00. The revenue generated by each unit is $20.00
- a. What is the break-even point in units for proposal A?
- b. What is the break-even point in units for proposal B?
Expert Solution & Answer
Want to see the full answer?
Check out a sample textbook solutionStudents have asked these similar questions
Complaints have come to the department manager regarding timeliness of requests for patient information and a decision must be made.
Three months ago, Community Hospital opened a 24-hour urgent-care center 10 miles away in a rapidly growing community. Kent Jones, the health information services manager, took part in the planning that included the use of a combined record and one patient identification number. The decision was made to allow electronic sharing of patient records between the facilities; however, at present it is necessary to fax some portions of the record upon request. In the past month, Kent has received four complaints from the urgent care center that records were not faxed in a timely manner.
There are 26 employees in health information services. Three full-time employees care for record activity during the day, with one employee devoted to record activity during the evening shift, when a team leader and four other employees are usually in the department. During the…
Complaints have come to the department manager regarding timeliness of requests for patient information and a decision must be made.
Three months ago, Community Hospital opened a 24-hour urgent-care center 10 miles away in a rapidly growing community. Kent Jones, the health information services manager, took part in the planning that included the use of a combined record and one patient identification number. The decision was made to allow electronic sharing of patient records between the facilities; however, at present it is necessary to fax some portions of the record upon request. In the past month, Kent has received four complaints from the urgent care center that records were not faxed in a timely manner.
There are 26 employees in health information services. Three full-time employees care for record activity during the day, with one employee devoted to record activity during the evening shift, when a team leader and four other employees are usually in the department. During the…
Entrepreneur Andrew Field bought a print shop and used his selling skills to boost sales to about $1 million annually. The high fixed cost structure of his business resulted in only a break-even situation, however, and Field saw no hope for improvement given his relatively small local markets.
The idea for a Web site finally struck. Field devised an interactive Web site system to fill his idle capacity. Customers design and submit their orders through a simple program. The company then e-mails a project number and link to a proof of the order, and once approved by the customer, a production, shipping, and delivery date are established.
Field filled his idle capacity and then took his company to the next level by soliciting more work and subcontracting that to competitor companies. Word of the ease and reliability of Fields system has spread, and the company now averages about 7,000 visitors to its site each day, generating sales of $8 to $9 million.
Q1. Would Fields strategy for…
Chapter 7 Solutions
OPERATIONS MGMT .WMYOMLAB><
Ch. 7.S - Prob. 1DQCh. 7.S - Prob. 2DQCh. 7.S - Prob. 3DQCh. 7.S - How is actual, or expected, output computed?Ch. 7.S - Explain why doubling the capacity of a bottleneck...Ch. 7.S - Distinguish between bottleneck time and throughput...Ch. 7.S - Prob. 7DQCh. 7.S - Prob. 8DQCh. 7.S - Prob. 9DQCh. 7.S - Prob. 10DQ
Ch. 7.S - Explain how net present value is an appropriate...Ch. 7.S - Prob. 12DQCh. 7.S - What are the techniques available to operations...Ch. 7.S - Amy Xias plant was designed to produce 7,000...Ch. 7.S - For the past month, the plant in Problem S7.1,...Ch. 7.S - If a plant has an effective capacity of 6,500 and...Ch. 7.S - Prob. 4PCh. 7.S - Material delays have routinely limited production...Ch. 7.S - Prob. 6PCh. 7.S - Southeastern Oklahoma State Universitys business...Ch. 7.S - Under ideal conditions, a service bay at a Fast...Ch. 7.S - A production line at V. J. Sugumarans machine shop...Ch. 7.S - A work cell at Chris Ellis Commercial Laundry has...Ch. 7.S - The three-station work cell Illustrated in Figure...Ch. 7.S - The three-station work cell at Pullman Mfg., Inc....Ch. 7.S - The Pullman Mfg., Inc., three-station work cell...Ch. 7.S - Klassen Toy Company, Inc., assembles two parts...Ch. 7.S - Prob. 15PCh. 7.S - Prob. 16PCh. 7.S - Markland Manufacturing intends to increase...Ch. 7.S - Using the data in Problem S7.17. a. What is the...Ch. 7.S - Given the data in Problem S7.17, at what volume...Ch. 7.S - Janelle Heinke, the owner of HaPeppas!, is...Ch. 7.S - Prob. 21PCh. 7.S - Prob. 22PCh. 7.S - Prob. 23PCh. 7.S - Prob. 24PCh. 7.S - Prob. 25PCh. 7.S - As a prospective owner of a club known as the Red...Ch. 7.S - Prob. 27PCh. 7.S - James Lawsons Bed and Breakfast, in a small...Ch. 7.S - Prob. 33PCh. 7.S - Prob. 34PCh. 7.S - Prob. 35PCh. 7.S - What is the present value of 5,600 when the...Ch. 7.S - Prob. 37PCh. 7.S - Prob. 38PCh. 7.S - Bolds Gym, a health club chain, is considering...Ch. 7.S - Prob. 1VCCh. 7.S - Prob. 2VCCh. 7.S - Prob. 3VCCh. 7 - What is process strategy?Ch. 7 - Prob. 2DQCh. 7 - Prob. 3DQCh. 7 - What is process redesign?Ch. 7 - Prob. 5DQCh. 7 - Name the tour quadrants of the service process...Ch. 7 - Prob. 7DQCh. 7 - Prob. 8DQCh. 7 - Identify manufacturing firms that compete on each...Ch. 7 - Identify the competitive advantage of each of the...Ch. 7 - Prob. 11DQCh. 7 - Identify the competitive advantage of each of the...Ch. 7 - Prob. 13DQCh. 7 - Prob. 14DQCh. 7 - Prob. 15DQCh. 7 - Explain what a flexible manufacturing system (FMS)...Ch. 7 - Prob. 17DQCh. 7 - Prob. 18DQCh. 7 - Prob. 19DQCh. 7 - Prob. 1PCh. 7 - Prob. 2PCh. 7 - Prob. 3PCh. 7 - Prob. 4PCh. 7 - Prob. 5PCh. 7 - Ski Boards, Inc., wants to enter the market...Ch. 7 - Prob. 7PCh. 7 - Prob. 8PCh. 7 - Metters Cabinets, Inc., needs to choose a...Ch. 7 - Prob. 10PCh. 7 - Prob. 11PCh. 7 - Prob. 12PCh. 7 - Rochester Manufacturings Process Decision...Ch. 7 - Prob. 2CSCh. 7 - Prepare the case for an optimistic sales manager...Ch. 7 - Prob. 1.1VCCh. 7 - Prob. 1.2VCCh. 7 - Prob. 1.3VCCh. 7 - Prob. 1.4VCCh. 7 - Prob. 2.1VCCh. 7 - Prob. 2.2VCCh. 7 - Process Strategy at Wheeled Coach Video Case Video...Ch. 7 - Prob. 2.4VC
Knowledge Booster
Learn more about
Need a deep-dive on the concept behind this application? Look no further. Learn more about this topic, operations-management and related others by exploring similar questions and additional content below.Similar questions
- How could the Facilities Manager have performed his task or integrated it as part of the strategic function of an FM Manager? What are some tactical projects that could have been initiated because of this complaint?arrow_forwardV what is feasibility Report ?Define when and why we need it And also define who prepare this document.arrow_forwardExplain with an example, A Service Project with a "Do-Nothing" Alternative?arrow_forward
- Wolfgang Kersten Mfg. intends to increase capacitythrough the addition of new equipment. Two vendors havepresented proposals. The fixed costs for proposal X are $150,000,and for proposal Y, Sl70,000. The variable cost for X is $120.00,and for Y, $100.00. The revenue generated by each unit is $200.00.a) What is the break-even point in units for proposal X?b) What is the break-even point in units for proposal Y?arrow_forwardIdentify a potential improvement in the sustainability design process, site design, water systems design, closing material loops with alternative products and services, and indoor environmental quality, commissioning, and supply chain considerations to recommend for Chipotle Mexican Grill. Be sure to clearly explain the reasoning for each improvement and what you will need to do to apply them (i.e. budget and schedule). Further identify potential trade-offs, concerns, or risks that may be associated with these decisions (i.e. technology not ready, cost, timing, internal conflict, lacking commitment, etc.). Include specific suppliers of materials or services that may fit potential needs.arrow_forwardLWT’s new business model will required product customization as well as changes in Customer Service. Explain the three dimensions on which LWT’s services will be impacted: service package, degree of customization, and the level of customer contact, (What will be the changes).arrow_forward
- The AJAX Company is considering implementing anew accounting system, which will automate salesprocessing, cash receipts, accounts payable, andcash disbursement procedures. Roger Moore,AJAX’s CIO sent an announcement letter to theAJAX community. In the letter, Moore said: “Ihave contracted with Spartan Consulting Group todo the needs analysis, system selection, and designwork. The programming and implementation willbe performed in-house using existing IT departmentstaff. The development process will be unobtrusive touser departments because Spartan knows what needsto be done. They will work independently, in thebackground, and will not disrupt departmental andinternal audit work flow with time-consuming interviews,surveys, and questionnaires. This promises tobe an efficient process that will produce a systemthat will be appreciated by all users.”RequiredDraft a memo from George Jones, Director of InternalAudits, in response to Moore’s letter.arrow_forwardProduct Name: SMARTPAK (Smart Backpack) Product Description: The SMARTPAK makes use of cutting-edge technology to give you several benefits. It is easier to use because it contains several space-saving features and useful functionality. In this section, we go through the product's physical, mechanical, and chemical qualities, as well as how it may be used as a consumer commodity and an industry input. Task: (estimate, assume, anything will do); this is just a proposal. Plant Size and Production Schedule: Indicate minimum and maximum rated capacity of production. The number of shifts perday, the number of operating days per yeararrow_forwardTitanic Cruise Company plans on releasing it’s new “Superliner” cruise ship in time forthe peak Spring cruise season. The Superliner is the largest and most expensive cruiseship ever built. The ship will be longer than 4 football fields. The ship has amenities thatwere never possible before on a commercial cruise ship. Features include rock climbingwalls, skydiving simulators, an open air “atrium” version of Central Park, and nearly twodozen specialty restaurants.Sinbad the Sailor, the President and CEO of Titanic, wants to figure out which itinerary forthe ship’s 17 day maiden voyage will be most profitable. He began by selecting a list ofports for the ship’s maiden voyage. He then projected 358,000 dollars daily onboardrevenue for each port based on the maximum passenger capacity. In addition, heprojected daily shore excursion revenue for different ports. Finally, he projected all of thedaily expenses for each port including docking fees, local taxes, fuel costs, labor costs,and…arrow_forward
- Explain the difference between the service projects and revenue projects ?arrow_forwardProject Risk Analysis Sydney, Australia’s M5 East Tunnel was constructed under strict budgetary and schedule requirements, but given the massive traffic delays now hampering commuters, the requirements may have been excessive. Due to an inexpensive computer system with a high failure rate, the tunnel’s security cameras frequently fail, requiring the operators to close the tunnel due to inability to react to an accident, fire, or excessive pollution inside the tunnel. The tunnel was built to handle 70,000 vehicles a day, but it now carries 100,000, so any glitch can cause immediate traffic snarls. A managerial risk analysis, including the risk of overuse, might have anticipated these problems and mandated a more reliable set of computers once the costs of failure had been included. Required: As the project manager, discuss the risk management process you think might have identified the danger in using a cheap computer system Discuss the type of risk analysis approach you think would…arrow_forwardQ You have been asked to select between three projects. Project A has a netpresent value of $54,750 and will take six months to complete. Project B hasa net present value of $85,100 and will take two years to complete. ProjectC has a net present value of $15,000 and a benefit-cost ratio of 5:2. Whichproject should you choose?A. Project AB. Project BC. Project CD. There is not enough information to decide Q Which of the following is a defect?A. A mistake made by a team member on the jobB. A change that the team needs to make in how they do the workC. A project management plan that does not meet its requirementsD. A change request that’s been rejected by the change control boardarrow_forward
arrow_back_ios
SEE MORE QUESTIONS
arrow_forward_ios
Recommended textbooks for you
- Practical Management ScienceOperations ManagementISBN:9781337406659Author:WINSTON, Wayne L.Publisher:Cengage,Operations ManagementOperations ManagementISBN:9781259667473Author:William J StevensonPublisher:McGraw-Hill EducationOperations and Supply Chain Management (Mcgraw-hi...Operations ManagementISBN:9781259666100Author:F. Robert Jacobs, Richard B ChasePublisher:McGraw-Hill Education
- Purchasing and Supply Chain ManagementOperations ManagementISBN:9781285869681Author:Robert M. Monczka, Robert B. Handfield, Larry C. Giunipero, James L. PattersonPublisher:Cengage LearningProduction and Operations Analysis, Seventh Editi...Operations ManagementISBN:9781478623069Author:Steven Nahmias, Tava Lennon OlsenPublisher:Waveland Press, Inc.
Practical Management Science
Operations Management
ISBN:9781337406659
Author:WINSTON, Wayne L.
Publisher:Cengage,
Operations Management
Operations Management
ISBN:9781259667473
Author:William J Stevenson
Publisher:McGraw-Hill Education
Operations and Supply Chain Management (Mcgraw-hi...
Operations Management
ISBN:9781259666100
Author:F. Robert Jacobs, Richard B Chase
Publisher:McGraw-Hill Education
Purchasing and Supply Chain Management
Operations Management
ISBN:9781285869681
Author:Robert M. Monczka, Robert B. Handfield, Larry C. Giunipero, James L. Patterson
Publisher:Cengage Learning
Production and Operations Analysis, Seventh Editi...
Operations Management
ISBN:9781478623069
Author:Steven Nahmias, Tava Lennon Olsen
Publisher:Waveland Press, Inc.
Inventory Management | Concepts, Examples and Solved Problems; Author: Dr. Bharatendra Rai;https://www.youtube.com/watch?v=2n9NLZTIlz8;License: Standard YouTube License, CC-BY