a)
To determine: The number of days for first 10 installations.
Introduction: Learning curve is referred as the cost curve, experience curve, efficiency curve or productivity curve. The leaving curve gives information about the cost, efficiency, productivity and performance of an organization.
a)
Answer to Problem 3P
Explanation of Solution
Given information:
Formula:
Calculation of number of days for first 10 installations:
At 85% learning curve, and 10 unit number, the unit factor is 7.116 (using learning curve coefficient table)
The times for all 10 installations are calculated by multiplying first unit of 8 with the unit factor 7.116 which yields 56.93 days.
Hence, the number of days for first 10 installations is 56.93 days.
b)
To determine: The number of days for second 10 installations.
Introduction: Learning curve is referred as the cost curve, experience curve, efficiency curve or productivity curve. The leaving curve gives information about the cost, efficiency, productivity and performance of an organization.
b)
Answer to Problem 3P
Explanation of Solution
Given information:
Formula:
Calculation of number of days for second 10 installations:
To calculate the number of days for second 10 installations which is from 11 to 20, the numbers of days of installations for 1 to 20 have to be calculated and then it has to be subtracted from number of days of installations of 1 to 10.
Number of installation of first 20 units:
At 85% learning curve, and 20 unit number, the unit factor is 12.402 (using learning curve coefficient table)
The times for all 20 installations are calculated by multiplying first unit of 8 with the unit factor 12.402 which yields 99.22 days.
From the computed number of days, subtract the number of needed for first 10 installations,
Hence, the number of days for second 10 installations is 42.29 days.
c)
To determine: The number of days for last 10 installations.
Introduction: Learning curve is referred as the cost curve, experience curve, efficiency curve or productivity curve. The leaving curve gives information about the cost, efficiency, productivity and performance of an organization.
c)
Answer to Problem 3P
Explanation of Solution
Given information:
Formula:
Calculation of number of days for last 10 installations:
To calculate the number of days for last10 installations which is from 21 to 30, the numbers of days of installations for 1 to 30 have to be calculated and then it has to be subtracted from number of days of installations of 1 to 20.
Number of installation of first 30 units:
At 85% learning curve, and 30 unit number, the unit factor is 17.091 (using learning curve coefficient table)
The times for all 30 installations are calculated by multiplying first unit of 8 with the unit factor 17.091 which yields 136.73 days.
From the computed number of days, subtract the number of needed for first 20 installations,
Hence, the number of days for final 10 installations is 37.51 days.
Want to see more full solutions like this?
Chapter 7 Solutions
EBK OPERATIONS MANAGEMENT
- A contractor is preparing a bid to install swimming pools at a new housing addition. The estimated time to build the first pool is 35 hours. The contractor estimates an 85 percent learning rate. Without using the computer: a. How long do you estimate the time required to install the second pool? b. How long do you estimate the time required to install the fourth pool?arrow_forwardSuppose a manufacturer of copiers has concluded that a 70 percent learning curve applies to the time a beginning service technician takes to install copy machines. Use the Learning Curve Excel template to answer the following questions: If the time required to install the first copy machine is estimated to be five hours, what is an estimate of the time required by a new technician to install the second and third copiers? Round your answers to one decimal place. For x = 2 it takes hours For x = 3 it takes hours If the learning rate changes to 65 or 95 percent, what is an estimate of the time required by a new technician to install the second and third copiers? Round your answers to one decimal place. For x = 2 and a 65% LC, it takes hours For x = 3 and a 65% LC, it takes hours For x = 2 and a 95% LC, it takes hours For x = 3 and a 95% LC, it takes hoursarrow_forwardCompany, is beginning the production of a new product. Management believes that 500 labor hours will be required to complete the new unit. An 85 percent incremental unit-time learning curve model for direct labor hours is assumed to be valid. Assume the q = -0.2345. What is the total hours for 3 units?arrow_forward
- A contractor is preparing a bid to install swimming pools at a new housing addition. The estimated time to build the first pool is 38 hours. The contractor estimates an 80 percent learning rate. Using POM for Windows or OM Explorer, how long do you estimate the time required to install the sixth pool? The time required to install the sixth pool is enter your response herehours. (Enter your response rounded to two decimal places.) Part 2 What is your estimate of the total time for all six pools? The total time for all six pools is enter your response here hours. (Enter your response rounded to two decimal places.)arrow_forwardYou need to develop a labor time estimate for a customer order of 50 network installations. It is estimated that the first installation will require 75 labor hours and a learning curve of 85 percent is expected. a. How many labor hours are required for the 25th installation?b. How many labor hours are required to complete all 50 installations? c. If the average labor cost is $28 per hour, what is the total labor cost for installing all the networks?d. How many workers are needed to complete the job in a week? Assuming each worker works 8 hours per day 5 days per week. Show breakdown of workarrow_forwardAssume a learning curve following the power law. If you double the initial cost c(1) of aproduct, the cost of the 21st unit, c(21), will:a. stay the same.b. be reduced by 50 percent.c. be doubled.d. increase by a factor of ln(2).arrow_forward
- A contractor is preparing a bid to install swimming pools at a new housing addition. The estimated time to build the first pool is 21 hours. The contractor estimates a 90 percent learning rate. Part 2 a. How long do you estimate the time required to install the second pool? enter your response here hours. (Enter your response rounded to two decimal places.) Part 3 b. How long do you estimate the time required to install the fourth pool? enter your response here hours. (Enter your response rounded to two decimal places.)arrow_forwardThe personnel manager of Powerwest Inc. wants to estimate the direct and cumulative average direct labor hours for producing 30 locomotive train units during the next year. He estimates from past experience that the learning rate is 90 percent. The production department estimate that manufacturing the first unit will take 30,000 hours. Each employee averages 200 hours per month. The production rate forecast is as follows: Month Production Rate (units) Month Production Rate (units) January 2 July 2 February 3 August 4 March 2 September 3 April 4 October 3 May 3 November 1 June 2 December 1 Show/explain step by step, so I fully understand the process. How many direct hours are required to produce the 30th unit? How many total hours are needed to produce all 30 units? What is the maximum number of employees required next year? If the learning rate were to change to 0.85, what would be the impact on the total hours…arrow_forwardMaxera Corporation has designed a new video game controller. It took the company 52 minutes to produce the first unit. If the company uses a 75% learning rate for this task, how long should it take the company to produce the 6th unit? the 18th unit? the 30th unit? the first 6 units? the first 18 units? the first 30 units? the units 7th through 18th? the units 19th through 30th?arrow_forward
- The personnel manager of Powerwest Inc. want to estimate the direct and cumulative average direct labor hours for producing 30 locomotive train units during then next year. He estimates from past experience that the learning rate is 90 percent. The production department estimate that manufacturing the first unit will take 30,000 hours. Each employee average 200 hours per month. The production rate forecast is as follows: Month Production Rate (units) Month Production Rate (units) January 2 July 2 February 3 August 4 March 2 September 3 April 4 October 3 May 3 November 1 June 2 December 1 How many direct hours are required to produce the 30th unit? How many total hours are needed to produce all 30 units? What is the maximum number of employees required next year? If the learning rate were to change to 0.85, what would be the impact on the total hours and the number of employees needed to product 30 units?arrow_forwardUse learning curve theory to predict the number of repetitions (units) that will be neededfor a trainee to achieve a unit time of 6 minutes if the trainee took 10 minutes to do the firstunit and a learning curve of 90 percent is operative.a. Use the learning table.b. Use the log formula.arrow_forwardThe first unit of a job took 40 hours to complete. The work has a learning percentage of 88. The manager wants time estimates for units 2, 3, 4, and 5. Develop those time estimates.arrow_forward
- Practical Management ScienceOperations ManagementISBN:9781337406659Author:WINSTON, Wayne L.Publisher:Cengage,Operations ManagementOperations ManagementISBN:9781259667473Author:William J StevensonPublisher:McGraw-Hill EducationOperations and Supply Chain Management (Mcgraw-hi...Operations ManagementISBN:9781259666100Author:F. Robert Jacobs, Richard B ChasePublisher:McGraw-Hill Education
- Purchasing and Supply Chain ManagementOperations ManagementISBN:9781285869681Author:Robert M. Monczka, Robert B. Handfield, Larry C. Giunipero, James L. PattersonPublisher:Cengage LearningProduction and Operations Analysis, Seventh Editi...Operations ManagementISBN:9781478623069Author:Steven Nahmias, Tava Lennon OlsenPublisher:Waveland Press, Inc.