Question
Chapter 8, Problem 1FSC
a.
To determine
The net income under the percentage of completion and complete contract method to each year.
Given information:
Total assets are $5,000,000.
Total liabilities are $2,000,000.
b.
To determine
The amount of the total assets, total liability and total equity under the percentage of completion and complete contract method to each year.
c.
To determine
The profit margin under the percentage of completion and completed contract
d.
To determine
The debt ratio under the percentage of completion and completed contract method each year.
Expert Solution & Answer
Want to see the full answer?
Check out a sample textbook solutionStudents have asked these similar questions
When accounting for revenue over time for a long-term contract, the percentage of completion used to recognize revenue in the first year usually is determined by measuring:
A. Cost incurred in the 1st year, divided by estimated remaining cost to complete the project.
B. Cost incurred in the 1st year, divided by estimated total cost for the completed project.
C. Cost incurred in the 1st year, divided by estimated gross profit.
D. Cost incurred in the 1st year, divided by estimated total cost to be incurred in the remaining years of the project.
Widjaja Company is accounting for a long-term construction contract using the percentage-of-completion method. It is a 4-year contract that is currently in its second year. The latest estimates of total contract costs indicate that the contract will be completed at a profit to Widjaja Company.
Instructions
a. What theoretical justification is there for Widjaja Company's use of the percentage-of-completion method?
b. How would progress billings be accounted for? Include in your discussion the classification of progress billings in Widjaja Company financial statements.
c. How would the income recognized in the second year of the 4-year contract be determined using the cost-to-cost method of determining percentage of completion?
d. What would be the effect on earnings per share in the second year of the 4-year contract of using the percentage-of-completion method instead of the completed-contract method? Discuss.
4
In accounting for construction contracts using the percentage of completion method, the gross profit recognized during the year would be the estimated gross profit multiplied by the percentage of the costs incurred to date to the :
Group of answer choices
Total estimated cost
Total contract price
Total cost incurred to date
Unbilled portion of the contract price
Chapter 8 Solutions
Intermediate Accounting (2nd Edition)
Ch. 8 - What are the primary issues involved in revenue...Ch. 8 - What is the fundamental principle underlying the...Ch. 8 - What is the fundamental principle underlying the...Ch. 8 - Prob. 8.4QCh. 8 - Prob. 8.5QCh. 8 - How is a performance obligation defined?Ch. 8 - What are the two criteria to define a good or...Ch. 8 - Prob. 8.8QCh. 8 - What principles regarding timing and measurement...Ch. 8 - Prob. 8.10Q
Ch. 8 - What is variable consideration and what factors...Ch. 8 - Describe and contrast the two approaches used to...Ch. 8 - Prob. 8.13QCh. 8 - What factors should accountants consider to...Ch. 8 - Prob. 8.15QCh. 8 - How does a seller account for any consideration...Ch. 8 - Prob. 8.17QCh. 8 - What are the two exceptions to the general rule...Ch. 8 - What are the three criteria required to recognize...Ch. 8 - When an entity does not meet the three criteria...Ch. 8 - Prob. 8.21QCh. 8 - Prob. 8.22QCh. 8 - How does a firm estimate the degree completed...Ch. 8 - Can a firm record inventory out on consignment as...Ch. 8 - What method do agents in a transaction use to...Ch. 8 - Prob. 8.26QCh. 8 - What qualitative disclosures do the standards...Ch. 8 - All of the following are elements of a contract...Ch. 8 - Prob. 8.2MCCh. 8 - Telecom Co. enters into a two-year contract with a...Ch. 8 - The transaction price must reflect the time value...Ch. 8 - Prob. 8.5MCCh. 8 - When allocating the transaction price to separate...Ch. 8 - Which of the following indicators is not...Ch. 8 - During Yoar 1 Moriwothor Construction Company...Ch. 8 - All of the following are indicators that the...Ch. 8 - Prob. 8.10MCCh. 8 - Prob. 8.11MCCh. 8 - Identify a Contract with a Customer. Complete the...Ch. 8 - Prob. 8.2BECh. 8 - Identifying Performance Obligations. Perfect Party...Ch. 8 - Identifying Performance Obligations. Perfect Party...Ch. 8 - Estimating Variable Consideration. Gear Garage...Ch. 8 - Estimating Variable Consideration. Using the...Ch. 8 - Estimating Variable Consideration. Sellet...Ch. 8 - Estimating Variable Consideration. Seliet...Ch. 8 - Prob. 8.9BECh. 8 - Allocation of Transaction Price. Martin Software...Ch. 8 - Prob. 8.11BECh. 8 - Allocation of Transaction Price. Sycamore Sidewalk...Ch. 8 - Allocation of Transaction Price. Sycamore enters...Ch. 8 - Prob. 8.14BECh. 8 - Allocation of Transaction Price. Using the...Ch. 8 - When to Recognize Revenue. For each scenario...Ch. 8 - Prob. 8.17BECh. 8 - Prob. 8.18BECh. 8 - Percentage-of-Completion Method, Journal Entries....Ch. 8 - Prob. 8.20BECh. 8 - Sales with the Right of Return. Both incorporated...Ch. 8 - Sales with the Right of Return. Using the...Ch. 8 - Sales Returns. Historically, about 5% or the...Ch. 8 - Sales on Consignment. Hanna Lighting recertify...Ch. 8 - Determining Performance Obligations. Pagit Inc, a...Ch. 8 - Prob. 8.2ECh. 8 - Estimating Variable Consideration. King Rat Pest...Ch. 8 - Prob. 8.4ECh. 8 - Prob. 8.5ECh. 8 - Prob. 8.6ECh. 8 - Allocation of Variable Consideration. Green-Up Inc...Ch. 8 - Allocation of Variable Consideration. Green-Up Inc...Ch. 8 - Prob. 8.9ECh. 8 - Prob. 8.10ECh. 8 - Determination of When to Recognize Revenue. Far...Ch. 8 - Prob. 8.12ECh. 8 - Percentage-of-Completion Method. Gary Construction...Ch. 8 - Prob. 8.14ECh. 8 - Prob. 8.15ECh. 8 - Prob. 8.16ECh. 8 - Sales with the Right of Return. Webster Hall, Inc....Ch. 8 - Prob. 8.18ECh. 8 - Prob. 8.19ECh. 8 - Other Principal Agent Transactions, Net Revenue...Ch. 8 - Prob. 8.1PCh. 8 - Prob. 8.2PCh. 8 - Comprehensive Revenue Recognition Problem. Casale...Ch. 8 - Prob. 8.4PCh. 8 - Determining When to Recognize Revenue. Megrew...Ch. 8 - Prob. 8.6PCh. 8 - Prob. 8.7PCh. 8 - Prob. 8.8PCh. 8 - Percentage-of-Completion Method. R Wayne Computer...Ch. 8 - Prob. 8.10PCh. 8 - Prob. 8.11PCh. 8 - Sales on Consignment. Pablo Products. Ltd sells...Ch. 8 - Prob. 1JCCh. 8 - Prob. 1FSCCh. 8 - Prob. 1SSCCh. 8 - Basis for Conclusions Case 1: Control According to...
Knowledge Booster
Similar questions
- Assuming the requirements for recognizing revenue over time are met, the profit to be recognized in any year is based on the completion ratio of: incurred contract costs divided by estimated total contract costs. incurred contract costs multiplied by estimated total contract costs. estimated total contract costs divided by incurred contract costs. estimated total contract costs multiplied by incurred contract costs.arrow_forwardIn accounting for construction contracts using the percentage of completion method, the gross profit recognized during the year would be the estimated gross profit by the percentage of the costs incurred to date the: Total estimate cost Total cost incurred to date Unbilled portion of the contract price Total contract pricearrow_forwardThe total estimated cost isarrow_forward
- 1. Determine the amount of construction in progress that will be reported. 2. How much revenue is recognized as of the end of the first year?arrow_forwardCarla Vista Construction Company began operations on January 1, 2020. During the year, Carla Vista entered into a non-cancellable contract with Martinez Corp. to construct a manufacturing facility. At that time, Carla Vista estimated that it would take five years to complete the facility at a total cost of $4,505,000. The total contract price for construction of the facility is $6,003,000. During the year, Carla Vista incurred $1,075,000 in construction costs related to the project. The estimated cost to complete the contract is $4,300,000. Martinez Corp. was billed and paid 27% of the contract price. The billings are non-refundable. Prepare schedules to calculate the amount of gross profit to be recognized for the year ended December 31, 2020, and the amount to be shown as contract assets or liabilities at December 31, 2020, under the completed-contract method. (Do not leave any answer field blank. Enter O for amounts. Enter negative amounts using either a negative sign preceding the…arrow_forwardCrane Corporation uses the completed-contract method. At the end of the first year of a $9023000 contract, the following information is available: Costs to date: Estimated costs to complete Progress billings during the year Cash collected during the year $2021000 O $991000 O $247750 O $275000 O $0 6011000 1811000 1536000 In the first year, Crane should recognize gross profit of Crane Corporation uses the co information is available: Costs to date: Estimated costs to complete Progress billings during the y Cash collected during the yea In the first voor Crano should r Snipping Tool Screenshot copied t Select here to markarrow_forward
- Long-term Contracts Clorad Corp. contracts with a customer to construct a building. It appropriately determines that it has one performance obligation which is satisfied over time. Using the following information for Year 1, compute Clorad's (a) total estimated costs for the contract, (b) revenue to date, and (c) gross profit recognized. Year 1 (of 4-year project): Construction costs incurred during the year $174,000 Estimated costs to complete the contract 426,000 Partial billings to customers 100,000 Collections from customers 25,000 Total contract price 1,000,000 (a) Total estimated costs for the contract $ (b) Revenue to date $ (c) Gross profit recognized $arrow_forwardRice Corp. recognizes revenue over time to account for long-term contracts and has the following information for the first year of the contract: Contract price Total expected costs on contract Costs incurred in current year Costs incurred in previous years $500,000 A.) $100,000 B.) $500,000 C.) $60,000 D.) $75,000 400,000 60,000 What is the amount of revenue recognized in year 1?arrow_forwardDomesticarrow_forward
- Thrasher Construction Co. was contracted to construct a building for $1,045,000. The building is owned by the customer throughout the contract period. The contract provides for progress payments. Thrasher's accounting year ends 31 December. Work began under the contract on 1 July 20X5, and was completed on 30 September 20X7. Construction activities are summarized below by year: 20X5 Construction costs incurred during the year, $192,600; estimated costs to complete, $674,100; progress billings during the year, $163,500; and collections, $149,800. 20x6 Construction costs incurred during the year, $481,500; estimated costs to complete, $203,300; progress billing during the year, $409,100; and collections, $406,600. 20X7 Construction costs incurred during the year, $209,000. Because the contract was completed, the remaining balance was billed and later collected in full per the contract. Required: 1. Prepare Thrasher's journal entries to record these events. Assume that percentage of…arrow_forwardjituarrow_forwardIf the company records revenue over time, how much must be shown as currentasset in the balance sheet of MOC Construction Company as of December 31?A. 5,500,000 C. 250,000B. 500,000 D. 100,000arrow_forward
arrow_back_ios
SEE MORE QUESTIONS
arrow_forward_ios
Recommended textbooks for you
- Intermediate Accounting: Reporting And AnalysisAccountingISBN:9781337788281Author:James M. Wahlen, Jefferson P. Jones, Donald PagachPublisher:Cengage Learning
Intermediate Accounting: Reporting And Analysis
Accounting
ISBN:9781337788281
Author:James M. Wahlen, Jefferson P. Jones, Donald Pagach
Publisher:Cengage Learning