Project Management: The Managerial Process (Mcgraw-hill Series Operations and Decision Sciences)
Project Management: The Managerial Process (Mcgraw-hill Series Operations and Decision Sciences)
7th Edition
ISBN: 9781259666094
Author: Erik W. Larson, Clifford F. Gray
Publisher: McGraw-Hill Education
bartleby

Concept explainers

bartleby

Videos

Textbook Question
Book Icon
Chapter 8, Problem 8.1.1C

Jack and Jill Smith have just retired and want to build a small, basic cabin in the Blue Mountains of Vermont.

They have hired Daryl Hannah as the general contractor for the project. She has assembled a team of three

workers to complete the project: Tom. Dick, and Harry. Daryl has negotiated a cost-plus contract with the

Smiths whereby she will receive 15 percent beyond the cost of labor and materials.

Before they sign the contract the Smiths want an estimate of how much the project is likely to cost and how long it will take.

Darryl has estimated that the cost for materials, permits, etc., will total $40000. She wants to determine labor costs as well as how long the project will take. This is one of several projects Daryl is managing, and other than occasionally helping out, her role is strictly limited to supervising. She has devised the following master plan and assignments.

Note that D2ck is the only skilled plumber in the group while Harry is the only skilled electrician. Tom is a general carpenter and can assist them with their work. Dick and Harry each get paid $300 a day while Tom gets paid $200 per day.

Darryl has negotiated a 10 percent management reserve to deal with unexpected problems. Unused funds will be returned to the Smiths.

Chapter 8, Problem 8.1.1C, Jack and Jill Smith have just retired and want to build a small, basic cabin in the Blue Mountains

Prepare a short proposal for the Smiths that includes a Gantt chart with resources assigned, and cost estimates if the project starts on 8/1/16. Did resource limitations affect the final schedule? If so, how? What financial risks does this project face? What can the Smiths do to protect themselves against those risks?

Blurred answer
Students have asked these similar questions
A small technology consulting company, specializing in developing manufacturing software for the home construction industry, secured a large contract a year ago to develop a software for designing and manufacturing roof truss. The development contract was for two years, and the maintenance contract was for five years. As part of the contract, the client included a 0.8 percent penalty per month for each additional month beyond the development contract end date of the software development project. Project progress reports indicate that the software development project is about 60 percent complete, seems to be encountering various problems, and it is behind schedule. The consequence of this is that the company could potentially lose money if the 0.8 percent performance penalty is invoked. The managing partner, in charge of the project, was able to trace some of the problems to poor quality control, not enough experienced software engineers, and unnecessary testing of incomplete software…
Quorex is evaluating two mutually exclusive projects. Project A has a net investment of $50,000 and net cash flows over a six-year period of $13,000 per year (NOTE: that project requires a reinvestment with the same cost and cash flow for another six years). Project B has a net investment of $48,500, but its net cash flows of $8,740 per year will occur over a 12-year period. If Quorex has a cost of capital of 14% for these projects, which project, if either, should be chosen, and what is its NPV?
Nyoka, as the assigned R&D PM, assigned Gabrielle Walters a mini project under the larger R&D Project. This mini project needs to be completed in 12 months. After consulting with Nickalia, the assigned accountant for the project, it was agreed that the approved budget for this project should be 200,000 USD with a constant burnt rate (the same amount is spent every month). Three months later, Gabrielle would have spent 50,000 USD. Upon close review, she finds that only 15% of the work has been completed, Jason Keene, a Cost Portfolio Management expert is being asked to assist Gabrielle by calculating and interpreting thefollowing: i. The Schedule Variance (SV) and the Cost Variance (CV) ii. the Schedule Performance Index (SPI) and Cost Performance index (CPI)
Knowledge Booster
Background pattern image
Management
Learn more about
Need a deep-dive on the concept behind this application? Look no further. Learn more about this topic, management and related others by exploring similar questions and additional content below.
Similar questions
SEE MORE QUESTIONS
Recommended textbooks for you
Text book image
Understanding Business
Management
ISBN:9781259929434
Author:William Nickels
Publisher:McGraw-Hill Education
Text book image
Management (14th Edition)
Management
ISBN:9780134527604
Author:Stephen P. Robbins, Mary A. Coulter
Publisher:PEARSON
Text book image
Spreadsheet Modeling & Decision Analysis: A Pract...
Management
ISBN:9781305947412
Author:Cliff Ragsdale
Publisher:Cengage Learning
Text book image
Management Information Systems: Managing The Digi...
Management
ISBN:9780135191798
Author:Kenneth C. Laudon, Jane P. Laudon
Publisher:PEARSON
Text book image
Business Essentials (12th Edition) (What's New in...
Management
ISBN:9780134728391
Author:Ronald J. Ebert, Ricky W. Griffin
Publisher:PEARSON
Text book image
Fundamentals of Management (10th Edition)
Management
ISBN:9780134237473
Author:Stephen P. Robbins, Mary A. Coulter, David A. De Cenzo
Publisher:PEARSON
Inventory Management | Concepts, Examples and Solved Problems; Author: Dr. Bharatendra Rai;https://www.youtube.com/watch?v=2n9NLZTIlz8;License: Standard YouTube License, CC-BY