Estimating Variable Consideration. Gear Garage Inc. enters into a contract to provide services totaling $80,000. The contract includes a potential performance bonus based on when Gear Garage completes the services. Gear Garage estimates the following scenarios for completion. Determine the expected value of the bonus under each scenario. Ignore any constraints on variable consideration.
Probability | ||||
Complete within | Bonus | Scenario 1 | Scenario 2 | Scenario 3 |
3 days | $10,000 | 65% | 50% | 0% |
5 days | $ 6,000 | 10% | 40% | 90% |
8 days | $ 2,000 | 25% | 10% | 10% |
Expert Solution & Answer
Trending nowThis is a popular solution!
Students have asked these similar questions
Determining the Transaction Price for a Revenue Contract
A contractor enters into a revenue contract with a customer to build customized equipment for $180,000 with a performance bonus of $99,000 that will be paid based on how quickly the equipment is completed. The amount of the performance bonus decreases by 15% of the original bonus per week for every week beyond the agreed upon completion date. The contractor has had experiences with similar contracts and thus has the data to predict the timing of completion of the contract. Therefore, the contractor concludes that the expected value method is the best predictor of revenue. The contractor estimates that there is a 60% probability that the contract will be completed by the agreed-upon completion date, a 35% probability that it will be completed one week late, and a 5% probability that it will be completed two weeks late.
Complete the following table in order to determine the transaction price for revenue recognition for the…
Sandhill Construction enters into a contract witha customer to build a warehouse for $910000 on March 30, 2021 with a
performance bonus of $40000 if the building is completed by July 31, 2021. The bonus is reduced by $8000 each week that
completion is delayed. Sandhill commonly includes these completion bonuses in its contracts and, based on prior experience, estimates
the following completion outcomes:
Completed by
Probability
July 31, 2021
70%
August 7, 2021
20%
August 14, 2021
5%
August 21, 2021
5%
The transaction price for this transaction is
O $673400
O $946400
O $665400
O $910000
Oriole Construction enters into a contract with a customer to build a warehouse for $ 860000 on March 30, 2021 with a performance bonus of $ 60000 if the building is completed by July 31, 2021. The bonus is reduced by $ 12000 each week that completion is delayed. Oriole commonly includes these completion bonuses in its contracts and, based on prior experience, estimates the following completion outcomes:
Completed by
Probability
July 31, 2021
60%
August 7, 2021
30%
August 14, 2021
5%
August 21, 2021
5%
The transaction price for this transaction is
$ 913400
$ 557400
$ 860000
$ 569400
Chapter 8 Solutions
INTERMEDIATE ACCOUNTING
Ch. 8 - What are the primary issues involved in revenue...Ch. 8 - What is the fundamental principle underlying the...Ch. 8 - What is the fundamental principle underlying the...Ch. 8 - Prob. 8.4QCh. 8 - Prob. 8.5QCh. 8 - How is a performance obligation defined?Ch. 8 - What are the two criteria to define a good or...Ch. 8 - Prob. 8.8QCh. 8 - What principles regarding timing and measurement...Ch. 8 - Prob. 8.10Q
Ch. 8 - What is variable consideration and what factors...Ch. 8 - Describe and contrast the two approaches used to...Ch. 8 - Prob. 8.13QCh. 8 - What factors should accountants consider to...Ch. 8 - Prob. 8.15QCh. 8 - How does a seller account for any consideration...Ch. 8 - Prob. 8.17QCh. 8 - What are the two exceptions to the general rule...Ch. 8 - What are the three criteria required to recognize...Ch. 8 - When an entity does not meet the three criteria...Ch. 8 - Prob. 8.21QCh. 8 - Prob. 8.22QCh. 8 - How does a firm estimate the degree completed...Ch. 8 - Can a firm record inventory out on consignment as...Ch. 8 - What method do agents in a transaction use to...Ch. 8 - Prob. 8.26QCh. 8 - What qualitative disclosures do the standards...Ch. 8 - All of the following are elements of a contract...Ch. 8 - Prob. 8.2MCCh. 8 - Telecom Co. enters into a two-year contract with a...Ch. 8 - The transaction price must reflect the time value...Ch. 8 - Prob. 8.5MCCh. 8 - When allocating the transaction price to separate...Ch. 8 - Which of the following indicators is not...Ch. 8 - During Yoar 1 Moriwothor Construction Company...Ch. 8 - All of the following are indicators that the...Ch. 8 - Prob. 8.10MCCh. 8 - Prob. 8.11MCCh. 8 - Identify a Contract with a Customer. Complete the...Ch. 8 - Prob. 8.2BECh. 8 - Identifying Performance Obligations. Perfect Party...Ch. 8 - Identifying Performance Obligations. Perfect Party...Ch. 8 - Estimating Variable Consideration. Gear Garage...Ch. 8 - Estimating Variable Consideration. Using the...Ch. 8 - Estimating Variable Consideration. Sellet...Ch. 8 - Estimating Variable Consideration. Seliet...Ch. 8 - Prob. 8.9BECh. 8 - Allocation of Transaction Price. Martin Software...Ch. 8 - Prob. 8.11BECh. 8 - Allocation of Transaction Price. Sycamore Sidewalk...Ch. 8 - Allocation of Transaction Price. Sycamore enters...Ch. 8 - Prob. 8.14BECh. 8 - Allocation of Transaction Price. Using the...Ch. 8 - When to Recognize Revenue. For each scenario...Ch. 8 - Prob. 8.17BECh. 8 - Prob. 8.18BECh. 8 - Prob. 8.19BECh. 8 - Prob. 8.20BECh. 8 - Sales with the Right of Return. Both incorporated...Ch. 8 - Sales with the Right of Return. Using the...Ch. 8 - Sales Returns. Historically, about 5% or the...Ch. 8 - Sales on Consignment. Hanna Lighting recertify...Ch. 8 - Determining Performance Obligations. Pagit Inc, a...Ch. 8 - Prob. 8.2ECh. 8 - Estimating Variable Consideration. King Rat Pest...Ch. 8 - Prob. 8.4ECh. 8 - Prob. 8.5ECh. 8 - Prob. 8.6ECh. 8 - Allocation of Variable Consideration. Green-Up Inc...Ch. 8 - Allocation of Variable Consideration. Green-Up Inc...Ch. 8 - Prob. 8.9ECh. 8 - Prob. 8.10ECh. 8 - Determination of When to Recognize Revenue. Far...Ch. 8 - Prob. 8.12ECh. 8 - Prob. 8.13ECh. 8 - Prob. 8.14ECh. 8 - Prob. 8.15ECh. 8 - Prob. 8.16ECh. 8 - Prob. 8.17ECh. 8 - Prob. 8.18ECh. 8 - Prob. 8.19ECh. 8 - Other Principal Agent Transactions, Net Revenue...Ch. 8 - Prob. 8.1PCh. 8 - Prob. 8.2PCh. 8 - Comprehensive Revenue Recognition Problem. Casale...Ch. 8 - Prob. 8.4PCh. 8 - Determining When to Recognize Revenue. Megrew...Ch. 8 - Prob. 8.6PCh. 8 - Prob. 8.7PCh. 8 - Prob. 8.8PCh. 8 - Prob. 8.9PCh. 8 - Prob. 8.10PCh. 8 - Prob. 8.11PCh. 8 - Prob. 8.12PCh. 8 - Prob. 1JCCh. 8 - Prob. 1FSCCh. 8 - Prob. 2FSCCh. 8 - Prob. 1SSCCh. 8 - Prob. 1BCC
Knowledge Booster
Learn more about
Need a deep-dive on the concept behind this application? Look no further. Learn more about this topic, accounting and related others by exploring similar questions and additional content below.Similar questions
- Marle Construction enters into a contract with a customer to build a warehouse for $950,000 on March 31, 2021, with a performance bonus of $50,000 if the building is completed by July 31, 2021. The bonus is reduced by $10,000 each week that the completion is delayed. Marle commonly includes these completion bonuses in its contracts and based on prior experience, estimates the following completion outcomes: Completed by Probability July 31, 2021 65% August 7, 2021 25% August 14, 2021 5% August 21, 2021 5% Using the probability weighted method, what will total revenue be? Using the most likely method, what will total revenue be?arrow_forwardESTIMATING VARIABLE CONSIDERATION AJD BUILDERS CONSTRUCTION COMPANY ENTERS INTO A CONTRACT WITH A CUSTOMER TO BUILD A 50 KILOMETERS ROAD TO P100,000,000 WITH A PERFORMANCE BONUS OF P60,000,000 THAT WILL BE PAID BASED ON THE TIMING OF COMPLETION. THE AMOUNT OF THE PERFORMANCE BONUS DECREASES BY 10% PER WEEK FOR EVERY WEEK BEYOND THE AGREED-UPON COMPLETION DATE. THE CONTRACT REQUIREMENTS ARE SIMILAR TO CONTRACTS THAT AJD BUILDERS HAS PERFORMED PREVIOUSLY, AND MANAGEMENT BELIEVES THAT SUCH EXPERIENCE IS PREDICTIVE FOR THIS CONTRACT. MANAGEMENT ESTIMATES THAT THERE IS A 60% PROBABILITY THAT THE CONTRACT WILL BE COMPLETED BY THE AGREED UPON COMPLETION DATE, A 30% PROBABILITY THAT IT WILL BE COMPLETED ONE WEEK LATE, AND ONLY A 10% PROBABILITY THAT IT WILL BE COMPLETED TWO WEEKS LATE. REQUIRED: DETERMINE THE PROBABILITY-WEIGHTED AMOUNT FOR THE MANAGEMENT TO DETERMINE THE TRANSACTION PRICE.arrow_forwardMarle Construction enters into a contract with a customer to build a warehouse for $950,000 on March 30, 2018 with a performance bonus of $50,000 if the building is completed by July 31, 2018. The bonus is reduced by $10,000 each week that completion is delayed. Marle commonly includes these completion bonuses in its contracts and, based on prior experience, estimates the following completion outcomes: Completed by Probability July 31, 2018 65% August 7, 2018 25% August 14, 2018 5% August 21, 2018 5% Determine the amount of the transaction price.arrow_forward
- Use the following information for the next two questions: Bass Co. appropriately uses the cost-to-cost method in measuring construction contract with a customer. its progress on Information on this contract, which was completed in 20x3, is a shown below: 20x1 20x2 20x3 20,000,000 20,000,000 20,000,000 Transaction price Profit each year Costs incurred each year (200,000) 8,200,000 400,000 1,400,000 3,600,000 (AICPA - Adapted) 1. 10. How much are the contract costs incurred in 20x2? a. 5,800,000 b. 6,200,000 c. 6,600,000 d. 10,200,000 11. How much are the estimated additional costs to complete as of December 31, 20x2? a. 5,400,000 b. 6,800,000 c. 7,200,000 d. 8,600,000arrow_forwardA company enters into a contract with a customer to build a building, with a performance bonus of $33,500 if the building is completed by September 30, 2021. The bonus is reduced by $5,000 each week that completion is delayed. The company commonly includes these completion bonuses in its contracts and, based on prior experience, estimates the following completion outcomes: Completed by ProbabilitySeptember 30, 2021 70%October 7, 2021 15%October 14, 2021 10%October 21, 2021 5%The amount of revenue the company should recognize related to this bonus is $_______________.arrow_forwardEureka Co. started work on a P10M fixed price construction contract in 20x1. The performance obligation in the contract is satisfied overtime. Eureka Co. measures its progress based on professional survey of performance completed to date (i.e., an output method). The estimated total contract costs are P6M. Information on the contract is as follows: 20x1 20x2 Costs incurred per year 2,700,000 1,980,000 Progress on the contract 42% 80% The customer accepted all billings but defaulted in its payment in 20x2. Eureka Co. assessed, on December 31,20x2, that it cannot collect 4% of the total contract price. Requirement: Compute for the revenues, costs of construction and profits recognized in 20x1 and 20x2, repectively.arrow_forward
- Nvidia enters into a contract which pays $2,100/month for six months of services. In addition, there is a 70% chance the contract will pay an additional $3,500 and a 30% chance the contract will pay an additional $1,500, depending on the outcome of the contract. Assume Nvidia estimates variable consideration as the most likely amount. What is the amount of revenue Nvidia would recognize for the first month of the contract? Note: Do not round intermediate calculations. Round final answer to whole dollars. Multiple Choice $2,100 $2,450 ☐ $2,683arrow_forwardThe Naples Company uses the percentage-of-completion method and the cost-to-cost method for its long-term construction contracts. On one such contract, Naples expects total revenues of P260,000. During the first year, Naples incurred costs pf P50,000 and billed the customer P30,000 under the contract. At what net amount should Naples Construction in Progress for this contract be reported at the end of the first year? a. P 35,000 b. 65,000arrow_forward12. Beaver Co., a construction firm, enters into a contract to buila a dam for a customer. The contract price is total construction costs plus 20% thereof. However, the variable fee increases to 25% if the project is completed within three years. Beaver Co. incurs the following costs: 20x1 20x2 20x3 Costs incurred each year 10,500,000 14,300,000 6,000,000 Estimated costs to complete 19,500,000 6,200,000 In 20x1, it is not highly probable that the additional fee will be received. However, after a change in circumstances in 20x2, it is now highly probable that the additional fee will be received. Beaver Co. uses the percentage of completion method based on costs. How much profit is recognized in 20x3? a. 850,000 b. 980,000 c. 1,200,000 d. 1,500,000arrow_forward
- 17 Using the figure below, calculate the percentage of revenue to the lender based on the monthly construction draw schedule. The project assumes a discount rate of 10%, and is for a 25-acre tract of land outside Lexington, KY. Construction Sales Revenue Month Draw (Lot Sales) 01234567899 509,600 0 327,600 0 327,600 0 327,600 0 109,200 226,100 109,200 226,100 109,200 226,100 0 455,525 0 455,525 0 455,525 0 455,525 The % of revenue to the lender is O.137.4% 72.8% 131.2% 76.2%arrow_forwardThis problem has subparts that still need to be answered Assume Avaya contracted to provide a customer with Internet infrastructure for $2,350,000. The project began in 2024 and was completed in 2025. Data relating to the contract are summarized below: 2024 2025 Costs incurred during the year $ 328,000 $ 1,830,000 Estimated costs to complete as of 12/31 1,312,000 0 Billings during the year 436,000 1,690,000 Cash collections during the year 341,000 1,785,000 Required: Compute the amount of revenue and gross profit or loss to be recognized in 2024 and 2025, assuming Avaya recognizes revenue over time according to percentage of completion. Compute the amount of revenue and gross profit or loss to be recognized in 2024 and 2025, assuming this project does not qualify for revenue recognition over time. Prepare a partial balance sheet to show how the information related to this contract would be presented at the end of 2024, assuming Avaya recognizes revenue over time…arrow_forwardConstruction Contract: Graded Question #1: George Co. enters into a contract to build an apartment for Jungle Co. for a fixed fee of P20,000,000. At contract inception, George Co. assesses its performance obligations in the contract and concludes that it has a single performance obligation that is satisfied over time. George Co. determines that the measure of progress best depicts its performance in the contract is input method based on costs incurred. George estimates that the total contract costs would amount to P16,000,000 over the construction period. George incurs contract costs of P2,000,000 during the year. How much revenue is recognized for the year?arrow_forward
arrow_back_ios
SEE MORE QUESTIONS
arrow_forward_ios
Recommended textbooks for you
- AccountingAccountingISBN:9781337272094Author:WARREN, Carl S., Reeve, James M., Duchac, Jonathan E.Publisher:Cengage Learning,Accounting Information SystemsAccountingISBN:9781337619202Author:Hall, James A.Publisher:Cengage Learning,
- Horngren's Cost Accounting: A Managerial Emphasis...AccountingISBN:9780134475585Author:Srikant M. Datar, Madhav V. RajanPublisher:PEARSONIntermediate AccountingAccountingISBN:9781259722660Author:J. David Spiceland, Mark W. Nelson, Wayne M ThomasPublisher:McGraw-Hill EducationFinancial and Managerial AccountingAccountingISBN:9781259726705Author:John J Wild, Ken W. Shaw, Barbara Chiappetta Fundamental Accounting PrinciplesPublisher:McGraw-Hill Education
Accounting
Accounting
ISBN:9781337272094
Author:WARREN, Carl S., Reeve, James M., Duchac, Jonathan E.
Publisher:Cengage Learning,
Accounting Information Systems
Accounting
ISBN:9781337619202
Author:Hall, James A.
Publisher:Cengage Learning,
Horngren's Cost Accounting: A Managerial Emphasis...
Accounting
ISBN:9780134475585
Author:Srikant M. Datar, Madhav V. Rajan
Publisher:PEARSON
Intermediate Accounting
Accounting
ISBN:9781259722660
Author:J. David Spiceland, Mark W. Nelson, Wayne M Thomas
Publisher:McGraw-Hill Education
Financial and Managerial Accounting
Accounting
ISBN:9781259726705
Author:John J Wild, Ken W. Shaw, Barbara Chiappetta Fundamental Accounting Principles
Publisher:McGraw-Hill Education
Revenue recognition explained; Author: The Finance Storyteller;https://www.youtube.com/watch?v=816Q6pOaGv4;License: Standard Youtube License