EBK PRODUCTION AND OPERATIONS ANALYSIS
7th Edition
ISBN: 9781478628385
Author: Olsen
Publisher: WAVELAND PRESS (ECONTENT)
expand_more
expand_more
format_list_bulleted
Concept explainers
Question
Chapter 8.5, Problem 31P
Summary Introduction
Interpretation:MRP lot-sizing calculations consider safety stock also. Explain why it should or should not be done. Comment on the statement that “A
Concept Introduction:MRP calculates the lot-sizes on the basis of pre-estimated demand, lead time etc. Variations are all around us in the world. Safety stock is a considered ‘insurance’ against normal variations. This is built in all calculations except the EOQ calculations.
Expert Solution & Answer
Want to see the full answer?
Check out a sample textbook solutionStudents have asked these similar questions
What are the net requirements of each item in the MPS?
Item Net Requirements
X
A
B
C
D
E
F
G
Discuss the advantages and disadvantages of including safety stock in MRP lot-sizing calculations. Do
you think a production control manager would be reluctant to build to safety stock if he or she is
behind schedule?
Explain DRP and different ways to deal with uncertain demand.
Chapter 8 Solutions
EBK PRODUCTION AND OPERATIONS ANALYSIS
Ch. 8.1 - Prob. 1PCh. 8.1 - Prob. 2PCh. 8.1 - Prob. 3PCh. 8.1 - Prob. 4PCh. 8.1 - Prob. 5PCh. 8.1 - Prob. 6PCh. 8.1 - Prob. 7PCh. 8.1 - Prob. 8PCh. 8.1 - Prob. 9PCh. 8.2 - Prob. 10P
Ch. 8.2 - Prob. 11PCh. 8.2 - Prob. 12PCh. 8.2 - Prob. 13PCh. 8.2 - Prob. 14PCh. 8.2 - Prob. 15PCh. 8.2 - Prob. 16PCh. 8.2 - Prob. 17PCh. 8.2 - Prob. 18PCh. 8.2 - Prob. 19PCh. 8.2 - Prob. 20PCh. 8.2 - Prob. 21PCh. 8.2 - Prob. 22PCh. 8.3 - Prob. 23PCh. 8.3 - Prob. 24PCh. 8.3 - Prob. 25PCh. 8.4 - Prob. 26PCh. 8.4 - Prob. 27PCh. 8.4 - Prob. 28PCh. 8.4 - Prob. 29PCh. 8.5 - Prob. 30PCh. 8.5 - Prob. 31PCh. 8.5 - Prob. 32PCh. 8.5 - Prob. 33PCh. 8.5 - Prob. 34PCh. 8.6 - Prob. 35PCh. 8.6 - Prob. 36PCh. 8.6 - Prob. 37PCh. 8.6 - Prob. 38PCh. 8.6 - Prob. 39PCh. 8.6 - Prob. 40PCh. 8 - Prob. 41APCh. 8 - Prob. 42APCh. 8 - Prob. 43APCh. 8 - Prob. 44APCh. 8 - Prob. 45APCh. 8 - Prob. 46APCh. 8 - Prob. 48APCh. 8 - Prob. 49APCh. 8 - Prob. 50APCh. 8 - Prob. 51AP
Knowledge Booster
Learn more about
Need a deep-dive on the concept behind this application? Look no further. Learn more about this topic, operations-management and related others by exploring similar questions and additional content below.Similar questions
- Completely fill in the MRP matrices for items J, K, and L. Do not complete the matrix for M and be careful to watch lot size restrictions. Item J LLC 0 Lot Size L4L LT 3 1 2 3 4 5 6 7 8 9 Gross Requirements Scheduled Receipts Projected on Hand 100 Net Requirements Planned Order Receipts Planned Order Releases Item K LLC _ Lot Size Mult 200 LT 2 1 2 3 4 5 6 7 8 9 Gross Requirements Scheduled Receipts Projected on Hand 110 Net Requirements Planned…arrow_forwardThis question is based on the following information pertaining to material Pogi: Usage 50 – 100 lbs. per day Lead time 8 – 12 days Size of the order 600 lbs. No. of days in a year 340 What is the average stock level? A. 1,250 B. 1,200 C. 1,000 D. 9252. What is the maximum stock level? 2,500 2,000 1,400 1,2003. What is the minimum stock level? 450 800 850 1,000 4. What is the re-order level? 1,200 1,600 1,750 1,800arrow_forwardExplain the function of a firm which affects the MRP system ?arrow_forward
- Q7. The president of Rose Bowl Enterprises, Desmond Howard, projects the firms aggregate DEMAND requirements over the next 8 months as follows: These are the monthly DEMAND, not production. MONTH JAN FEB MAR APR MAY JUN JULY AUG DEMAND 1,400 1,600 1,800 1,800 2,200 2,200 1,800 1,800 PRODUCTION 1,600 from December INVENTORY 200 from Dec plus 200 His operations manager is considering a new plan, which begins in January with 200 units on hand. Stockout cost of lost sales is $100 per unit. Inventory holding cost is $20 per unit per month. Ignore any idle time costs. The plan is called plan A. Plan A: Vary the workforce level to execute a strategy that produces the quantity demanded in the prior month. The December demand was given as 1,600 units per month. Therefore, the production for JAN will be 1,600. However, only 1,400 are needed. Therefore, the extra 200 produced go into inventory and there is a holding cost for inventory. Also, per the above, you already have 200 units in inventory…arrow_forwardWhat does MRP stand for?arrow_forward11. Unik hotel has the available capacity of 500 deluxe rooms, and the margin for each room is $100. The Christmas season is coming and the hotel opens booking from customers and must decide on how many orders to commit to at this time. If the hotel has orders that exceed capacity, it must arrange to upgrade the room for guests, which results in a loss of $50 per room. 2. What is the overbooking level should the hotel accept if cancellations are normally distributed, with a mean of 20 per cent of the orders accepted and a coefficient of variation of 0.5? OA) 142 B) 158 O C) 161 OD) 173arrow_forward
- Pennington Cabinets is a manufacturer of several different lines of kitchen and bathroom cabinets that are sold through major home improvement retailers. Pennington built material requirement planning as follows: Current Jan Feb Mar 1200 1000 Gross requirements Scheduled receipts 800 Projected available balance Net requirements Planned order receipts 820 Planned order release Compute net requirements in Feb. Your Answer: Answerarrow_forwardFigure shows a partially completed MPS record for 2 inch pneumatic control valves. Suppose that you receive the following orders at right for the valves (shown in the order of their arrival). As they arrive, you must decide whether to accept or reject them. Which orders would you accept for shipment?Order Amount (Units) Week Requested1 15 22 30 53 25 34 75 7arrow_forwardThe partially completed inventory record for the rotor subassembly in the table below shows gross requirements, scheduled receipts, lead time, and current on hand inventory a. Complete the last three rows of the record for an FOQ of 160 units (Enter your responses as integers. A response of "0" is equivalent to being not applicable) Item: Rotor subassembly Gross requirements Scheduled: receipts Projected on hand i inventory Planned receipts 15 1 65 160 2 10 3 35 4 45 Lot Size: FOQ-160 units Lead Time: 2 weeks Week 5 80 6 80 N 7 50 8 80 399999arrow_forward
arrow_back_ios
SEE MORE QUESTIONS
arrow_forward_ios
Recommended textbooks for you
- Practical Management ScienceOperations ManagementISBN:9781337406659Author:WINSTON, Wayne L.Publisher:Cengage,Operations ManagementOperations ManagementISBN:9781259667473Author:William J StevensonPublisher:McGraw-Hill EducationOperations and Supply Chain Management (Mcgraw-hi...Operations ManagementISBN:9781259666100Author:F. Robert Jacobs, Richard B ChasePublisher:McGraw-Hill Education
- Purchasing and Supply Chain ManagementOperations ManagementISBN:9781285869681Author:Robert M. Monczka, Robert B. Handfield, Larry C. Giunipero, James L. PattersonPublisher:Cengage LearningProduction and Operations Analysis, Seventh Editi...Operations ManagementISBN:9781478623069Author:Steven Nahmias, Tava Lennon OlsenPublisher:Waveland Press, Inc.
Practical Management Science
Operations Management
ISBN:9781337406659
Author:WINSTON, Wayne L.
Publisher:Cengage,
Operations Management
Operations Management
ISBN:9781259667473
Author:William J Stevenson
Publisher:McGraw-Hill Education
Operations and Supply Chain Management (Mcgraw-hi...
Operations Management
ISBN:9781259666100
Author:F. Robert Jacobs, Richard B Chase
Publisher:McGraw-Hill Education
Purchasing and Supply Chain Management
Operations Management
ISBN:9781285869681
Author:Robert M. Monczka, Robert B. Handfield, Larry C. Giunipero, James L. Patterson
Publisher:Cengage Learning
Production and Operations Analysis, Seventh Editi...
Operations Management
ISBN:9781478623069
Author:Steven Nahmias, Tava Lennon Olsen
Publisher:Waveland Press, Inc.
Inventory Management | Concepts, Examples and Solved Problems; Author: Dr. Bharatendra Rai;https://www.youtube.com/watch?v=2n9NLZTIlz8;License: Standard YouTube License, CC-BY