Question
Chapter 9, Problem 11P
a)
Summary Introduction
To determine: The takt time.
Introduction: Process layout refers to the plan or graphical representation about the design of the floor of a plant. It helps the firm to improve the efficiency of the design and it would help to improve the location of the departments.
b)
Summary Introduction
To determine: The number of employees to be cross-trained for the cell.
c)
Summary Introduction
To determine: The operation which may warrant special consideration.
Expert Solution & Answer
Want to see the full answer?
Check out a sample textbook solutionStudents have asked these similar questions
Rock View Restaurant is a new fast-food restaurant chain. The Operations Manager has dividedits normal drive-through service process into the following tasks:
Tasks
Description
Task Time (In Seconds)
Predecessors
A
Take Order
25
None
B
Receive payment
20
A
C
Gather drinks
35
A
D
Gather Food
32
A
E
Put food etc. In bag
25
C,D
F
Give food to Customer
10
B,E
Currently, Rock View Restaurant has a single window with one person who takes the order,gather the food, collects the money and gives the food to the customer. This takes an average of147 seconds per customer so only 25.5 cars can be served. Rock View Restaurant wants toincrease its drive-through capacity to 60 cars per hour by forming a multi-window line.i. Using the LOT heuristic, assign the tasks to the windows to produce the desiredservice rate making sure that the precedence relationship is maintained.
Rock View Restaurant is a new fast-food restaurant chain. The Operations Manager has dividedits normal drive-through service process into the following tasks:
Tasks
Description
Task Time (In Seconds)
Predecessors
A
Take Order
25
None
B
Receive payment
20
A
C
Gather drinks
35
A
D
Gather Food
32
A
E
Put food etc. In bag
25
C,D
F
Give food to Customer
10
B,E
Currently, Rock View Restaurant has a single window with one person who takes the order,gather the food, collects the money and gives the food to the customer. This takes an average of147 seconds per customer so only 25.5 cars can be served. Rock View Restaurant wants toincrease its drive-through capacity to 60 cars per hour by forming a multi-window line.1. Calculate the efficiency of the newly design process.
Rock View Restaurant is a new fast-food restaurant chain. The Operations Manager has dividedits normal drive-through service process into the following tasks:
Tasks
Description
Task Time (In Seconds)
Predecessors
A
Take Order
25
None
B
Receive payment
20
A
C
Gather drinks
35
A
D
Gather Food
32
A
E
Put food etc. In bag
25
C,D
F
Give food to Customer
10
B,E
Currently, Rock View Restaurant has a single window with one person who takes the order,gather the food, collects the money and gives the food to the customer. This takes an average of147 seconds per customer so only 25.5 cars can be served. Rock View Restaurant wants toincrease its drive-through capacity to 60 cars per hour by forming a multi-window line.1. Calculate the cycle time in seconds.
Chapter 9 Solutions
Principles of Operations Management: Sustainability and Supply Chain Management (10th Edition)
Ch. 9 - Prob. 1EDCh. 9 - Prob. 1DQCh. 9 - Prob. 2DQCh. 9 - Prob. 3DQCh. 9 - Prob. 4DQCh. 9 - Prob. 5DQCh. 9 - Prob. 6DQCh. 9 - Prob. 7DQCh. 9 - Prob. 8DQCh. 9 - Prob. 9DQ
Ch. 9 - Prob. 10DQCh. 9 - Prob. 11DQCh. 9 - Prob. 12DQCh. 9 - Prob. 13DQCh. 9 - Prob. 14DQCh. 9 - Prob. 15DQCh. 9 - Prob. 16DQCh. 9 - Prob. 17DQCh. 9 - Prob. 18DQCh. 9 - Prob. 1PCh. 9 - Prob. 2PCh. 9 - Prob. 3PCh. 9 - Roy Creasey Enterprises, a machine shop, is...Ch. 9 - Adam Munson Manufacturing, in Gainesville,...Ch. 9 - Prob. 6PCh. 9 - Prob. 7PCh. 9 - Prob. 8PCh. 9 - Six processes are to be laid out in six areas...Ch. 9 - Prob. 11PCh. 9 - Stanford Rosenberg Computing wants to establish an...Ch. 9 - Illinois Furniture, Inc., produces all types of...Ch. 9 - Prob. 14PCh. 9 - The Action Toy Company has decided to manufacture...Ch. 9 - Prob. 16PCh. 9 - Prob. 17PCh. 9 - Prob. 18PCh. 9 - Prob. 19PCh. 9 - Prob. 20PCh. 9 - Prob. 21PCh. 9 - Prob. 22PCh. 9 - Prob. 23PCh. 9 - Prob. 1CSCh. 9 - Prob. 2CSCh. 9 - Henry Coupe, the manager of a metropolitan branch...Ch. 9 - Prob. 4CSCh. 9 - Prob. 1.1VCCh. 9 - Prob. 1.2VCCh. 9 - Prob. 1.3VCCh. 9 - Prob. 1.4VCCh. 9 - Prob. 1.5VCCh. 9 - Prob. 1.6VCCh. 9 - Prob. 2.1VCCh. 9 - Prob. 2.2VCCh. 9 - Prob. 2.3VC
Knowledge Booster
Similar questions
- Rock View Restaurant is a new fast-food restaurant chain. The Operations Manager has dividedits normal drive-through service process into the following tasks: Tasks Description Task Time (In Seconds) Predecessors A Take Order 25 None B Receive payment 20 A C Gather drinks 35 A D Gather Food 32 A E Put food etc. In bag 25 C,D F Give food to Customer 10 B,E Currently, Rock View Restaurant has a single window with one person who takes the order,gather the food, collects the money and gives the food to the customer. This takes an average of147 seconds per customer so only 25.5 cars can be served. Rock View Restaurant wants toincrease its drive-through capacity to 60 cars per hour by forming a multi-window line.1. Draw the precedence diagram to represent the process at Rock view restaurant.arrow_forwardA) Which step in this process is the bottleneck? =30 min for tan leather B) How many briefcases are processed at the bottleneck workstation per hour?=60/30=2 briefcases per hr C) What is the throughput time of the overall process?=30+15+10+10+10 Throughput = 75 minutes given the above information please answer qestions 1-3 below. If the manufacturing facility operates 8 hours per day, 250 days a year, what is the annual capacity of this manufacturing process. Assume the company decides to hire additional workers in order to duplicate the bottleneck step identified in part a so that there are 3 of these workstations instead of 1. Redraw the diagram showing the flow of the revised process. Answer parts a through d again based on the new process created in part e?arrow_forwardRock View Restaurant is a new fast-food restaurant chain. The Operations Manager has dividedits normal drive-through service process into the following tasks: Task Description Task time in seconds Predecessors A Take Order 25 none B Received Payment 20 A C Gather Drinks 35 A D Gather Food 32 A E Put food etc. in bag 25 C,D F Give food to customer 10 B,E Currently, Rock View Restaurant has a single window with one person who takes the order,gather the food, collects the money and gives the food to the customer. This takes an average of147 seconds per customer so only 25.5 cars can be served. Rock View Restaurant wants toincrease its drive-through capacity to 60 cars per hour by forming a multi-window line. Using the LOT heuristic, assign the tasks to the windows to produce the desiredservice rate making sure that the precedence relationship is maintained.Calculate the efficiency of the newly design process.arrow_forward
- Rock View Restaurant is a new fast-food restaurant chain. The Operations Manager has dividedits normal drive-through service process into the following tasks: Task Description Task time in seconds Predecessors A Take Order 25 none B Received Payment 20 A C Gather Drinks 35 A D Gather Food 32 A E Put food etc. in bag 25 C,D F Give food to customer 10 B,E Currently, Rock View Restaurant has a single window with one person who takes the order,gather the food, collects the money and gives the food to the customer. This takes an average of147 seconds per customer so only 25.5 cars can be served. Rock View Restaurant wants toincrease its drive-through capacity to 60 cars per hour by forming a multi-window line. i. Draw the precedence diagram to represent the process at Rock View Restaurant.ii. Calculate the cycle time in seconds.iii. Calculate the minimum number of windows that Rock View Restaurant will need toserve 60 cars per hour.arrow_forwardRock View Restaurant is a new fast food restaurant chain. The Operations Manager has dividedits normal drive-through service process into the following tasks:Tasks Description Task Time(InSeconds)PredecessorsA Take order 25 NoneB Receive payment 20 AC Gather drinks 35 AD Gather food 32 AE Put food etc. in bag 25 C,DF Give food to customer 10 B,E Currently, Rock View Restaurant has a single window with one person who takes the order, gather the food, collects the money and gives the food to the customer. This takes an average of 147 seconds per customer so only 25.5 cars can be served.…arrow_forwardRock View Restaurant is a new fast food restaurant chain. The Operations Manager has dividedits normal drive-through service process into the following tasks:Tasks Description Task Time(InSeconds)PredecessorsA Take order 25 NoneB Receive payment 20 AC Gather drinks 35 AD Gather food 32 AE Put food etc. in bag 25 C,DF Give food to customer 10 B,E Currently, Rock View Restaurant has a single window with one person who takes the order, gather the food, collects the money and gives the food to the customer. This takes an average of 147 seconds per customer so only 25.5 cars can be served.…arrow_forward
- Rock View Restaurant is a new fast food restaurant chain. The Operations Manager has divided its normal drive-through service process into the following tasks:Tasks Description Task Time(In Seconds)PredecessorsA Take order 25 NoneB Receive payment 20 AC Gather drinks 35 AD Gather food 32 AE Put food etc. in bag 25 C,DF Give food to customer10 B,ECurrently, Rock View Restaurant has a single window with one person who takes the order, gather the food, collects the money and gives the food to the customer. This takes an average of 147 seconds per customer so only 25.5 cars can be served. Rock View Restaurant wants to increase its drive-through capacity to 60 cars per hour by forming a multi-window line. Calculate the efficiency of the newly design process.arrow_forwardRock View Restaurant is a new fast food restaurant chain. The Operations Manager has divided its normal drive-through service process into the following tasks:Tasks Description Task Time(In Seconds)PredecessorsA Take order 25 NoneB Receive payment 20 AC Gather drinks 35 AD Gather food 32 AE Put food etc. in bag 25 C,DF Give food to customer10 B,ECurrently, Rock View Restaurant has a single window with one person who takes the order, gather the food, collects the money and gives the food to the customer. This takes an average of 147 seconds per customer so only 25.5 cars can be served. Rock View Restaurant wants to increase its drive-through capacity to 60 cars per hour by forming a multi-window line. Using the LOT heuristic, assign the tasks to the windows to produce the desired service rate making sure that the precedence relationship is maintained.v. Calculate the efficiency of the newly design processarrow_forwardThe Simple process has 4 steps. Step 1 & 3 has two resource units, while Step 2 and 3 only has one. The time it takes each resource unit to complete the step is also shown on the diagram. I need help understanding these and the steps that needs to be taken to answer these questions (i) What is the total capacity of the resource units in (units/hr) at each step? (ii) At which of the four steps is there a bottleneck resource pool? (iii) What is the overall process capacity? (iv) If 300 units/hr worth of raw materials flowed into the process, what would be thethroughput of the process?arrow_forward
- Suppose the times for the individual operations for the in-line skate assembly are as follows: Task Description Time (sec) 1 Assemble wheels, bearings, and axle hardware 11 2 Assemble brake housing and pad 8 3 Complete wheel assembly 20 4 Inspect wheel assembly 13 5 Assemble boot 18 6 Join boot and wheel subassemblies 7 7 Add line and final assembly 10 8 Perform final inspection 10 Consider the production line achieving an output rate of 180 per hour below. Using the proposed design, calculate the total time and idle time for each workstation. If your answer is zero, enter "0". Round your answers to the nearest whole number. Station Tasks Total Time, seconds Idle Time, seconds A 1 and 2 B 3 C 5 D 4 and 6 E 7 and 8 Total What is the assembly line efficiency? Round your answer to one decimal place. %arrow_forwardRocky’s Pre-Cast Shop is considering two different processes for completing Pre-Cast jobs. Process A uses one person to setup the job and do the pre-casting. If this approach is used, an experienced person can complete an average of 20 jobs per day. Process B uses two people. One person does the setup and the second person does the actual pre-casting. Setup on one job can be done while pre-casting is being completed on another but pre-casting must be completed on a job before the pre-cast machine can start processing the next. After some practice, this second process can be completed with a standard time of 10 minutes for setup and 15 minutes for actual pre-casting. In either case, assume an 8-hour day, 5 days per week, 250 days per year. 3. Assuming ideal conditions, what is the maximum capacity of process B? 4. How long would it take to process 200 jobs using process A (assume only one worker and one machine)? 5. If Rocky’s is primarily…arrow_forwardA dentist’s office has three steps to a routine visit: A receptionist enters the patient’s data A dental assistant takes x-rays of the patient A dentist performs a checkup on the patient If there are 2 receptionists at the office, 3 dental assistants, and 4 dentists, draw a process flow diagram for this office. Remember to account for the multiple resources at each stage.arrow_forward
arrow_back_ios
SEE MORE QUESTIONS
arrow_forward_ios
Recommended textbooks for you
- Practical Management ScienceOperations ManagementISBN:9781337406659Author:WINSTON, Wayne L.Publisher:Cengage,Operations ManagementOperations ManagementISBN:9781259667473Author:William J StevensonPublisher:McGraw-Hill EducationOperations and Supply Chain Management (Mcgraw-hi...Operations ManagementISBN:9781259666100Author:F. Robert Jacobs, Richard B ChasePublisher:McGraw-Hill Education
- Purchasing and Supply Chain ManagementOperations ManagementISBN:9781285869681Author:Robert M. Monczka, Robert B. Handfield, Larry C. Giunipero, James L. PattersonPublisher:Cengage LearningProduction and Operations Analysis, Seventh Editi...Operations ManagementISBN:9781478623069Author:Steven Nahmias, Tava Lennon OlsenPublisher:Waveland Press, Inc.
Practical Management Science
Operations Management
ISBN:9781337406659
Author:WINSTON, Wayne L.
Publisher:Cengage,
Operations Management
Operations Management
ISBN:9781259667473
Author:William J Stevenson
Publisher:McGraw-Hill Education
Operations and Supply Chain Management (Mcgraw-hi...
Operations Management
ISBN:9781259666100
Author:F. Robert Jacobs, Richard B Chase
Publisher:McGraw-Hill Education
Purchasing and Supply Chain Management
Operations Management
ISBN:9781285869681
Author:Robert M. Monczka, Robert B. Handfield, Larry C. Giunipero, James L. Patterson
Publisher:Cengage Learning
Production and Operations Analysis, Seventh Editi...
Operations Management
ISBN:9781478623069
Author:Steven Nahmias, Tava Lennon Olsen
Publisher:Waveland Press, Inc.