Stanford Rosenberg Computing wants to establish an assembly line for producing a new product, the Personal Digital Assistant (PDA). The tasks, task times, and immediate predecessors for the tasks are as follows:
Rosenberg’s goal is to produce 180 PDAs per hour.
a) What is the cycle time?
b) What is the theoretical minimum for the number of work stations that Rosenberg can achieve in this assembly line?
c) Can the theoretical minimum actually be reached when work stations are assigned?
Expert Solution & Answer
Want to see the full answer?
Check out a sample textbook solutionStudents have asked these similar questions
Stanford Rosenberg Computing wants to establish anassembly line for producing a new product, the Personal DigitalAssistant (PDA). The tasks, task times, and immediate predecessorsfor the tasks are as follows: Rosenberg's goal is to produce 180 PDAs per hour.a) What is the cycle time?b) What is the theoretical minimum for the number of workstations that Rosenberg can achieve in this assembly line?c) Can the theoretical minimum actually be reached when workstations are assigned?
Stanford Rosenberg Computing wants to establish an assembly line for producing a new product, the Personal Digital Assistant (PDA). The tasks, task times, and immediate predecessors for the tasks are as follows:
Task
Time
(sec)
Immediate Predecessor
A
11
−
B
15
A
C
7
A
D
4
B, C
E
20
D
Rosenberg's goal is to produce
175
PDAs per hour.
a) The cycle time for the production of a PDA =
nothing
seconds (round your response to two decimal places).
B) what's the minimum number of workstations in the assembly line?
C) Can the minimum actually be reached when workstations are assigned?
Sue Helms Appliances wants to establish an assembly line to manufacture its new product, the Micro Popcorn Popper. The goal is to produce
five
poppers per hour. The tasks, task times, and immediate predecessors for producing one Micro Popcorn Popper are as follows:
Task
Performance Time (mins)
Task Must Follow Task Listed Below
A
8
−
B
11
A
C
10
A, B
D
9
B, C
E
8
C
F
4
D, E
A
C
F
B
E
D
In the diagram, there are 6 circles labeled using the letters from A to F. There are 8 of arrows, and each arrow connects one circle to another circle. The arrows are situated in the following manner: A to B, A to C, B to C, C to D, B to D, C to E, D to F, and E to F.
Part 2
a) The theoretical minimum number of
workstations=55
(round your response up to the…
Chapter 9 Solutions
MyOMLab Principles of operations management : Sustainability and supply chain management (Book & eText Access Card)
Ch. 9 - Prob. 1EDCh. 9 - Prob. 1DQCh. 9 - Prob. 2DQCh. 9 - Prob. 3DQCh. 9 - Prob. 4DQCh. 9 - Prob. 5DQCh. 9 - Prob. 6DQCh. 9 - Prob. 7DQCh. 9 - Prob. 8DQCh. 9 - Prob. 9DQ
Ch. 9 - Prob. 10DQCh. 9 - Prob. 11DQCh. 9 - Prob. 12DQCh. 9 - Prob. 13DQCh. 9 - Prob. 14DQCh. 9 - Prob. 15DQCh. 9 - Prob. 16DQCh. 9 - Prob. 17DQCh. 9 - Prob. 18DQCh. 9 - Prob. 1PCh. 9 - Prob. 2PCh. 9 - Prob. 3PCh. 9 - Roy Creasey Enterprises, a machine shop, is...Ch. 9 - Adam Munson Manufacturing, in Gainesville,...Ch. 9 - Prob. 6PCh. 9 - Prob. 7PCh. 9 - Prob. 8PCh. 9 - Six processes are to be laid out in six areas...Ch. 9 - Prob. 11PCh. 9 - Stanford Rosenberg Computing wants to establish an...Ch. 9 - Illinois Furniture, Inc., produces all types of...Ch. 9 - Prob. 14PCh. 9 - The Action Toy Company has decided to manufacture...Ch. 9 - Prob. 16PCh. 9 - Prob. 17PCh. 9 - Prob. 18PCh. 9 - Prob. 19PCh. 9 - Prob. 20PCh. 9 - Prob. 21PCh. 9 - Prob. 22PCh. 9 - Prob. 23PCh. 9 - Prob. 1CSCh. 9 - Prob. 2CSCh. 9 - Henry Coupe, the manager of a metropolitan branch...Ch. 9 - Prob. 4CSCh. 9 - Prob. 1.1VCCh. 9 - Prob. 1.2VCCh. 9 - Prob. 1.3VCCh. 9 - Prob. 1.4VCCh. 9 - Prob. 1.5VCCh. 9 - Prob. 1.6VCCh. 9 - Prob. 2.1VCCh. 9 - Prob. 2.2VCCh. 9 - Prob. 2.3VC
Knowledge Booster
Learn more about
Need a deep-dive on the concept behind this application? Look no further. Learn more about this topic, operations-management and related others by exploring similar questions and additional content below.Similar questions
- A company needs to rebalance a product layout for producing new plastic license plates. They plan to use the assembly line six hours in order to meet projected demand of 2,160 license plates each day. The following table describes the tasks involved in the production of this product: Without regard to projected demand, what is the maximum possible cycle time for this assembly line? Task Time (secs) Immediate Predecessor a 3 none b 4 none c 5 a,b d 7 none e 9 c,darrow_forwardStanford Rosenberg Computing wants to establish an assembly line for producing a new product, the Personal Digital Assistant (PDA). The tasks, task times, and immediate predecessors for the tasks are as follows: Task Time (sec) Immediate Predecessor A 11 − B 14 A C 8 A D 4 B, C E 20 D Rosenberg's goal is to produce 180 PDAs per hour. a) The cycle time for the production of a PDA = 20 seconds (round your response to two decimal places). Part 3 b) The theoretical minimum number of workstations that Rosenberg can achieve in this assembly line=3(round your response up to the next whole number). c) For one to assign the tasks to the actual workstations and be able to use the "theoretical minimum" number, the activity assignment should be: Workstation # Tasks Assigned to Workstation 1 A ▼…arrow_forwardStanford Rosenberg Computing wants to establish an assembly line for producing a new product, the Personal Digital Assistant (PDA). The tasks, task times, and immediate predecessors for the tasks are as follows: Task Time (sec) Immediate Predecessor A 11 − B 15 A C 7 A D 4 B, C E 20 D Rosenberg's goal is to produce 170 PDAs per hour. a) The cycle time for the production of a PDA = enter your response here seconds (round your response to two decimal places). b) The theoretical minimum number of workstations that Rosenberg can achieve in this assembly line=enter your response here (round your response up to the next whole number). c) For one to assign the tasks to the actual workstations and be able to use the "theoretical minimum" number, the activity assignment should be: Workstation # Tasks Assigned to…arrow_forward
- Use the longest work element rule to balance the assembly line described in the following table and Figure so that it will produce 40 units per hour.a. What is the cycle time?b. What is the theoretical minimum number of workstations?c. Which work elements are assigned to each workstation?d. What are the resulting efficiency and balance delay percentages?e. Use the shortest work element rule to balance the assembly line. Do you note any changes in solution? Work Element Time (Sec) Immediate Predecessor(s) A B C D E F G H I J K 40 80 30 25 20 15 60 45 10 75 15 None A A B C B B D E,G F H,I,Jarrow_forwardThe Action Toy Company has decided to manufacture a new train set, the production of which is broken into six steps. The demand for the train is 4,500 units per 40-hour workweek: (See image) The theoretical minimum number of workstations is ???Were you able to assign all the tasks to the theoretical minimum number of workstations? Yes or No ??arrow_forwardJane produces custom greeting cards using six distinct workelements. She would like to produce 10 cards in each 8-hourcard-making session. Figure 5.17 details each work elementand its associated durations in minutes as well as their pre-cedence relationships. a. What cycle time is required to satisfy the required output rate?b. What is the theoretical minimum number of workstationsrequired?c. If Jane identifies a five-station solution, what is the associ-ated efficiency and balance delay?d. If the cycle time increased by 100 percent, would the the-oretical minimum number of workstations also increaseby 100 percent?arrow_forward
- The Action Toy Company has decided to manufacture a new train set, the production of which is broken into six steps. The demand for the train is 4,800 units per 40-hourworkweek: a) Draw a precedence diagram of this operation. b) Given the demand, what is the cycle time for this operation? c) What is the theoretical minimum number of workstations?arrow_forwardA manufacturing company is designing an assembly lineto produce its main product. Th e line should be able to produce60 units per hour. Th e following data in Table 10-16 give thenecessary information. (a) Which task is the bottleneck?(b) Draw a precedence diagram for the above information.(c) Compute the cycle time with a desired output of 60 unitsper hourarrow_forwardPlease answer question d, e, f a. Draw a precedence diagram.b. What cycle time would provide the desired output? c. What is the maximum possible output of the line? d. What is the theoretical minimum number of workstations using the cycle time computed in” b “above? e. Assign tasks to workstations using the cycle time in “b” above. f. Calculate the efficiency and idle time percentage of the line.arrow_forward
- As part of a major plant renovation project, the industrial engineering department has been asked to balance a revised assembly operation to achieve an output of 250 units per 8-hour day. Task times and precedence relationships are as follows: Task Duration(minutes) ImmediatePredecessor a 0.5 - b 0.4 a c 0.5 b d 0.3 - e 1.8 d f 1.9 c g 2 e, f Do each of the following: a. Determine the number of followers for each task. (Please answer number of tasks following task for A-G)arrow_forwardWhy are product layouts atypical in service environments?arrow_forwardIllinois Furniture, Inc., produces all types of officefurniture. The "Executive Secretary" is a chair that has beendesigned using ergonomics to provide comfort during long workhours. The chair sells for $130. There are 480 minutes availableduring the day, and the average daily demand has been 50 chairs.There are eight tasks: a) Draw a precedence diagram of this operation. •b) What is the cycle time for this operation?c) What is the theoretical minimum number of workstations?d) Assign tasks to workstations.e) What is the idle time per cycle?f) How much total idle time is present in an 8-hour shift?g) What is the efficiency of the assembly line, given your answer in (d)?arrow_forward
arrow_back_ios
SEE MORE QUESTIONS
arrow_forward_ios
Recommended textbooks for you
- Practical Management ScienceOperations ManagementISBN:9781337406659Author:WINSTON, Wayne L.Publisher:Cengage,Operations ManagementOperations ManagementISBN:9781259667473Author:William J StevensonPublisher:McGraw-Hill EducationOperations and Supply Chain Management (Mcgraw-hi...Operations ManagementISBN:9781259666100Author:F. Robert Jacobs, Richard B ChasePublisher:McGraw-Hill Education
- Purchasing and Supply Chain ManagementOperations ManagementISBN:9781285869681Author:Robert M. Monczka, Robert B. Handfield, Larry C. Giunipero, James L. PattersonPublisher:Cengage LearningProduction and Operations Analysis, Seventh Editi...Operations ManagementISBN:9781478623069Author:Steven Nahmias, Tava Lennon OlsenPublisher:Waveland Press, Inc.
Practical Management Science
Operations Management
ISBN:9781337406659
Author:WINSTON, Wayne L.
Publisher:Cengage,
Operations Management
Operations Management
ISBN:9781259667473
Author:William J Stevenson
Publisher:McGraw-Hill Education
Operations and Supply Chain Management (Mcgraw-hi...
Operations Management
ISBN:9781259666100
Author:F. Robert Jacobs, Richard B Chase
Publisher:McGraw-Hill Education
Purchasing and Supply Chain Management
Operations Management
ISBN:9781285869681
Author:Robert M. Monczka, Robert B. Handfield, Larry C. Giunipero, James L. Patterson
Publisher:Cengage Learning
Production and Operations Analysis, Seventh Editi...
Operations Management
ISBN:9781478623069
Author:Steven Nahmias, Tava Lennon Olsen
Publisher:Waveland Press, Inc.
Inventory Management | Concepts, Examples and Solved Problems; Author: Dr. Bharatendra Rai;https://www.youtube.com/watch?v=2n9NLZTIlz8;License: Standard YouTube License, CC-BY