Fundamentals of Corporate Finance Alternate Edition
Fundamentals of Corporate Finance Alternate Edition
10th Edition
ISBN: 9780077479459
Author: Stephen A. Ross, Randolph W. Westerfield, Bradford D. Jordan
Publisher: MCGRAW-HILL HIGHER EDUCATION
bartleby

Concept explainers

bartleby

Videos

Question
Book Icon
Chapter 9, Problem 13QP
Summary Introduction

To calculate: The rate of crossover for two projects.

Introduction:

The net present value is one of the capital budgeting techniques, which is used to identify the profitability in the proposed investment. The internal rate of return is a rate of discount, which makes the predictable investment’s NPV equals zero.

Expert Solution & Answer
Check Mark

Answer to Problem 13QP

The crossover rate for the two projects is 11.19%. The NPV profiles show that both the projects have higher NPV for rate of discount below 11.19% and have lower NPV for the rate above 11.19%.

Explanation of Solution

Given information:

The details of two projects are provided. The cash flows of project X for year 1, year 2, and year 3, are $8,850, $9,100, and $8,800 respectively. The initial investment is $20,000. The cash flows of project Y for 3 years are $10,100, $7,800, $8,700 respectively, and the initial investment is $20,000.

Note:

  • NPV is the difference between the present values of the cash inflows and the present values of cash outflows.
  • The IRR is a rate of interest, which makes a project’s NPV equals zero. Hence, using the available information, assume that NPV is equal to zero and form an equation to compute the IRR.

Equation of NPV to compute IRR assuming that NPV is equal to zero:

NPV=0=$20,000+$8,850(1+IRR)+$9,100(1+IRR)2+$8,800(1+IRR)30=$20,000+$8,850(1+IRR)+$9,100(1+IRR)2+$8,800(1+IRR)3

Compute IRR for project X using a spreadsheet:

Step 1:

Fundamentals of Corporate Finance Alternate Edition, Chapter 9, Problem 13QP , additional homework tip  1

  • Type the equation of NPV in H6 in the spreadsheet and consider the IRR value as H7.

Step 2:

Fundamentals of Corporate Finance Alternate Edition, Chapter 9, Problem 13QP , additional homework tip  2

  • Assume the IRR value as 10%.

Step 3:

Fundamentals of Corporate Finance Alternate Edition, Chapter 9, Problem 13QP , additional homework tip  3

  • In the spreadsheet, go to data and select What-if analysis.
  • In What-if analysis, select Goal Seek.
  • In “Set cell”, select H6 (the formula).
  • The “To value” is considered as 0 (the assumption value for NPV).
  • The H7 cell is selected for  “By changing cell”.

Step 4:

Fundamentals of Corporate Finance Alternate Edition, Chapter 9, Problem 13QP , additional homework tip  4

  • Following the previous step, click OK in the Goal Seek Status. The Goal Seek Status appears with the IRR value.

Step 5:

Fundamentals of Corporate Finance Alternate Edition, Chapter 9, Problem 13QP , additional homework tip  5

  • The value appears to be 16.091166038864%.

Hence, the IRR value is 16.09%.

Compute IRR for project Y using a spreadsheet:

Step 1:

Fundamentals of Corporate Finance Alternate Edition, Chapter 9, Problem 13QP , additional homework tip  6

  • Type the equation of NPV in H6 in the spreadsheet and consider the IRR value as H7.

Step 2:

Fundamentals of Corporate Finance Alternate Edition, Chapter 9, Problem 13QP , additional homework tip  7

  • Assume the IRR value as 10%.

Step 3:

Fundamentals of Corporate Finance Alternate Edition, Chapter 9, Problem 13QP , additional homework tip  8

  • In the spreadsheet, go to data and select What-if analysis.
  • In What-if analysis, select Goal Seek.
  • In “Set cell”, select H6 (the formula).
  • The “To value” is considered as 0 (the assumption value for NPV).
  • The H7 cell is selected for “By changing cell”.

Step 4:

Fundamentals of Corporate Finance Alternate Edition, Chapter 9, Problem 13QP , additional homework tip  9

  • Following the previous step, click OK in the Goal Seek Status. The Goal Seek Status appears with the IRR value.

Step 5:

Fundamentals of Corporate Finance Alternate Edition, Chapter 9, Problem 13QP , additional homework tip  10

  • The value appears to be 16.2429872464063%.

Hence, the IRR value is 16.24%.

Formula to compute the crossover rate:

Crossover rate for each year=Cash flows from project XCash flows from project Y

Equation of crossover rate to compute R:

0=$1,250(1+R)+$1,300(1+R)2+$100(1+R)3

Where,

R denotes the crossover rate.

Compute R using a spreadsheet:

Step 1:

Fundamentals of Corporate Finance Alternate Edition, Chapter 9, Problem 13QP , additional homework tip  11

  • Type the equation of NPV in H6 in the spreadsheet and consider the IRR value as H7.

Step 2:

Fundamentals of Corporate Finance Alternate Edition, Chapter 9, Problem 13QP , additional homework tip  12

  • Assume the IRR value as 10%.

Step 3:

Fundamentals of Corporate Finance Alternate Edition, Chapter 9, Problem 13QP , additional homework tip  13

  • In the spreadsheet, go to data and select What-if analysis.
  • In What-if analysis, select Goal Seek.
  • In “Set cell”, select H6 (the formula).
  • The “To value” is considered as 0 (the assumption value for NPV).
  • The H7 cell is selected for  “By changing cell”.

Step 4:

Fundamentals of Corporate Finance Alternate Edition, Chapter 9, Problem 13QP , additional homework tip  14

  • Following the previous step, click OK in the Goal Seek Status. The Goal Seek Status appears with the IRR value.

Step 5:

Fundamentals of Corporate Finance Alternate Edition, Chapter 9, Problem 13QP , additional homework tip  15

  • The value appears to be 11.1945910036974%.

Hence, the R-value is 11.19%.

Formula to calculate the NPV:

NPV=Present value of cash inflowPresent value of cash outflow

Note: As the discount rate is over a range of 0% to 25%, calculate NPV for 0%, 5%, 10%, 15%, 20%, and 25%.

Compute the NPV with the discount rate of 0% for project X:

NPV=Present value of cash inflowPresent value of cash outflow=($8,850(1+0)+$9,100(1+0)2+$8,800(1+0)3)$20,000=$6,750

Compute the NPV with the discount rate of 0% for project Y:

NPV=Present value of cash inflowPresent value of cash outflow=($10,100(1+0)+$7,800(1+0)2+$8,700(1+0)3)$20,000=$6,600

Hence, the NPVs for projects X and Y @ 0% are $6,750 and $6,600 respectively.

Compute the NPV with the discount rate of 5% for project X:

NPV=Present value of cash inflowPresent value of cash outflow=($8,850(1+0.05)+$9,100(1+0.05)2+$8,800(1+0.05)3)$20,000=$8,428.571429+$8,253.968254+$7,601.770867$20,000=$4,284.31

Compute the NPV with the discount rate of 5% for project Y:

NPV=Present value of cash inflowPresent value of cash outflow=($10,100(1+0.05)+$7,800(1+0.05)2+$8,700(1+0.05)3)$20,000=$9,619.047619+$7,074.829932+$7,515.387107$20,000=$4,209.26

Hence, the NPVs for projects X and Y @ 5% are $4.284.31 and $4,209.26 respectively.

Compute the NPV with the discount rate of 10% for project X:

NPV=Present value of cash inflowPresent value of cash outflow=($8,850(1+0.10)+$9,100(1+0.10)2+$8,800(1+0.10)3)$20,000=$8,045.454545+$7,520.661157+$6,611.570248$20,000=$2,177.69

Compute the NPV with the discount rate of 10% for project Y:

NPV=Present value of cash inflowPresent value of cash outflow=($10,100(1+0.10)+$7,800(1+0.10)2+$8,700(1+0.10)3)$20,000=$9,181.818182+$6,446.280992+$6,536.438768$20,000=$2,164.54

Hence, the NPVs for projects X and Y @ 10% are $2,177.69 and $2,164.54 respectively.

Compute the NPV with the discount rate of 15% for project X:

NPV=Present value of cash inflowPresent value of cash outflow=($8,850(1+0.15)+$9,100(1+0.15)2+$8,800(1+0.15)3)$20,000=$7,695.652174+$6,880.907372+$5,786.142845$20,000=$362.70

Compute the NPV with the discount rate of 15% for project Y:

NPV=Present value of cash inflowPresent value of cash outflow=($10,100(1+0.15)+$7,800(1+0.15)2+$8,700(1+0.15)3)$20,000=$8,782.608696+$5,897.920605+$5,720.391222$20,000=$400.92

Hence, the NPVs for projects X and Y @ 15% are $362.70 and $400.92 respectively.

Compute the NPV with the discount rate of 20% for project X:

NPV=Present value of cash inflowPresent value of cash outflow=($8,850(1+0.20)+$9,100(1+0.20)2+$8,800(1+0.20)3)$20,000=$7,375+$6,319.444444+$5,092.592593$20,000=$1,212.96

Compute the NPV with the discount rate of 20% for project Y:

NPV=Present value of cash inflowPresent value of cash outflow=($10,100(1+0.20)+$7,800(1+0.20)2+$8,700(1+0.20)3)$20,000=$8,416.666667+$5,416.666667+$5,034.722222$20,000=$1,131.94

Hence, the NPVs for projects X and Y @ 20% are -$1,212.96 and -$1,131.94 respectively.

Compute the NPV with the discount rate of 25% for project X:

NPV=Present value of cash inflowPresent value of cash outflow=($8,850(1+0.25)+$9,100(1+0.25)2+$8,800(1+0.25)3)$20,000=$7,080+$5,824+$4,505.6$20,000=$2,590.4

Compute the NPV with the discount rate of 25% for project Y:

NPV=Present value of cash inflowPresent value of cash outflow=($10,100(1+0.25)+$7,800(1+0.25)2+$8,700(1+0.25)3)$20,000=$8,080+$4,992+$4,454.4$20,000=$2,473.6

Hence, the NPVs for projects X and Y at 25% are -$2,590.4 and -$2,473.6 respectively.

Want to see more full solutions like this?

Subscribe now to access step-by-step solutions to millions of textbook problems written by subject matter experts!

Chapter 9 Solutions

Fundamentals of Corporate Finance Alternate Edition

Ch. 9.6 - What does the profitability index measure?Ch. 9.6 - How would you state the profitability index rule?Ch. 9.7 - Prob. 9.7ACQCh. 9.7 - If NPV is conceptually the best procedure for...Ch. 9 - Prob. 9.1CTFCh. 9 - Prob. 9.2CTFCh. 9 - Prob. 9.3CTFCh. 9 - Prob. 9.4CTFCh. 9 - Prob. 9.5CTFCh. 9 - What is a benefitcost ratio?Ch. 9 - Prob. 9.7CTFCh. 9 - Prob. 1CRCTCh. 9 - Net Present Value [LO1] Suppose a project has...Ch. 9 - Prob. 3CRCTCh. 9 - Prob. 4CRCTCh. 9 - Prob. 5CRCTCh. 9 - Net Present Value [LO1] Concerning NPV: a....Ch. 9 - Prob. 7CRCTCh. 9 - Profitability Index [LO7] Concerning the...Ch. 9 - Payback and Internal Rate of Return [LO2, 5] A...Ch. 9 - Prob. 10CRCTCh. 9 - Capital Budgeting Problems [LO1] What difficulties...Ch. 9 - Prob. 12CRCTCh. 9 - Modified Internal Rate of Return [LO6] One of the...Ch. 9 - Net Present Value [LO1] It is sometimes stated...Ch. 9 - Internal Rate of Return [LO5] It is sometimes...Ch. 9 - Prob. 1QPCh. 9 - Prob. 2QPCh. 9 - Prob. 3QPCh. 9 - Prob. 4QPCh. 9 - Prob. 5QPCh. 9 - Prob. 6QPCh. 9 - Prob. 7QPCh. 9 - Prob. 8QPCh. 9 - Prob. 9QPCh. 9 - Prob. 10QPCh. 9 - Prob. 11QPCh. 9 - Prob. 12QPCh. 9 - Prob. 13QPCh. 9 - Prob. 14QPCh. 9 - Prob. 15QPCh. 9 - Prob. 16QPCh. 9 - Prob. 17QPCh. 9 - Prob. 18QPCh. 9 - Prob. 19QPCh. 9 - Prob. 20QPCh. 9 - Prob. 21QPCh. 9 - Cash Flow Intuition [LO1, 2] A project has an...Ch. 9 - Prob. 23QPCh. 9 - Prob. 24QPCh. 9 - Prob. 25QPCh. 9 - Prob. 26QPCh. 9 - Problems with IRR [LO5] McKeekin Corp. has a...Ch. 9 - Prob. 28QPCh. 9 - Prob. 1MCh. 9 - Prob. 2MCh. 9 - Prob. 3M
Knowledge Booster
Background pattern image
Finance
Learn more about
Need a deep-dive on the concept behind this application? Look no further. Learn more about this topic, finance and related others by exploring similar questions and additional content below.
Recommended textbooks for you
Text book image
Essentials Of Investments
Finance
ISBN:9781260013924
Author:Bodie, Zvi, Kane, Alex, MARCUS, Alan J.
Publisher:Mcgraw-hill Education,
Text book image
FUNDAMENTALS OF CORPORATE FINANCE
Finance
ISBN:9781260013962
Author:BREALEY
Publisher:RENT MCG
Text book image
Financial Management: Theory & Practice
Finance
ISBN:9781337909730
Author:Brigham
Publisher:Cengage
Text book image
Foundations Of Finance
Finance
ISBN:9780134897264
Author:KEOWN, Arthur J., Martin, John D., PETTY, J. William
Publisher:Pearson,
Text book image
Fundamentals of Financial Management (MindTap Cou...
Finance
ISBN:9781337395250
Author:Eugene F. Brigham, Joel F. Houston
Publisher:Cengage Learning
Text book image
Corporate Finance (The Mcgraw-hill/Irwin Series i...
Finance
ISBN:9780077861759
Author:Stephen A. Ross Franco Modigliani Professor of Financial Economics Professor, Randolph W Westerfield Robert R. Dockson Deans Chair in Bus. Admin., Jeffrey Jaffe, Bradford D Jordan Professor
Publisher:McGraw-Hill Education
Capital Budgeting Introduction & Calculations Step-by-Step -PV, FV, NPV, IRR, Payback, Simple R of R; Author: Accounting Step by Step;https://www.youtube.com/watch?v=hyBw-NnAkHY;License: Standard Youtube License