Chapter 9, Problem 16P
a)
Summary Introduction
To draw: The precedence diagram.
b)
Summary Introduction
To assign: The different tasks to different workstations.
c)
Summary Introduction
To determine: How the balance could be improved to 100%
d)
Summary Introduction
To determine: The theoretical minimum number of workstations.
Expert Solution & Answer
Want to see the full answer?
Check out a sample textbook solutionStudents have asked these similar questions
The following table details the tasks required forIndiana-based Frank Pianki Industries to manufacture a fullyportable industrial vacuum cleaner. The times in the table are inminutes. Demand forecasts indicate a need to operate with a cycletime of 10 minutes. a) Draw the appropriate precedence diagram for this production line.b) Assign tasks to workstations and determine how much idle time is present each cycle.c) Discuss how this balance could be improved to 100%.d) What is the theoretical minimum number of workstations?
The following table details the tasks required for Indiana-based Frank Pianki Industries to manufacture a fully portable industrial vacuum cleaner. The times in the table are in minutes. Demand forecasts indicate a need to operate with a cycle time of
11
minutes.
Activity
Activity Description
Performance Time (mins)
Predecessors
A
Attach wheels to tub
5.0
−
B
Attach motor to lid
1.5
−
C
Attach battery pack
2.8
B
D
Attach safety cutoff
4.0
C
E
Attach filters
3.0
B
F
Attach lid to tub
2.0
A, E
G
Assemble attachments
3.0
−
H
Function test
3.7
D, F, G
I
Final inspection
2.0
H
J
Packing
2.0
I
a-b) One of the possible assignment of tasks to workstations is shown correctly in…
The following table details the tasks required forIndiana-based Frank Pianki Industries to manufacture a fullyportable industrial vacuum cleaner. The times in the table are inminutes. Demand forecasts indicate a need to operate with a cycletime of 10 minutes.ACTIVITY ACTIVITY DESCRIPTION
IMMEDIATEPREDECESSORS TIMEA Attach wheels to tub — 5B Attach motor to lid — 1.5C Attach battery pack B 3D Attach safety cutoff C 4E Attach fi lters B 3F Attach lid to tub A, E 2G Assemble attachments — 3H Function test D, F, G 3.5I Final inspection H 2J Packing I 2a) Draw the appropriate precedence diagram for this productionline.b) Assign tasks to workstations and determine how much idletime is present each cycle.c) Discuss how this balance could be improved to 100%.d) What is the theoretical minimum number of workstations?
Chapter 9 Solutions
EBK PRINCIPLES OF OPERATIONS MANAGEMENT
Ch. 9 - Prob. 1EDCh. 9 - Prob. 1DQCh. 9 - Prob. 2DQCh. 9 - Prob. 3DQCh. 9 - Prob. 4DQCh. 9 - Prob. 5DQCh. 9 - Prob. 6DQCh. 9 - Prob. 7DQCh. 9 - Prob. 8DQCh. 9 - Prob. 9DQ
Ch. 9 - Prob. 10DQCh. 9 - Prob. 11DQCh. 9 - Prob. 12DQCh. 9 - Prob. 13DQCh. 9 - Prob. 14DQCh. 9 - Prob. 15DQCh. 9 - Prob. 16DQCh. 9 - Prob. 17DQCh. 9 - Prob. 18DQCh. 9 - Prob. 1PCh. 9 - Prob. 2PCh. 9 - Prob. 3PCh. 9 - Roy Creasey Enterprises, a machine shop, is...Ch. 9 - Adam Munson Manufacturing, in Gainesville,...Ch. 9 - Prob. 6PCh. 9 - Prob. 7PCh. 9 - Prob. 8PCh. 9 - Prob. 9PCh. 9 - Six processes are to be laid out in six areas...Ch. 9 - Stanford Rosenberg Computing wants to establish an...Ch. 9 - Illinois Furniture, Inc., produces all types of...Ch. 9 - Prob. 14PCh. 9 - The Action Toy Company has decided to manufacture...Ch. 9 - Prob. 16PCh. 9 - Prob. 17PCh. 9 - Prob. 18PCh. 9 - Prob. 19PCh. 9 - Prob. 20PCh. 9 - Prob. 21PCh. 9 - Prob. 22PCh. 9 - Prob. 23PCh. 9 - Prob. 25PCh. 9 - Prob. 26PCh. 9 - Prob. 27PCh. 9 - Prob. 1CSCh. 9 - Prob. 2CSCh. 9 - Henry Coupe, the manager of a metropolitan branch...Ch. 9 - Prob. 4CSCh. 9 - Prob. 1.1VCCh. 9 - Prob. 1.2VCCh. 9 - Prob. 1.3VCCh. 9 - Prob. 1.4VCCh. 9 - Prob. 1.5VCCh. 9 - Prob. 1.6VCCh. 9 - Prob. 2.1VCCh. 9 - Prob. 2.2VCCh. 9 - Prob. 2.3VC
Knowledge Booster
Learn more about
Need a deep-dive on the concept behind this application? Look no further. Learn more about this topic, operations-management and related others by exploring similar questions and additional content below.Similar questions
- Ola Ltd, which uses a job costing system, had two jobs in process at the start of the year: Job L1 ($68,000) andJob L2 ($30,000). The following information is available:i) The company applies manufacturing overhead on the basis of machine hours. Budgeted overhead andmachine activity for the year were anticipated to be $1,000,000 and 25,000 hours, respectively.ii) The company worked on three jobs during the first quarter (i.e. from 1 January to 31 March). Directmaterials used, direct labour incurred and machine hours consumed were as shown in the following table: Job numbers Direct material Direct labour Machine hoursL1 $15,000 $30,000 900L2 - 33,000 1,600L3 45,000 65,000 2,000HI5017 Managerial AccountingPage 2 of 22iii) Manufacturing overhead incurred during the first quarter was $215,000.iv) Ola Ltd completed Job L1 and Job L2 during the first quarter. Job L2 was sold on credit, producing a profitof $30,000 for the company.Required:a) Calculate the company’s predetermined overhead…arrow_forwardLine balancing As the Operations Manager of Shane Manufacturing Ltd., you are given the task to balance the assembly line that is used to produce a special type of toy. a. Develop your own scenario (quantitative example) of this line balancing problem. Include all relevant information. b. Draw the precedence diagram for the problem that you set up in part “a" above. c. Use the example that you set up to demonstrate how you will balance the line. d. Calculate the efficiency of the line.arrow_forwardJ.C. Howard’s medical testing company in Kansas wishes to assign a set of jobs to a set of machines. The follow-ing table provides the production data of each machine when performing the specific job: MACHINEABCD1 7 9 8 102 10 9 7 63 11 5 9 64 9 11 5 8 a) Determine the assignment of jobs to machines that will maxi-mize total production. b) What is the total production of your assignments?arrow_forward
- The following table details the tasks required for Florida-based James Industries, Inc. to manufacture a fully portable industrial vacuum cleaner. The times in the table are in minutes. Demand forecasts indicate a need to operate with a cycle time of 10 minutes. ACTIVITY ACTIVITY DESCRIPTION IMMEDIATE PREDECESSORS TIME A Attach wheels to tub - 5 B Attach motor to lid - 1.5 C Attach battery pack B 3 D Attach safety cutoff C 4 E Attach filters B 3 F Attach lid to tub A, E 2 G Assemble attachments - 3 H Function test D, F, G 3.5 I Final inspection H 2 J Packing I 2 a) Draw the appropriate precedence diagram for this production line. b) Assign tasks to workstations and determine how much idle time is present in each cycle. c) What is the efficiency rate?arrow_forwardUse excel to show formulas 1. A company is designing a product layout for a new product. They plan to use this production line 16 hours a day in order to meet forecasted demand of 1200 units per day. For output to equal forecasted demand, what should be the actual cycle time for this production?arrow_forwardMendoza Industries manufactures chainsaws. The company has two activities that are used to apply overhead to its products: Machining, applied at the rate of $15 per machine hour • Finishing, applied at the rate of $25 per direct labor hour ● This month, 200 chainsaws were made, using 1,000 machine hours and 400 direct labor hours. Total direct material costs were $20,000 and total direct labor cots were $6,000. What is the total cost to manufacture the 200 chainsaws? O $25,000 O $45,000 O $51,000 O $26,000arrow_forward
- Management wants to design an assembly line that will turn out 800 videotapes per day. There will be eight working hours in each day. The industrial engineering staff has assembled the information below: A) Determine the maximum and minimum cycle times.B) Determine the optimum cycle time.C) What is the minimum number of stations needed?D) Draw the precedence diagram.E) Assign tasks to stations in order of most following tasks first. Submit an Excel file based on Chapter 6 Excel Template to indicate your computation.arrow_forwardPrint Item Equivalent Units of Production Data for the two departments of Kimble & Pierce Company for June of the current fiscal year are as follows: Drawing Department Winding Department Work in process, June 1 10,000 units, 38% completed 4,000 units, 35% completed Completed and transferred to next processing department during June 60,000 units 60,500 units Work in process, June 30 11,500 units, 70% completed 3,500 units, 60% completed Production begins in the Drawing Department and finishes in the Winding Department. a. If all direct materials are placed in process at the beginning of production, determine the direct materials and conversion equivalent units of production for June for the Drawing Department. If an amount is zero, enter in "0". Drawing Department Direct Materials and Conversion Equivalent Units of Production For June Whole Units Direct MaterialsEquivalent Units ConversionEquivalent Units Inventory in process, June 1 fill…arrow_forwardThe City Commission of Nashville has decided to build a botanical garden and picnic area in the heart of the city for the recreation of its citizens. The precedence table for all the activities required to construct this area successfully is as follows: Code A B с D E F G H I Description Find location; determine resource requirements Requisition of lumber and sand Dig and grade Saw lumber into appropriate sizes Position lumber in correct locations Time (hrs) 20 60 100 30 20 10 20 10 30 Nail lumber together Put sand in and under the equipment Put dirt around the equipment Put grass all over the garden, landscape, paint Refer to the legend for the activity that corresponds to each code. Using the line drawing tool, draw a Gantt chart for activites E through I of the project. Immediate Predecessor(s) None A A B D, C E F F G, H A B C- D- E F G H- H 0 20 40 60 80 100 120 140 160 180 200 Q ✔arrow_forward
- Alvis Construction Supply Company has a department that manufactures wood trusses (wood frames used in the construction industry). The following information is for the production of these trusses for the month of February: Work-in-process inventory, February 1 4,300 trusses Direct materials: 100% complete $ 10,780 Conversion: 30% complete $ 15,558 Units started during February 18,300 trusses Units completed during February and transferred out 17,300 trusses Work-in-process inventory, February 29 Direct materials: 100% complete Conversion: 30% complete Costs incurred during February Direct materials $ 59,340 Conversion $ 92,392 Required Using the weighted-average method, calculate the following: 1-a. Costs per equivalent unit. (Round your answers to 4 decimal places.) 1-b. Cost of goods completed and transferred out. (Round "Cost per EU" to 4 decimal places. Round final answer to nearest whole dollars.) 1-c. Costs remaining in the…arrow_forwardSue Helms Appliances wants to establish an assem-bly line to manufacture its new product, the Micro Popcorn Popper. The goal is to produce five poppers per hour. The tasks,task times, and immediate predecessors for producing one MicroPopcorn Popper are as follows:TASK TIME (min) IMMEDIATEPREDECESSORSA 10 —B 12 AC 8 A, BD 6 B, CE 6 CF 6 D, Ea) What is the theoretical minimum for the smallest number ofworkstations that Helms can achieve in this assembly line?b) Graph the assembly line, and assign workers to workstations.Can you assign them with the theoretical minimum?c) What is the efficiency of your assignment?arrow_forwardThe director of social services of a county has learned that the state has mandated additional information requirements. This will place an additional burden on the agency. The director has identified three acceptable alternatives to handle the increased workload. One alternative is to reassign present staff members, the second is to hire and train two new workers, and the third is to redesign current practice so that workers can readily collect the information with little additional effort. An unknown factor is the caseload for the coming year when the new data will be collected on a trial basis. The estimated costs for various options and caseloads are shown in the following table: CASELOAD Moderate High Very High Reassign staff $ 80 * 90 95 New staff 70 70 70 Redesign collection 90 80 70 *Cost in $ thousands. After contemplating the caseload question, the director of social services has decided that reasonable caseload probabilities are 0.30 for…arrow_forward
arrow_back_ios
SEE MORE QUESTIONS
arrow_forward_ios
Recommended textbooks for you
- Practical Management ScienceOperations ManagementISBN:9781337406659Author:WINSTON, Wayne L.Publisher:Cengage,Operations ManagementOperations ManagementISBN:9781259667473Author:William J StevensonPublisher:McGraw-Hill EducationOperations and Supply Chain Management (Mcgraw-hi...Operations ManagementISBN:9781259666100Author:F. Robert Jacobs, Richard B ChasePublisher:McGraw-Hill Education
- Purchasing and Supply Chain ManagementOperations ManagementISBN:9781285869681Author:Robert M. Monczka, Robert B. Handfield, Larry C. Giunipero, James L. PattersonPublisher:Cengage LearningProduction and Operations Analysis, Seventh Editi...Operations ManagementISBN:9781478623069Author:Steven Nahmias, Tava Lennon OlsenPublisher:Waveland Press, Inc.
Practical Management Science
Operations Management
ISBN:9781337406659
Author:WINSTON, Wayne L.
Publisher:Cengage,
Operations Management
Operations Management
ISBN:9781259667473
Author:William J Stevenson
Publisher:McGraw-Hill Education
Operations and Supply Chain Management (Mcgraw-hi...
Operations Management
ISBN:9781259666100
Author:F. Robert Jacobs, Richard B Chase
Publisher:McGraw-Hill Education
Purchasing and Supply Chain Management
Operations Management
ISBN:9781285869681
Author:Robert M. Monczka, Robert B. Handfield, Larry C. Giunipero, James L. Patterson
Publisher:Cengage Learning
Production and Operations Analysis, Seventh Editi...
Operations Management
ISBN:9781478623069
Author:Steven Nahmias, Tava Lennon Olsen
Publisher:Waveland Press, Inc.
Inventory Management | Concepts, Examples and Solved Problems; Author: Dr. Bharatendra Rai;https://www.youtube.com/watch?v=2n9NLZTIlz8;License: Standard YouTube License, CC-BY