Textbook Question
Chapter 9, Problem 23P
As the Cottrell Bicycle Co. of St. Louis completes plans for its new assembly line, it identifes 25 different tasks in the production process. VP of Operations Jonathan Cottrell now faces the job of balancing the line. He lists precedences and provides time estimates for each step based on work-sampling techniques. His goal is to produce 1,000 bicycles per standard 40-hour workweek.
- a. Balance this operation, using various heuristics. Which is best and why?
- b. What happens if the firm can change to a 41-hour workweek?
Expert Solution & Answer
Want to see the full answer?
Check out a sample textbook solutionStudents have asked these similar questions
A dress-making operation is being designed as an assemblyline. Table 10-22 shows the tasks that need to be performed, theirtask times, and preceding tasks. If the goal is to produce 30 dressesper hour, answer the questions that follow the table.
(a) Compute the cycle time.(b) Which task is the bottleneck?(c) What is the maximum output for this line?(d) Compute the theoretical minimum number of stations.(e) Assign work elements to stations, using the longest tasktime rule.(f) Compute the effi ciency and balance delay of yourassignment.
Kiko Teddy Bear is a manufacturer of stuffed teddy bears. Kiko would like to be able to produce 40teddy bears per hour on its assembly line. The following information will assist in answering thequestions that follow:
Task Information for Kiko Teddy Bear
Work Element Task Description ImmediatePredecessor Task Time (inseconds)A Cut teddy bear pattern None 90B Sew teddy bear cloth A 75C Stuff teddy bear B 50D Glue on eyes C 20E Glue on nose C…
Kiko Teddy Bear is a manufacturer of stuffed teddy bears. Kiko would like to be able to produce 40teddy bears per hour on its assembly line. The following information will assist in answering thequestions that follow:
Task Information for Kiko Teddy Bear
Work Element Task Description ImmediatePredecessor Task Time (inseconds)A Cut teddy bear pattern None 90B Sew teddy bear cloth A 75C Stuff teddy bear B 50D Glue on eyes C 20E Glue on nose C…
Chapter 9 Solutions
Operations Management - 2 DVDs
Ch. 9 - Prob. 1DQCh. 9 - Prob. 2DQCh. 9 - Prob. 3DQCh. 9 - Prob. 4DQCh. 9 - Prob. 5DQCh. 9 - Prob. 6DQCh. 9 - Prob. 7DQCh. 9 - Prob. 8DQCh. 9 - What are the requirements for a focused work...Ch. 9 - Prob. 10DQ
Ch. 9 - Prob. 11DQCh. 9 - Prob. 12DQCh. 9 - Prob. 13DQCh. 9 - Prob. 14DQCh. 9 - Prob. 15DQCh. 9 - Prob. 16DQCh. 9 - Explain the concept of cross-docking.Ch. 9 - What is a heuristic? Name several that can be used...Ch. 9 - Prob. 1PCh. 9 - Prob. 2PCh. 9 - Three departmentsmilling (M), drilling (D), and...Ch. 9 - Roy Creasey Enterprises, a machine shop, is...Ch. 9 - Prob. 5PCh. 9 - Prob. 6PCh. 9 - Prob. 7PCh. 9 - Prob. 8PCh. 9 - Six processes are to be laid out in six areas...Ch. 9 - After an extensive product analysis using group...Ch. 9 - Stanford Rosenberg Computing wants to establish an...Ch. 9 - Illinois Furniture, Inc., produces all types of...Ch. 9 - Sue Helms Appliances wants to establish an...Ch. 9 - The Action Toy Company has decided to manufacture...Ch. 9 - The following table details the tasks required for...Ch. 9 - Tailwind, Inc., produces high-quality but...Ch. 9 - Prob. 17PCh. 9 - Because of the expected high demand for Mach 10,...Ch. 9 - Prob. 19PCh. 9 - Suppose production requirements in Solved Problem...Ch. 9 - The preinduction physical examination given by the...Ch. 9 - Samuel Smith's company wants to establish an...Ch. 9 - As the Cottrell Bicycle Co. of St. Louis completes...Ch. 9 - Prob. 1CSCh. 9 - Prob. 2CSCh. 9 - Prob. 3CSCh. 9 - Prob. 4CSCh. 9 - Prob. 1.1VCCh. 9 - Prob. 1.2VCCh. 9 - Prob. 1.3VCCh. 9 - Prob. 1.4VCCh. 9 - Prob. 1.5VCCh. 9 - Prob. 2.1VCCh. 9 - Prob. 2.2VCCh. 9 - Prob. 2.3VC
Knowledge Booster
Learn more about
Need a deep-dive on the concept behind this application? Look no further. Learn more about this topic, operations-management and related others by exploring similar questions and additional content below.Similar questions
- Karina Nieto works for New Products Inc., and one of hermany tasks is assigning new workers to departments. Thecompany recently hired six new employees and would likeeach one to be assigned to a different department. The em-ployees have completed a two-month training session ineach of the six departments from which they received theevaluations shown below (higher numbers are better).Determine how the new employees should be assigned todepartments so that overall performance is maximized.arrow_forwardA producer of inkjet printers is planning to add a new line of printers, and you have been asked to balance the process, given the following task times and precedence relationships. Assume that cycle time is to be the minimum possible. Task Length(minutes) Immediate(Predecessor) a 0.2 - b 0.4 a c 0.3 - d 1.3 b, c e 0.1 - f 0.8 e g 0.3 d, f h 1.2 g Click here for the Excel Data File a. Do each of the following: (1) Enter the number of following tasks for each of the tasks shown in the table below. (2) Assign tasks to stations in order of greatest number of following tasks. Use greatest positional weight as a tiebreaker rule. (3) Determine the percentage of idle time. (Round your answer to 2 decimal places.) (4) Compute the rate of output in printers per day that could be expected for this line, assuming a 420-minute working day. (Round your answer 2 decimal places.) b. Answer these questions: (1) What is the…arrow_forwardA local toy maker uses a manufacturing line running eight hours a day that produces a toy which needs 7 tasks in total. The regular requirements are 100 toys. Task times are 2.73,2.01,2.13,2.0.2.11,2.71 and A,B,C,D,E,F and G, respectively, 2.95 minutes. However, there are precedent laws because of the essence of the substance that must be followed. This type of task has no predecessors; task B needs the completion of task A. To begin task C and task D, each task requires the completion of task B. Mission must be done until task E is defined. Goal F has to be done with Task D and Task Finally, task G will only start until task Fis has been completed. Since we extend the remaining job rule to balance the production line with the linkage broken in the longest working period, check circle is the task allocated to the THIRD stationarrow_forward
- If the cycle time is 65.4 seconds and A is assigned as the first task in Workstation #1, what is the idle time after assigning task A? Task Task Time (seconds) Tasks That Must Precede Other Tasks Number of Following Tasks A 28 - 7 B 13 - 8 C 35 B 7 D 11 A 6 E 20 C 6 F 6 D, E 5 G 23 F 3 H 25 F 2 I 37 G 1 J 11 G, H 1 K 27 I, J 0 Total 236 a. 26.9 minutes b. 37.4 seconds c. 28.5 seconds d. 31.6 seconds e. 57.6 secondsarrow_forward(Note: Task N is a dummy task. It must be included in the relationships, but its duration is 0. Be sure its duration is set to 0) Please see attached charts and diagram. Assign the following resources to the tasks. All resources will be full time. (Set the leveling to manual first). Task Resource Cost / Day A R1 200 B R2 300 C R3 300 D R4 300 E R2 300 F R4 300 G R1 200 H R5 200 I R6 400 J R5 200 K R1 200 L R3 300 M R2 300 N - - 2. Level if necessary. Then determine the new critical path and duration. 3. What is the total cost of the project (Fixed + Resource cost)? How much does the project need in the first, second, and third weeks?arrow_forward(Note: Task N is a dummy task. It must be included in the relationships, but its duration is 0. Be sure its duration is set to 0) Please see attached charts and diagram. Assign the following resources to the tasks. All resources will be full time. (Set the leveling to manual first). Task Resource Cost / Day A R1 200 B R2 300 C R3 300 D R4 300 E R2 300 F R4 300 G R1 200 H R5 200 I R6 400 J R5 200 K R1 200 L R3 300 M R2 300 N - - 1. Check for over-allocation. Which resources are over allocated? 2. Level if necessary. Then determine the new critical path and duration. 3. What is the total cost of the project (Fixed + Resource cost)? How much does the project need in the first, second, and third weeks?arrow_forward
- Alocal toy manufacturer is using a production line that runs 8 hours per day and produces a toy that requires a total of 7 tasks to be performied. The daily demand is 150 toys. Times of the tasks are 2.73, 2.01, 2.13, 2.0, 2.61, 2.71, and 2.95 minutes for A, B, C, D, E, F, and G, respectively. However, due to the nature of the product there are precedence rules that must be observed. Such that Task A does not need any predecessors; task B requires taskA to be completed. To start task Cand task D, each require task B to be completed. Task C must be completed prior to stating task E. Task F needs both task D and task Eto be completed. Finally, task G can start only once taskFis completed.What is the minimum number of workstations needed?arrow_forwardAlocal toy manufacturer is using a production line that runs 8 hours per day and produces a toy that requires a total of 7 tasks to be performed. The daily demand is 100 toys. Times of the tasks are 2.73, 2.01 201 2.13, 2.0, 2.61, 2.71 , and 2.95 minutes for A,B,C,D,E,F, and respectively. However, due to the nature of the product there are precedence rules that must be observed. Such that Task Adoes not need any predecessorsB requires task A to completed. To start task C and task Deach require task B to be completed. Task C must be completed prior to stating task E. Task F needs both task D and task Eto be completed. Finally, task G can start only once task Fis completed.Given we apply the most remaining tasks rule for balancing the assembly line with ties broken according to longest task time firstthe tasks that will be assigned to the SECOND workstation arearrow_forwardGiven this list of tasks, how much idle time is at station 3 if the cycle time is 15 minutes and the Longest Operation Time heuristic is used? Task Duration (min) Predecessor A 8 -- B 7 A C 9 B D 6 C E 7 C F 7 D,E G 9 F H 12 G ANSWER Unselected 3 minutes Unselected 2 minutes Unselected 1 minute Unselected I DON'T KNOW YETarrow_forward
- Eddys Pizza is currently redesigning its order-processing and pizza-making procedures for itsoperations which usually start at 5pm and close at 2am. For Eddys to meet customers’ speedydelivery requirement, six elements must be completed as summarised in the table below.WorkElementDescription Precedence Time (Mins)1 Receive customer order - 32 Shape dough 1 23 Prepare toppings 1 34 Assemble Pizza 2, 3 45 Bake pizza 4 46 Select complementary drink - 17 Deliver pizza 5, 6 4i. Draw the precedence diagram for the pizza making process.ii. If the demand for pizza is 90 pieces during the operating time, calculate the desired cycletime iii. Balance the line and calculate its efficiencyarrow_forwardKiko Teddy Bear is a manufacturer of stuffed teddy bears. Kiko would like to be able to produce 40 teddy bears per hour on its assembly line. The following information will assist in answering the questions that follow: Task Information for Kiko Teddy Bear Work Element Task Description Immediate Predecessor Task time (in seconds) A Cut teddy bear pattern None 90 B Sew teddy bear cloth a 75 C stuff teddy bear b 50 D glue on eyes c 20 E glue on nose c 15 F sew on mouth c 35 G attach manufacturer's label b 15 H Inspect and pack teddy bear d,e,f,g 40 a. Draw a precedence diagram. b. What cycle time would provide the desired output? c. What is the maximum possible output of the line? d. What is the theoretical minimum number of workstations using the cycle time computed in” b “ above? e. Assign tasks to workstations using the cycle time in “b” above. f. Calculate the efficiency and idle time percentage of the line.arrow_forwardUpdike Upholstery cuts and sews fabric for customordered chairs, ottomans, and sofas. Often, the more com-plicated patterns are for the smaller pieces, where cuttingis more time consuming than sewing. Thus, cutting andsewing times vary. Today’s list of jobs, shown below, arefor an important customer who needs them shipped out(in one shipment) as soon as possible. Determine thesequence of jobs that will complete the customer’s orderas quickly as possible, and notify the customer when theorder is expected to ship.arrow_forward
arrow_back_ios
SEE MORE QUESTIONS
arrow_forward_ios
Recommended textbooks for you
- Practical Management ScienceOperations ManagementISBN:9781337406659Author:WINSTON, Wayne L.Publisher:Cengage,Operations ManagementOperations ManagementISBN:9781259667473Author:William J StevensonPublisher:McGraw-Hill EducationOperations and Supply Chain Management (Mcgraw-hi...Operations ManagementISBN:9781259666100Author:F. Robert Jacobs, Richard B ChasePublisher:McGraw-Hill Education
- Purchasing and Supply Chain ManagementOperations ManagementISBN:9781285869681Author:Robert M. Monczka, Robert B. Handfield, Larry C. Giunipero, James L. PattersonPublisher:Cengage LearningProduction and Operations Analysis, Seventh Editi...Operations ManagementISBN:9781478623069Author:Steven Nahmias, Tava Lennon OlsenPublisher:Waveland Press, Inc.
Practical Management Science
Operations Management
ISBN:9781337406659
Author:WINSTON, Wayne L.
Publisher:Cengage,
Operations Management
Operations Management
ISBN:9781259667473
Author:William J Stevenson
Publisher:McGraw-Hill Education
Operations and Supply Chain Management (Mcgraw-hi...
Operations Management
ISBN:9781259666100
Author:F. Robert Jacobs, Richard B Chase
Publisher:McGraw-Hill Education
Purchasing and Supply Chain Management
Operations Management
ISBN:9781285869681
Author:Robert M. Monczka, Robert B. Handfield, Larry C. Giunipero, James L. Patterson
Publisher:Cengage Learning
Production and Operations Analysis, Seventh Editi...
Operations Management
ISBN:9781478623069
Author:Steven Nahmias, Tava Lennon Olsen
Publisher:Waveland Press, Inc.
Inventory Management | Concepts, Examples and Solved Problems; Author: Dr. Bharatendra Rai;https://www.youtube.com/watch?v=2n9NLZTIlz8;License: Standard YouTube License, CC-BY