a)

Summary Introduction

To determine: The cost of plan A layout.

Introduction: Process layout refers to the plan or graphical representation about the design of the floor of a plant. It helps the firm to improve the efficiency of the design and it would help to improve the location of the departments.

a)

Expert Solution
Check Mark

Answer to Problem 2P

The cost of plan A layout is $23,400.

Explanation of Solution

Given information:

Given the distances in feet from one department to the other as follows

EBK PRINCIPLES OF OPERATIONS MANAGEMENT, Chapter 9, Problem 2P , additional homework tip  1

And the work pieces moved from one department to the other as follows

EBK PRINCIPLES OF OPERATIONS MANAGEMENT, Chapter 9, Problem 2P , additional homework tip  2

Calculation of cost of plan A layout:

Calculate the total weekly material handling cost, MH cost using the formula

MHcost=i=1nj=1nxij×Cij (1)

where   n= total number of departments

i,j = individual departments

xij= number of loads moved from department i to department j

Cij= cost to move an item from department i to department j

Substitute into the equation (1), the various values to obtain

MtoD=20×600×$0.5=$6,000MtoF=12×1,800×$0.5=$10,800MtoP=8×200×$0.5=$800

DtoF=400×6×$0.5=$1,200DtoP=200×10×$0.5=$1,000FtoP=4×1,800×$0.5=$3,600

Add all the costs to obtain the total material handling costs $23,400_ .

Hence, the cost of plan A layout is $23,400.

b)

Summary Introduction

To determine: The cost of the layout.

b)

Expert Solution
Check Mark

Answer to Problem 2P

The cost of the layout is $20,600.

Explanation of Solution

Given information:

Given the distances in feet from one department to the other as follows

EBK PRINCIPLES OF OPERATIONS MANAGEMENT, Chapter 9, Problem 2P , additional homework tip  3

And the work pieces moved from one department to the other as follows

EBK PRINCIPLES OF OPERATIONS MANAGEMENT, Chapter 9, Problem 2P , additional homework tip  4

Calculation of cost of the layout:

After switching departments F and P, calculate the total material handling cost, MH cost using the formula

Calculate the total weekly material handling cost, MH cost using the formula

MHcost=i=1nj=1nxij×Cij (2)

where   n= total number of departments

i,j = individual departments

xij= number of loads moved from department i to department j

Cij= cost to move an item from department i to department j

Substitute in equation (2), the various values to obtain

MtoD=20×600×$0.5=$6,000MtoF=8×1,800×$0.5=$7,200MtoP=12×200×$0.5=$1,200

DtoF=400×10×$0.5=$2,000DtoP=200×6×$0.5=$600FtoP=4×1,800×$0.5=$3,600

Add all the costs to obtain the total material handling costs $20,600_

Hence, the cost of the layout is $20,600.

c)

Summary Introduction

To determine: The cost of the layout.

c)

Expert Solution
Check Mark

Answer to Problem 2P

The cost of the layout is $22,000.

Explanation of Solution

Given information:

Given the distances in feet from one department to the other as follows

EBK PRINCIPLES OF OPERATIONS MANAGEMENT, Chapter 9, Problem 2P , additional homework tip  5

And the work pieces moved from one department to the other as follows

EBK PRINCIPLES OF OPERATIONS MANAGEMENT, Chapter 9, Problem 2P , additional homework tip  6

Calculation of cost of the layout:

After switching departments M and D, calculate the total material handling cost, MH cost using the formula

Calculate the total weekly material handling cost, MH cost using the formula

MHcost=i=1nj=1nxij×Cij (3)

where   n= total number of departments

i,j = individual departments

xij= number of loads moved from department i to department j

Cij= cost to move an item from department i to department j

Substitute in equation (3), the various values to obtain

MtoD=20×600×$0.5=$6,000MtoF=10×1,800×$0.5=$9,000MtoP=6×200×$0.5=$600

DtoF=400×8×$0.5=$1,600DtoP=200×12×$0.5=$1,200FtoP=4×1,800×$0.5=$3,600

Add all the costs to obtain the total material handling costs $22,000_ .

Hence, the cost of the layout is $22,000.

d)

Summary Introduction

To determine: The best layout in terms of cost perspective.

d)

Expert Solution
Check Mark

Explanation of Solution

Best layout in terms of cost perspective:

From above calculations, the cost perspective, Plan B which has the total material handling costs of $20,600 is cost effective than other plans.

Hence, Plan B is the best layout.

Want to see more full solutions like this?

Subscribe now to access step-by-step solutions to millions of textbook problems written by subject matter experts!
Students have asked these similar questions
Maureen Marcy is designing the layout for a new business in town. The Collegiate Spa. From visiting spas in neighboring towns, she has compiled the following data on movement between spa activities. Help Maureen determine where to locate each activity on a 2 × 3 grid so that nonadjacent moves are                                            1      2      3      4      5      6    1. Relaxation lounge   50 25   75   2. Facial 10         75 3. Massage 30     50   50 4. Power shower           25 5. Mineral bath   50       50 6. Sauna
Three graduates who recently graduated from the College of Law are considering opening a law office in that would make inexpensive legal services available to those who could not afford these services elsewhere. The intent is to provide easy access for their clients by having the office open 300 days a year, 8 hours each day from 8 A.M. to 4 P.M. The office will be staffed by a lawyer, assistant, secretary, and receptionist. To assist with market projections and to determine the feasibility of this project, the three graduates hired a management accountant who graduated from the College of Business and Economics of 8 years ago. The results of this market study show that if the firm spends USD 500,000 on advertising in the first year, the number of new clients expected each day may have the following probability distribution: Number of new clients per day   Probability            Expected Outcome 20                                 0.1                                2 30…
Three graduates who recently graduated from the College of Law are considering opening a law office in that would make inexpensive legal services available to those who could not afford these services elsewhere. The intent is to provide easy access for their clients by having the office open 300 days a year, 8 hours each day from 8 A.M. to 4 P.M. The office will be staffed by a lawyer, assistant, secretary, and receptionist. To assist with market projections and to determine the feasibility of this project, the three graduates hired a management accountant who graduated from the College of Business and Economics of 8 years ago. The results of this market study show that if the firm spends USD 500,000 on advertising in the first year, the number of new clients expected each day may have the following probability distribution: Number of new clients per day   Probability            Expected Outcome 20                                 0.1                                2 30…
Knowledge Booster
Background pattern image
Operations Management
Learn more about
Need a deep-dive on the concept behind this application? Look no further. Learn more about this topic, operations-management and related others by exploring similar questions and additional content below.
Similar questions
SEE MORE QUESTIONS
Recommended textbooks for you
Text book image
Practical Management Science
Operations Management
ISBN:9781337406659
Author:WINSTON, Wayne L.
Publisher:Cengage,