Question
Chapter 9.6, Problem 7P
Summary Introduction
Interpretation: The sequence of the projects that the individual should followin order to minimize the maximum lateness is to be determined.
Concept Introduction: The activities under a project are programmed based on the needs of the individual and attaining ease is the priority of the individual.
Expert Solution & Answer
Want to see the full answer?
Check out a sample textbook solutionStudents have asked these similar questions
Using the FCFS rule for scheduling, the sequence is 1-2-3
For the schedule developed using the FCFS rule, the total length of time taken to
complete the three suits (including delivery) : hours (enter your response as a
whole number).
=
G
Sunny Park Tailors has been asked to make three different types of wedding suits
for separate customers. The table below highlights the time taken in hours for
cutting and sewing (process 1) and delivery (process 2) of each of the suits.
Times Taken for Different Activities (hours)
Cut and Sew
3
5
6
Suit
1
2
7
3
Deliver
4
2
∞ N
8
Assume that orders for suits have been listed in the above table in the order in
which they were received.
Using the FCFS rule for scheduling,
the sequence is 1-2-3.
For the schedule developed using the
FCFS rule, the total length of time
taken to complete the three suits
(including delivery) = hours (enter
your response as a whole number).
Sunny Park Tailors has been asked to make three different types of
wedding suits for separate customers. The table below highlights the
time taken in hours for cutting and sewing (process 1) and delivery
(process 2) of each of the suits.
Times Taken for Different Activities (hours)
Cut and Sew
Suit
1
2
3
6
5
8
Deliver
324
2
4
Assume that orders for suits have been listed in the above table in the
order in which they were received.
snip
Chapter 9 Solutions
EBK PRODUCTION AND OPERATIONS ANALYSIS
Ch. 9.5 - Prob. 1PCh. 9.5 - Prob. 2PCh. 9.5 - Prob. 3PCh. 9.5 - Prob. 4PCh. 9.5 - Prob. 5PCh. 9.6 - Prob. 6PCh. 9.6 - Prob. 7PCh. 9.6 - Prob. 8PCh. 9.6 - Prob. 9PCh. 9.6 - Prob. 10P
Ch. 9.7 - Prob. 11PCh. 9.7 - Prob. 12PCh. 9.7 - Prob. 13PCh. 9.7 - Prob. 14PCh. 9.7 - Prob. 15PCh. 9.7 - Prob. 16PCh. 9.7 - Prob. 17PCh. 9.8 - Prob. 18PCh. 9.8 - Prob. 19PCh. 9.8 - Prob. 20PCh. 9.8 - Prob. 21PCh. 9.8 - Prob. 22PCh. 9.9 - Prob. 23PCh. 9.9 - Prob. 24PCh. 9.9 - Prob. 25PCh. 9.10 - Prob. 27PCh. 9.10 - Prob. 28PCh. 9.10 - Prob. 29PCh. 9 - Prob. 30APCh. 9 - Prob. 31APCh. 9 - Prob. 32APCh. 9 - Prob. 33APCh. 9 - Prob. 34APCh. 9 - Prob. 35APCh. 9 - Prob. 36APCh. 9 - Prob. 37APCh. 9 - Prob. 38APCh. 9 - Prob. 39APCh. 9 - Prob. 40APCh. 9 - Prob. 41APCh. 9 - Prob. 42APCh. 9 - Prob. 43APCh. 9 - Prob. 44APCh. 9 - Prob. 45APCh. 9 - Prob. 46APCh. 9 - Prob. 47AP
Knowledge Booster
Learn more about
Need a deep-dive on the concept behind this application? Look no further. Learn more about this topic, operations-management and related others by exploring similar questions and additional content below.Similar questions
- A nursing home must schedule nurses in a manner that balances providing adequate patient care while keeping costs down. From historical records, administrators can project the minimum number of nurses to have on hand during each day/time slot. This data is shown below. Shift Time Slot Minimum number of nurses needed 1 12 am-4 10 2 4 am-8 6 3 8 am-12 8 4 12 pm-4 12 5 4 pm-8 10 6 8 pm-12 14 Nurses must start work at the beginning of one of the four-hour shifts (starting as early as 12 am midnight or as late as 8pm evening) and work for eight hours. Nurses who begin working at 8 pm will work until 4 am the next morning. Formulate and solve the nurse-scheduling problem so as to minimize excess stagging while satisfying minimum staffing requrements. What is the value of total excess staffing?arrow_forwardK Using the FCFS rule for scheduling, the sequence is 1-2-3 For the schedule developed using the FCFS rule, the total length of time taken to complete the three suits (including delivery) = hours (enter your response as a whole number). Sunny Park Tailors has been asked to make three different types of wedding suits for separate customers. The table below highlights the time taken in hours for cutting and sewing (process 1) and delivery (process 2) of each of the suits. Times Taken for Different Activities (hours) Cut and Sew Suit 1 2 3 7 4 5 Deliver 2 3 6 Assume that orders for suits have been listed in the above table in the order in which they were received Darrow_forwardsniparrow_forward
- The following jobs are waiting to be processed at Rick Solano’s machine center. Solano’s machine center has a relatively long backlog and sets a fresh schedule every 2 weeks, which does not disturb earlier schedules. Below are the jobs received during the previous 2 weeks. They are ready to be scheduled today, which is day 241 (day 241 is a workday). Job names refer to names of clients and contract numbers. Job Date job received Productiondays needed Date job due BR-02 228 15 300 CX-01 225 25 270 DE-06 230 35 320 RG-05 235 40 360 SY-11 231 30 310 a. Complete the following table. (Show your supporting calculations.) b.Which dispatching rule has the best score for flow time? c. Which dispatching rule would you select? Support your decision.arrow_forwardThomas has four assignments due in class tomorrow, and his class times are as follows. Class Time Marketing 304 8 am OM 385 10 am Finance 216 2 pm Psychology 4:30 pm Each class lasts one hour, and Thomas has no other classes. It is now midnight, and Thomas estimates that the marketing, OM, finance, and psychology assignments will take him six, three, four, and two hours, respectively. Use the Excel Sequencing template to determine how he should schedule the work. Can he complete all of it on time? (Hint: Using SPT and EDD. First, convert times to due dates past midnight).arrow_forwarda-b) Using Johnson's rule for 2-machine scheduling, the sequence is: Scheduled Order Job V 1 2 3 4 5 6 7 NDX W Y c) For the schedule developed using Johnson's rule, the total length of time taken to complete the seven printing and binding jobs (including binding) = hours (enter your response as a whole number). W The following set of seven jobs is to be processed through two work centers at George Heinrich's printing company. The sequence is first printing, then binding. Processing time at each of the work centers is shown in the following table: Job >>> W X > N T U V Y Printing (hours) Binding (hours) 4 12 8 693556 7 14 2 10 1 13arrow_forward
- On Monday morning, Baxter Industries has the following jobs waiting for processing in two departments, milling, and drilling, in that order. Time Required (hours) Job Mill Drill 216 7 11 327 6 10 462 8 4 519 5 8 258 3 5 617 12 15 Develop a minimum makespan schedule using Johnson's rule. The schedule using Johnson's rule is - - - - - . Choose the correct Gantt chart with the minimum makespan schedule. The correct graph is .arrow_forwardA defense contractor in Dallas has six jobs awaiting processing. Processing time and due dates are given in the table. Assume that jobs arrive in the order shown. Compare the average completion time, utilization, average jobs in the system and average job lateness of the following scheduling rules. Start date is day 1. a) SPT: shortest processing time and b) EDD: earliest due datearrow_forwardRon Satterfield's excavation company uses both Ganit scheduling charts and Gantt load charts. Today, which is the end of day 7, Ron is reviewing the Gantt chart depicting these schedules: Job #151 was scheduled to begin on day 3 and to take 5 days. It got started on time and is 1 day ahead of schedule. Job #177 was scheduled to begin on day 1 and take 4 days. It is currently on time. Job #179 was scheduled to start on day 6 and take 2 days. It actually got started on day 5 and is progressing according to plan. Job #211 was scheduled to begin on day 5, but missing equipment delayed it until day 6. It is progressing as expected and should take 3 days. Job #215 was scheduled to begin on day 5 and take 5 days. It got started on time but has since fallen behind 1 day. This exercise contains only part a a) Add the actual progress to the Gantt schedule shown on the right (on which the planned timings have been already plotted as blue lines). Using the line drawing tool, plot the actual…arrow_forward
- Using Johnson's rule for 2-machine scheduling, the sequence is: Scheduled Order Job 1 2 3 11 4 5 6 For the schedule developed using Johnson's rule, the total length of time taken to complete the six jobs (including the 2nd operation) = hours (enter your response as a whole number). Six jobs are to be processed through a two-step operation. The first operation involves sanding, and the second involves painting. Processing times are as follows: Job A amoa I - B C D E Operation 1 (hours) 4 10 3 14 6 7 Operation 2 (hours) 8 51112 14arrow_forwardRon Satterfield's excavation company uses both Gantt scheduling charts and Gantt load charts. Today, which is the end of day 7, Ron is reviewing the Gantt chart depicting these schedules: Job #151 was scheduled to begin on day 3 and to take 7 days. It got started on time and is 1 day ahead of schedule. Job #177 was scheduled to begin on day 3 and take 5 days. It is currently on time. Job #179 was scheduled to start on day 6 and take 3 days. It actually got started on day 5 and is progressing according to plan. Job #211 was scheduled to begin on day 5, but missing equipment delayed it until day 6. It is progressing as expected and should take 3 days. Job #215 was scheduled to begin on day 4 and take 5 days. It got started on time but has since fallen behind 2 days. This exercise contains only part a. a) Add the actual progress to the Gantt schedule shown on the right (on which the planned timings have been already plotted as blue lines). Using the line drawing tool, plot the actual…arrow_forwardUsing the FCFS rule for scheduling, the sequence is ▼ 1-3-2 3-1-2 1-2-3 2-1-3 2-3-1 3-2-1 . Part 2 For the schedule developed using the FCFS rule, the total length of time taken to complete the three suits (including delivery) = enter your response here hours (enter your response as a whole number). Part 3 Using Johnson's rule for 2-machine scheduling, the sequence is ▼ 3-1-2 1-2-3 2-1-3 3-2-1 2-3-1 1-3-2 . Part 4 For the schedule developed using the Johnson's rule, the total length of time taken to complete the three suits (including delivery) = enter your response here hours (enter your response as a whole number). Part 5 Of the two developed schedules, ▼ Johnson's the FCFS rule gets the schedule finished sooner. ... Question content area right Part 1 Sunny Park Tailors has been asked to make three different types of wedding suits for separate customers. The table below highlights the time taken in hours for cutting and sewing…arrow_forward
arrow_back_ios
SEE MORE QUESTIONS
arrow_forward_ios
Recommended textbooks for you
- Practical Management ScienceOperations ManagementISBN:9781337406659Author:WINSTON, Wayne L.Publisher:Cengage,Operations ManagementOperations ManagementISBN:9781259667473Author:William J StevensonPublisher:McGraw-Hill EducationOperations and Supply Chain Management (Mcgraw-hi...Operations ManagementISBN:9781259666100Author:F. Robert Jacobs, Richard B ChasePublisher:McGraw-Hill Education
- Purchasing and Supply Chain ManagementOperations ManagementISBN:9781285869681Author:Robert M. Monczka, Robert B. Handfield, Larry C. Giunipero, James L. PattersonPublisher:Cengage LearningProduction and Operations Analysis, Seventh Editi...Operations ManagementISBN:9781478623069Author:Steven Nahmias, Tava Lennon OlsenPublisher:Waveland Press, Inc.
Practical Management Science
Operations Management
ISBN:9781337406659
Author:WINSTON, Wayne L.
Publisher:Cengage,
Operations Management
Operations Management
ISBN:9781259667473
Author:William J Stevenson
Publisher:McGraw-Hill Education
Operations and Supply Chain Management (Mcgraw-hi...
Operations Management
ISBN:9781259666100
Author:F. Robert Jacobs, Richard B Chase
Publisher:McGraw-Hill Education
Purchasing and Supply Chain Management
Operations Management
ISBN:9781285869681
Author:Robert M. Monczka, Robert B. Handfield, Larry C. Giunipero, James L. Patterson
Publisher:Cengage Learning
Production and Operations Analysis, Seventh Editi...
Operations Management
ISBN:9781478623069
Author:Steven Nahmias, Tava Lennon Olsen
Publisher:Waveland Press, Inc.
Inventory Management | Concepts, Examples and Solved Problems; Author: Dr. Bharatendra Rai;https://www.youtube.com/watch?v=2n9NLZTIlz8;License: Standard YouTube License, CC-BY