Bowman Builders manufactures steel storage sheds for commercial use. Joe Bowman, president of Bowman Builders, is contemplating producing sheds for home use. The activities necessary to build an experimental model and related data are given in Table B.2.
- a. What is the project normal time completion date? (See Chapter 3 for a review of project management.)
- b. Formulate an LP problem to crash this project to 10 weeks.
TABLE B.2 Data for Problem B.29
Expert Solution & Answer
![Check Mark](/static/check-mark.png)
Want to see the full answer?
Check out a sample textbook solution![Blurred answer](/static/blurred-answer.jpg)
Students have asked these similar questions
Students shall, with a point of view of him/herself as project manager (PM), submit a Project Management Plan (PMP) for the given engineering project below: - “Procurement & Installation of Emergency Generator at Fire station” Students are allowed to propose their own project, given that the projects shall have enough scale to address the element described below:- a. Student should produce a project definition statement regarding the proposed project. b. Student should propose a suitable project team to carry out the project. Student should in the PMP describe the duties and power of different team memebrs in the project. c. The PMP shall include a risk management plan, which student shall identify, analyse and proposed mitigations measures for smooth delivery of the project deliverables. The risk manamgenet plan shall include a risk register d. The PMP shall include a quality management plan, which student shall propose a method statement to control the quality of the delivery of…
Q1. Project Planning and Quality Management:
a) Develop a comprehensive project plan that includes the scope, objectives, timeline, and
resource requirements for the development and production of the product related to Central
Cable Berhad (CCB).
b) Identify key quality management principles that will be crucial in ensuring the product meets
industry standards and customer expectations.
c) Propose a quality control plan outlining methods, tools, and checkpoints to ensure the
consistent quality of the electric wires.
Activity 3: Scenarios of a project activities (tables given below) and their required times to be
completed in addition to their predecessors for developing a Website":
Activity Description
Duration (days) Preceding Activities
A
Determine user needs
9
в
Review s/w and languages
7
Purchase software
9.
D
Design format and style
B.
E
Write programs
7
Review outcome product
with user
F
10
G
Make revisions
C
H
Select server site
8
E
Install on server
11
D, F
Test
G, H, I
1. Draw the path.
2. Calculate the carly finishing time (forwards calculations)
3. Highlight the total time to complete the project (days or weeks)
4. Calculate the late finishing time (backwards calculations)
5. Calculate the slack time of the non-critical path activities
6. Identify the critical path (highlight critical path activities)
7. what would happen if revised to take seven weeks instead of five weeks
Chapter B Solutions
EBK OPERATIONS MANAGEMENT
Ch. B - Prob. 1DQCh. B - Prob. 2DQCh. B - Prob. 3DQCh. B - Prob. 4DQCh. B - Prob. 5DQCh. B - Prob. 6DQCh. B - Prob. 7DQCh. B - Prob. 8DQCh. B - Prob. 9DQCh. B - Prob. 10DQ
Ch. B - Prob. 11DQCh. B - Where a constraint crosses the vertical or...Ch. B - Prob. 13DQCh. B - Prob. 1PCh. B - Prob. 2PCh. B - Prob. 3PCh. B - B.4. Consider the following linear programming...Ch. B - Prob. 5PCh. B - Prob. 6PCh. B - Prob. 7PCh. B - Prob. 8PCh. B - Green Vehicle Inc. manufactures electric cars and...Ch. B - Prob. 10PCh. B - Prob. 11PCh. B - Prob. 12PCh. B - The LP relationships that follow were formulated...Ch. B - Prob. 14PCh. B - Prob. 15PCh. B - Prob. 16PCh. B - Prob. 17PCh. B - Prob. 18PCh. B - Prob. 19PCh. B - Prob. 20PCh. B - Prob. 21PCh. B - Prob. 22PCh. B - Prob. 23PCh. B - How many corner points are there in the feasible...Ch. B - Prob. 25PCh. B - Prob. 26PCh. B - A fertilizer manufacturer has to fulfill supply...Ch. B - Prob. 28PCh. B - Bowman Builders manufactures steel storage sheds...Ch. B - Prob. 30PCh. B - Quain Lawn and Garden, Inc Bill and Jeanne Quain...Ch. B - Quain Lawn and Garden, Inc Bill and Jeanne Quain...
Knowledge Booster
Learn more about
Need a deep-dive on the concept behind this application? Look no further. Learn more about this topic, operations-management and related others by exploring similar questions and additional content below.Similar questions
- 1. Using Microsoft Excel TM prepare a Gantt Chart for the following project. Activity Predecessor(s) Duration (Days) 1. Forming the problem statement 2. Identifying functional requirements 3. Identifying constraints and limitations 4. Defining a schedule 5. Defining the design parameters 6. Identifying alternatives 7. Evaluating and analyzing alternatives 8. Select a solution 9. Gather supplies 10. Construct prototype 11. Test performance 12. 1 1 1 1 1 2,3 1 2 1 2 7 1 8 4 10 1 Redesign 13. 11 2 Demonstrate solution to 12 1 class 5 COarrow_forwardQ.No.7. Consider the following diagram, why is it used and explain what information does it provide to the Project Manager.arrow_forwardEX6-12 (Algo) You are creating a customer database... You are creating a customer database for the Lehigh Valley IronPigs minor league baseball team. Given the information below, complete the forward and backward pass, compute activity slack, and identify the critical path. How long will this project take? ABCDACHSX K L Description Systems Subsystem A design Subsystem B design Subsystem C design Program A Program B Program C Subsystem A test Subsystem B test Subsystem C test Integration Integration test days. Predecessor None A A A B с D E F G H, I, J K Time (days) 7 3 1 3 5 15 5 3 3 5 3arrow_forward
- Activity Preceded By ABCDEFG А ww ww A B,C D E BC F. G Expected Time Regular Crash 6 days 2 day 12 6 4 10 8 C 18 6 2 6 6 2 8 4 Direct Cost Regular Crash $2000 $3800 2000 10000 4000 4600 3900 5000 7600 16000 19600 2000 4000 1000 3400 2800 Requested: (a) Construct a network including the Early and Late Start and Finish times. (b) Identify the normal Critical Path(s) and the normal expected completion time (c) Can the project be crashed to last 18 days? Which activities should be crashed and at what additional cost?arrow_forwardQ1 ) Scenarios of a project activities (tables given below) and their required times to be completed in addition to their predecessors for developing a ‘Website’: Activity Description Duration (weeks) Preceding Activities A Determine user needs 8 -- B Review s/w and languages 4 -- C Purchase software 10 -- D Design format and style 10 B E Write programs 6 A F Review outcome product with user 12 C G Make revisions 4 C H Select server site 8 E I Install on server 14 D,F J Test 8 G,H,I Draw the path. Calculate the early finishing time (forwards calculations) Highlight the total time to complete the project (days) Calculate the late finishing time (backwards calculations) Calculate the slack time of the non-critical path activities Identify the critical path (highlight critical path activities) what would happen if activity D revised to take 14 instead of 10 days?arrow_forward17. What is the minimum cost of crashing the following project at Sawaya Robotics by 4 days? Activity Normal Time (days) Crash Time (days) Normal Cost Crash Cost Immediate Predecessor(s) Design 6 5 $900 $1,000 - Wiring 8 6 300 400 - Chip install 4 3 500 600 - Software 5 3 900 1,200 A, B Testing 8 5 1,000 1,600 C Part 2 a)The minimum cost of crashing the following project by 4 days is $ _____ (enter your response as a whole number).arrow_forward
- Project Managent 11. Explain concept of risk management in projects. b. Explain the importance of planning and monitoring and controlling scope on a project.arrow_forward21. The following table provides the information necessary to construct a project network and project crash data: Activity (i, j) Activity Predecessor Activity Time (weeks) Normal Crash Activity Cost Normal Crash a (1,2) --- 16 8 $2000 $4400 b (1,3) --- 14 9 1000 1800 c (2,4) a 8 6 500 700 d (2,5) a 5 4 600 1300 e (3,5) b 4 2 1500 3000 f (3,6) b 6 4 800 1600 g (4,6) c 10 7 3000 4500 h (5,6) d, e 15 10 5000 8000 a. Construct the project network b. Manually crash the network to 28 weeks Note:- Do not provide handwritten solution. Maintain accuracy and quality in your answer. Take care of plagiarism. Answer completely. You will get up vote for sure.arrow_forward36 Which of the following factor that causes a change in the cost of an activity? a. Cost objective b. Cost driver c. Activity d. Cost allocationarrow_forward
- a. Introduction PPE GLOVEb. Objective of Project/Manufacturing Processc. History of Company/Product (PPE GLOVE)arrow_forwardPlease do not give solution in image format thanku For the project of construction of a state of the art spacious, heated, and enclosed bus stop shelter located in Downtown New york near the University of New York on OCTranspo’s main transit line. The project budget is not to exceed $10M and it should be completed in less than one year. For the above project, the following are required:a) What could be the justifications for carrying out such a project in the area? List ten project deliverables taking into account major purpose, being creative and environmentally friendly (be aware of the above project constraints).b) Consider all possible stakeholders falling under the two main groups; internal and external. Create a simple stakeholder register table. Include the following categories; Name/Organization, role, type (internal/external), influence or impact, and interest.c) List three potential risks that the project may encounter knowing that the project is in phase 2; planning.arrow_forwardscenarios of a project activities (tables given below) and their required times to be completed in addition to their predecessors for developing a Website': Description Preceding Activities Activity Duration (days) Determine user needs Review s/w and languages Purchase software D. Design format and style 5 в E Write programs 3. A F Review outcome product with user 6. Make revisions C Select server site E Install on server D, F Test 4. G, H, I 1. Draw the path. 2. Calculate the carly finishing time (forwards calculations) 3. Highlight the total time to complete the project (days or weeks) 4. Calculate the late finishing time (backwards calculations) 5. Calculate the slack time of the non-critical path activities 6. Identify the critical path (highlight critical path activities) 7. what would happen if revised to take seven weeks instead of five weeksarrow_forward
arrow_back_ios
SEE MORE QUESTIONS
arrow_forward_ios
Recommended textbooks for you
- Practical Management ScienceOperations ManagementISBN:9781337406659Author:WINSTON, Wayne L.Publisher:Cengage,Operations ManagementOperations ManagementISBN:9781259667473Author:William J StevensonPublisher:McGraw-Hill EducationOperations and Supply Chain Management (Mcgraw-hi...Operations ManagementISBN:9781259666100Author:F. Robert Jacobs, Richard B ChasePublisher:McGraw-Hill Education
- Purchasing and Supply Chain ManagementOperations ManagementISBN:9781285869681Author:Robert M. Monczka, Robert B. Handfield, Larry C. Giunipero, James L. PattersonPublisher:Cengage LearningProduction and Operations Analysis, Seventh Editi...Operations ManagementISBN:9781478623069Author:Steven Nahmias, Tava Lennon OlsenPublisher:Waveland Press, Inc.
![Text book image](https://www.bartleby.com/isbn_cover_images/9781337406659/9781337406659_smallCoverImage.gif)
Practical Management Science
Operations Management
ISBN:9781337406659
Author:WINSTON, Wayne L.
Publisher:Cengage,
![Text book image](https://www.bartleby.com/isbn_cover_images/9781259667473/9781259667473_smallCoverImage.gif)
Operations Management
Operations Management
ISBN:9781259667473
Author:William J Stevenson
Publisher:McGraw-Hill Education
![Text book image](https://www.bartleby.com/isbn_cover_images/9781259666100/9781259666100_smallCoverImage.gif)
Operations and Supply Chain Management (Mcgraw-hi...
Operations Management
ISBN:9781259666100
Author:F. Robert Jacobs, Richard B Chase
Publisher:McGraw-Hill Education
![Text book image](https://www.bartleby.com/isbn_cover_images/9780135198100/9780135198100_smallCoverImage.gif)
![Text book image](https://www.bartleby.com/isbn_cover_images/9781285869681/9781285869681_smallCoverImage.gif)
Purchasing and Supply Chain Management
Operations Management
ISBN:9781285869681
Author:Robert M. Monczka, Robert B. Handfield, Larry C. Giunipero, James L. Patterson
Publisher:Cengage Learning
![Text book image](https://www.bartleby.com/isbn_cover_images/9781478623069/9781478623069_smallCoverImage.gif)
Production and Operations Analysis, Seventh Editi...
Operations Management
ISBN:9781478623069
Author:Steven Nahmias, Tava Lennon Olsen
Publisher:Waveland Press, Inc.
Inventory Management | Concepts, Examples and Solved Problems; Author: Dr. Bharatendra Rai;https://www.youtube.com/watch?v=2n9NLZTIlz8;License: Standard YouTube License, CC-BY