FUND. OF ACCT. W/CONNECT
FUND. OF ACCT. W/CONNECT
22nd Edition
ISBN: 9781260001136
Author: Wild
Publisher: MCG
bartleby

Concept explainers

bartleby

Videos

Question
Book Icon
Chapter C, Problem 1APSA
To determine

Concept Introduction:

Manufacturing overhead allocation:

Manufacturing overhead cost is the pool of all indirect costs incurred for the production. These are the costs which are not directly traceable to the product. Manufacturing costs include indirect material indirect labor and overheads. These costs are allocated to the products using the overhead allocation rate. The formula for overhead allocation rate is as follows:

Overhead allocation rate = Estimated Manufacturing overhead CostAllocation base 

Requirement-1:

To determine: Activity overhead rates

Expert Solution
Check Mark

Answer to Problem 1APSA

Solution: Activity overhead rates are as follows:

Activity Activity Rate
Grinding $ 24.62 Per Machine Hour
Polishing $ 10.38 Per Machine Hour
Product Modification $ 40.00 Per Engineering Hour
Providing Power $ 15.00 Per Direct Labor Hour
System Calibration $ 1,250.00 Per Batch

Explanation of Solution

Explanation: Activity overhead rates are calculated as follows:

Activity Overhead Cost Allocation base Activity Rate
  A B   = A/B
Grinding $ 320,000 13000 Machine Hours $ 24.62 Per Machine Hour
Polishing $ 135,000 13000 Machine Hours $ 10.38 Per Machine Hour
Product Modification $ 600,000 15000 Engineering Hours $ 40.00 Per Engineering Hour
Providing Power $ 255,000 17000 Direct Labor Hours $ 15.00 Per Direct Labor Hour
System Calibration $ 500,000 400 Batches $ 1,250.00 Per Batch
Conclusion

Conclusion: Hence, costs are allocated to the products using the overhead allocation rate.

To determine

Requirement-2:

To determine: The overhead Costs assigned to jobs

Expert Solution
Check Mark

Answer to Problem 1APSA

Solution: The overhead Costs assigned to jobs are as follows:

• Job 3175 = $74,650

• Job 4286 = $383,425

Explanation of Solution

Explanation: The overhead Costs assigned to jobs are calculated as follows:

Job 3175:        
Activity Allocation base Activity Rate Allocated Overhead Cost
  A   B =A*B
Grinding 550 Machine Hours $ 24.62 $ 13,538.46
Polishing 550 Machine Hours $ 10.38 $ 5,711.54
Product Modification 26 Engineering Hours $ 400.00 $ 10,400.00
Providing Power 500 Direct Labor Hours $ 15.00 $ 7,500.00
System Calibration 30 Batches $ 1,250.00 $ 37,500.00
Total Overhead Cost allocated to Job 3175 (C) $ 74,650.00
Job 4286:        
Activity Allocation base Activity Rate Allocated Overhead Cost
  A   B =A*B
Grinding 5500 Machine Hours $ 24.62 $ 135,384.62
Polishing 5500 Machine Hours $ 10.38 $ 57,115.38
Product Modification 32 Engineering Hours $ 400.00 $ 12,800.00
Providing Power 4375 Direct Labor Hours $ 15.00 $ 65,625.00
System Calibration 90 Batches $ 1,250.00 $ 112,500.00
Total Overhead Cost allocated to Job 4286 = $ 383,425.00
Conclusion

Conclusion: Hence, costs are allocated to the products using the overhead allocation rate.

To determine

Requirement-3:

To determine: The overhead Cost per unit for each job

Expert Solution
Check Mark

Answer to Problem 1APSA

Solution: The overhead Cost per unit for each job is as follows:

• Job 3175 = $373.25 Per unit

• Job 4286 = $1543.27 Per unit

Explanation of Solution

Explanation: The overhead Cost per unit for each job is calculated as follows:

Job 3175:        
Activity Allocation base Activity Rate Allocated Overhead Cost
  A   B =A*B
Grinding 550 Machine Hours $ 24.62 $ 13,538.46
Polishing 550 Machine Hours $ 10.38 $ 5,711.54
Product Modification 26 Engineering Hours $ 400.00 $ 10,400.00
Providing Power 500 Direct Labor Hours $ 15.00 $ 7,500.00
System Calibration 30 Batches $ 1,250.00 $ 37,500.00
Total Overhead Cost allocated to Job 3175 (C) $ 74,650.00
Number of Units (D) 200
Overhead Cost per unit = (C/D) $ 373.25
Job 4286:        
Activity Allocation base Activity Rate Allocated Overhead Cost
  A   B =A*B
Grinding 5500 Machine Hours $ 24.62 $ 135,384.62
Polishing 5500 Machine Hours $ 10.38 $ 57,115.38
Product Modification 32 Engineering Hours $ 400.00 $ 12,800.00
Providing Power 4375 Direct Labor Hours $ 15.00 $ 65,625.00
System Calibration 90 Batches $ 1,250.00 $ 112,500.00
Total Overhead Cost allocated to Job 4286 = $ 383,425.00
Number of Units (D) 2,500
Overhead Cost per unit = (C/D) $ 153.37
Conclusion

Conclusion: Hence, costs are allocated to the products using the overhead allocation rate.

To determine

Requirement-4:

To determine: The overhead Cost allocated per unit for each job using the plant wide overhead rate

Expert Solution
Check Mark

Answer to Problem 1APSA

Solution: The overhead Cost allocated per unit for each job using the plant wide overhead rate is as follows:

• Job 3175 = $382.88 Per unit

• Job 4286 = $306.31 Per unit

Explanation of Solution

Explanation: The overhead Cost allocated per unit for each job using the plant wide overhead rate is as follows:

Total Estimated Overhead Cost (A) $ 1,810,000
Total Machine hours (B) 13,000
Overhead allocation rate (C) = A/B = $ 139.23
   
For Job 3175:  
Overhead allocated (D) = (550 MH *C) $ 76,576.92
Number of Units (E) 200
Overhead Cost per unit = (D/E) $ 382.88
   
For Job 4286:  
Overhead allocated (D) = (5500 MH *C) $ 765,769.23
Number of Units (E) 2500
Overhead Cost per unit = (D/E) $ 306.31
Conclusion

Conclusion: Hence, all overhead costs are allocated using a single plant wide overhead rate.

To determine

Requirement-5:

To Compare: The overhead Cost allocated per unit under both the methods

Expert Solution
Check Mark

Answer to Problem 1APSA

Solution: The overhead Cost allocated per unit under both the methods is compared as follows:

Overhead Cost per unit: ABC Method Plant wide Method
Job 3175 $ 373.25 $ 382.88
Job 4286 $ 153.37 $ 306.31

Explanation of Solution

Explanation: The overhead Cost allocated per unit under both the methods is compared as follows:

Overhead Cost per unit: ABC Method Plant wide Method
Job 3175 $ 373.25 $ 382.88
Job 4286 $ 153.37 $ 306.31

Activity bases costing method is better method to allocated the overhead costs.

Conclusion

Conclusion: Hence, it can be concluded that the Activity bases costing method is better method to allocated the overhead costs.

Want to see more full solutions like this?

Subscribe now to access step-by-step solutions to millions of textbook problems written by subject matter experts!
Knowledge Booster
Background pattern image
Accounting
Learn more about
Need a deep-dive on the concept behind this application? Look no further. Learn more about this topic, accounting and related others by exploring similar questions and additional content below.
Recommended textbooks for you
Text book image
FINANCIAL ACCOUNTING
Accounting
ISBN:9781259964947
Author:Libby
Publisher:MCG
Text book image
Accounting
Accounting
ISBN:9781337272094
Author:WARREN, Carl S., Reeve, James M., Duchac, Jonathan E.
Publisher:Cengage Learning,
Text book image
Accounting Information Systems
Accounting
ISBN:9781337619202
Author:Hall, James A.
Publisher:Cengage Learning,
Text book image
Horngren's Cost Accounting: A Managerial Emphasis...
Accounting
ISBN:9780134475585
Author:Srikant M. Datar, Madhav V. Rajan
Publisher:PEARSON
Text book image
Intermediate Accounting
Accounting
ISBN:9781259722660
Author:J. David Spiceland, Mark W. Nelson, Wayne M Thomas
Publisher:McGraw-Hill Education
Text book image
Financial and Managerial Accounting
Accounting
ISBN:9781259726705
Author:John J Wild, Ken W. Shaw, Barbara Chiappetta Fundamental Accounting Principles
Publisher:McGraw-Hill Education
Cost Classifications - Managerial Accounting- Fixed Costs Variable Costs Direct & Indirect Costs; Author: Accounting Instruction, Help, & How To;https://www.youtube.com/watch?v=QQd1_gEF1yM;License: Standard Youtube License