Operations Management
13th Edition
ISBN: 9780136860419
Author: Lee Krajewski
Publisher: Pearson Education
expand_more
expand_more
format_list_bulleted
Question
Chapter E, Problem 12P
Summary Introduction
To determine: The person who is capable of reaching the 10th unit by 1 hour.
Introduction:
Learning curve:
Learning curve is based on the premise that when a person is repeating a task or job again and again, the performance of the person on that job or task will improve. It will depict relationship between cost and output over a definitive period of time.
Expert Solution & Answer
Want to see the full answer?
Check out a sample textbook solutionStudents have asked these similar questions
The first day of basic training at the Air Force Academy is quite a sight, with 1500 cadets being processed in. This involves getting haircuts, uniforms, room assignments, and a mountain of paperwork. At the Uniform Fitting station, the worker takes the measurements on the cadet (which takes about 2 minutes), then retrieves shirts, pants and hats in his/her size (which takes about 2 minutes), waits for the cadet to try on the pants (which takes about 1 minute) and then marks the pants for hemming (which takes about 1 minute). The in-processing takes place from 8 AM to 5 PM with an hour off for lunch (8 hours).
__________2a. How many cadets can a single worker fit for uniforms on that hectic day?
__________2b. How many workers would be needed to fit 1601 cadets in one day, if everyone works at full capacity?
You're responding to a troubleshooting issue in HR regarding a broken laser printer. According to reports, the printer completes the print operation and sends the paper through successfully. The content appears to be appropriately printed on the page. The toner, on the other hand, is readily smudged and adheres to other papers, equipment, and clothing. Which part of the printer is most likely in need of replacement? Make a list of the steps required to complete the assignment.
local market research fim has just won a contract for several thousand small projects involving
data gathering and statistical analysis. In the past, the firm has assigned each project to a single member of its highly trained professional staff. This person would both gather and analyze the data Using this approach, an experienced person can complete an average of 10 such projects in an eight-hour day. The firm's management is thinking of assigning two people to each project in order to allow them to specialize and become more efficient The process would require the data gatherer to fill out a matrix on the computer, check it and transmit it to the statistical analysis program for the analyst
to complete. Data can be gathered on one project while the analysis is being completed on
another, but the analysis must be complete before the statistical analysis program can accept the
new data. After some practice, the new process can be completed with a standard time of 20
minutes…
Chapter E Solutions
Operations Management
Ch. E - Prob. 1DQCh. E - Prob. 2DQCh. E - Prob. 3DQCh. E - Prob. 4DQCh. E - Prob. 5DQCh. E - Prob. 6DQCh. E - Prob. 7DQCh. E - Prob. 8DQCh. E - Prob. 1PCh. E - Prob. 2P
Ch. E - Prob. 3PCh. E - Prob. 4PCh. E - Prob. 5PCh. E - Prob. 6PCh. E - Prob. 7PCh. E - Prob. 8PCh. E - Prob. 9PCh. E - Prob. 10PCh. E - Prob. 11PCh. E - Prob. 12PCh. E - Prob. 13PCh. E - Suad Alwan, the purchasing agent for Dubai...Ch. E - Prob. 15PCh. E - Prob. 16PCh. E - Regional Power owns 25 small power generating...Ch. E - Prob. 18PCh. E - Prob. 19PCh. E - Prob. 20PCh. E - Prob. 21PCh. E - Prob. 22PCh. E - Prob. 23PCh. E - Prob. 24PCh. E - Using the accompanying log-log graph, answer the...Ch. E - Prob. 25PCh. E - Prob. 26PCh. E - Prob. 28PCh. E - Prob. 29PCh. E - Prob. 30PCh. E - Prob. 31PCh. E - Prob. 1CSCh. E - Prob. 2CSCh. E - Prob. 3CS
Knowledge Booster
Similar questions
- A time study analyst timed an assembly operation for 30 cycles, and then computed the average time per cycle, which was 18.75 minutes. The analyst assigned a performance rating of .96, and decided that an appropriate allowance was 15 percent. Assume the allowance factor is based on the workday. Determine the following: the observed time (OT), the normal time (NT), and the standard time (ST).arrow_forwardene is working with the operations manager to determine what the standard labor cost is for a spice chest. He has watched the process from start to finish and taken detailed notes on what each employee does. The first employee selects and mills the wood, so it is smooth on all four sides. This takes the employee 1 hour(s) for each chest. The next employee takes the wood and cuts it to the proper size. This takes 43 minutes. The next employee assembles and sands the chest. Assembly takes 3 hour(s). The chest then goes to the finishing department. It takes 3 hour(s) to finish the chest. All employees are cross-trained so they are all paid the same amount per hour, $17.62. What is the standard cost per chest for labor? Round to the nearest penny, two decimal places.arrow_forwardAn assembly operation has a 90 percent learning curve. The line has just begun work on a new item; the initial unit required 28 hours. Estimate the time that will be needed to complete:a. The first five unitsb. Units 20 through 25arrow_forward
- A recently negotiated union contract allows workers in a shipping department 24 minutes for rest, 10 minutes for personal time, and 14 minutes for delays for each four hours worked. A time study analyst observed a job that is performed continuously and found an average time of 6.0 minutes percycle for a worker she rated at 95 percent. What standard time is applicable for that operation?arrow_forwardThe owner of Touchdown Sports Bar wants to develop a time standard for the task of mixing a specialty cocktail. In a preliminary study, he observed one of his bartenders perform this task seven times with an average of 90 seconds and a standard deviation of five seconds. What is the standard time for this task if the bartender worked at a 20 percent faster pace than is average, and an allowance of 10 percent of job time is used?arrow_forwardThe department wants to produce 5000 parts per day. Processing time per part is measured to be 2.5 minutes. One shift with 6 hours are planned to be in a day. From previous experience the actual performance is 90%. Assume there are 50 minutes downtime per shift. (a) What is the time standard of this part? (b) What is the Takt time of this part now? (c) How many machines are required in order to produce 5000 parts per day?arrow_forward
- Suad Alwan, the purchasing agent for Dubai Airlines, has determined that the third plane took 20,000 hours to produce. Using an 80% learning curve and a $40-per-hour labor charge, he wants to determine the cost of the four additional planes. a) Time required for the fourth unit = 18,231 hours b) Cost of the fourth unit = ? dollars (round to the nearest whole number)arrow_forwardGiven the following information from an assembly task: First cycle time: 35 seconds Learning rate of 90% a. Determine the predicted performance time of the 200th b. Determine the number of cycles it will take to reach the standard time of 14 secondsarrow_forwardOnline training could be an example of asynchronous training. True or falsearrow_forward
- Can someone help me to solve the following problem showing all work thank you!arrow_forwardThe normal time for a work cycle in a worker–machine system is 6.27 min. For setting the standard time, the PFD allowance factor is 12% and the machine allowance factor is 25%.The work cycle includes manual elements totaling a normal time of 5.92 min, all but 0.65 min of which are performed as internal elements. Determine (a) the standard time for the cycle and (b) the daily output at standard performance. (c) During an 8-hour shift, theworker lost 39 min due to personal time, rest breaks, and delays, and she produced 72 pieces. What was the worker’s pace on the operator-controlled portion of the shift?arrow_forwardWrite down the Process of Job Analysis. After getting all the information, finalize the Job Summary, Job specification and Description of the desired positionarrow_forward
arrow_back_ios
SEE MORE QUESTIONS
arrow_forward_ios
Recommended textbooks for you
- Practical Management ScienceOperations ManagementISBN:9781337406659Author:WINSTON, Wayne L.Publisher:Cengage,Operations ManagementOperations ManagementISBN:9781259667473Author:William J StevensonPublisher:McGraw-Hill EducationOperations and Supply Chain Management (Mcgraw-hi...Operations ManagementISBN:9781259666100Author:F. Robert Jacobs, Richard B ChasePublisher:McGraw-Hill Education
- Purchasing and Supply Chain ManagementOperations ManagementISBN:9781285869681Author:Robert M. Monczka, Robert B. Handfield, Larry C. Giunipero, James L. PattersonPublisher:Cengage LearningProduction and Operations Analysis, Seventh Editi...Operations ManagementISBN:9781478623069Author:Steven Nahmias, Tava Lennon OlsenPublisher:Waveland Press, Inc.
Practical Management Science
Operations Management
ISBN:9781337406659
Author:WINSTON, Wayne L.
Publisher:Cengage,
Operations Management
Operations Management
ISBN:9781259667473
Author:William J Stevenson
Publisher:McGraw-Hill Education
Operations and Supply Chain Management (Mcgraw-hi...
Operations Management
ISBN:9781259666100
Author:F. Robert Jacobs, Richard B Chase
Publisher:McGraw-Hill Education
Purchasing and Supply Chain Management
Operations Management
ISBN:9781285869681
Author:Robert M. Monczka, Robert B. Handfield, Larry C. Giunipero, James L. Patterson
Publisher:Cengage Learning
Production and Operations Analysis, Seventh Editi...
Operations Management
ISBN:9781478623069
Author:Steven Nahmias, Tava Lennon Olsen
Publisher:Waveland Press, Inc.