Chapter E, Problem 13P
Summary Introduction
To determine: The time taken for the 3rd unit.
Introduction:
Learning curve:
Learning curve is based on the premise that when a person is repeating a task or job again and again, the performance of the person on that job or task will improve. It will depict relationship between cost and output over a definitive period of time.
Expert Solution & Answer
Want to see the full answer?
Check out a sample textbook solutionStudents have asked these similar questions
Beth Zion Hospital has received initial certification from the state of California to become a center for liver transplants. The hospital, however, must complete its first 18 transplants under great scrutiny and at no cost to the patients. The very first transplant, just completed, required 28 hours. On the basis of research at the hospital, Beth Zion estimates that it will have an 75% learning curve. Using Table E.3, estimate the time it will take to complete:
Unit number 5
75%
Unit time: .513
Total time: 3.459
80%
Unit number 5
Unit time: .596
Total time: 3.738
85%
Unit number 5
Unit time: .686
Total time: 4.031
Unit number 18
75%
Unit time: .301
Total time: .8.245
Unit number 18
80%
Unit time: 3.94
Total Time: 9.716
Unit number 18
85%
Unit time: .508
Total time: 11.405
a) the 5th transplant = 14.36 hours
b) the first 5 transplant = ? hours (round your response to two decimal places)
In essay form,,, what do you think is the relevance of learning curve to work productivity? Thank youuuuu :(((
A contractor is preparing a bid to install swimming pools at a new housing addition. The estimated time to build the first pool is 38 hours. The contractor estimates an 80 percent learning rate. Using POM for Windows or OM Explorer, how long do you estimate the time required to install the sixth pool?
The time required to install the sixth pool is enter your response herehours. (Enter your response rounded to two decimal places.)
Part 2
What is your estimate of the total time for all six pools?
The total time for all six pools is enter your response here hours. (Enter your response rounded to two decimal places.)
Chapter E Solutions
Operations Management: Sustainability And Supply Chain Management Custom Edition For Temple University, Version 3
Ch. E - Prob. 1DQCh. E - Prob. 2DQCh. E - Prob. 3DQCh. E - Prob. 4DQCh. E - Prob. 5DQCh. E - Prob. 6DQCh. E - Prob. 7DQCh. E - Prob. 8DQCh. E - Prob. 1PCh. E - Prob. 2P
Ch. E - Prob. 3PCh. E - Prob. 4PCh. E - Prob. 5PCh. E - Prob. 6PCh. E - Prob. 7PCh. E - Prob. 8PCh. E - Prob. 9PCh. E - Prob. 10PCh. E - Prob. 11PCh. E - Prob. 12PCh. E - Prob. 13PCh. E - Suad Alwan, the purchasing agent for Dubai...Ch. E - Prob. 15PCh. E - Prob. 16PCh. E - Regional Power owns 25 small power generating...Ch. E - Prob. 18PCh. E - Prob. 19PCh. E - Prob. 20PCh. E - Prob. 21PCh. E - Prob. 22PCh. E - Prob. 23PCh. E - Prob. 24PCh. E - Using the accompanying log-log graph, answer the...Ch. E - Prob. 26PCh. E - Prob. 1CSCh. E - Prob. 2CSCh. E - Prob. 3CS
Knowledge Booster
Similar questions
- You are asked to do a learning curve analysis as part of your internship project, but you discover that the data is pretty slim. Unfortunately you don't have time to do more field work and you have to come up with the best estimate based on the available data. Here's what you know: It took 98.71 minutes to complete the seventh unit and only 89.35 minutes to complete the twelfth unit. What is your best estimate of the Learning Rate for this process?arrow_forwardThe 4th unit of a 10-unit job took seven hours to complete. The 6th unit has been worked on for two hours, but is not yet finished. Estimate the additional amount of time needed to finish the 6th unit if the work has a 65% learning curve slope O a. 6.143 hours O b. 5.114 hours O c. 3.441 hours O d. 3.058 hours O e. 4.143 hoursarrow_forwardFor an 80% learning curve, if the 100th unit produced required 280 hours, how long will it take to produce the 400th unit? Show your calculations.arrow_forward
- What techniques can a firm use to move to a steeper learning curve?arrow_forwardLucid Inc. has developed a cutting-edge medical device. It took the company 500 hours to build the first device. The company uses an 87% learning rate for this task. How long should it take the company to build the 24th device? the 76th device? the 128th device?arrow_forwardNUBD Company is planning to introduce a new product with an 85 percent learning rate for production for batches of 1,000 units. The variable labor costs are P30 per unit for the first 1,000-unit batch. Each batch requires 100 hours. There are P10,000 in fixed costs not subject to learning. What is the cumulative total time (labor hours) to produce 2,000 units based on the cumulative average-time learning curve?arrow_forward
- You need to develop a labor time estimate for a customer order of 50 network installations. It is estimated that the first installation will require 75 labor hours and a learning curve of 85 percent is expected. a. How many labor hours are required for the 25th installation?b. How many labor hours are required to complete all 50 installations? c. If the average labor cost is $28 per hour, what is the total labor cost for installing all the networks?d. How many workers are needed to complete the job in a week? Assuming each worker works 8 hours per day 5 days per week. Show breakdown of workarrow_forwardIf the 80% learning curve applies, what wil be the cumulative average time to produce three units if first unit takes 100hoursarrow_forwardNational Company is planning to introduce a new product with an 90 percent learning rate for production for batches of 1,000 units. The variable labor costs are P30 per unit for the first 1,000-unit batch. Each batch requires 100 hours. There are P10,000 in fixed costs not subject to learning. What is the total labor cost for the cumulative total time using the incremental unit-time learning curve to produce 2,000 units?arrow_forward
- What does a learning curve specifically measure?arrow_forwardThe fifth unit of a 25-unit job took 14.5 hours to complete. If a 90 percent learning curve is appropriate:a. How long should it take to complete the last unit?b. How long should it take to complete the 10th unit?c. Estimate the average time per unit for the 25 units.arrow_forwardNational Company is planning to introduce a new product with an 85 percent learning rate for production for batches of 1,000 units. The variable labor costs are P30 per unit for the first 1,000-unit batch. Each batch requires 100 hours. There are P10,000 in fixed costs not subject to learning. What is the cumulative average time per batch using the incremental unit-time learning curve for 2,000 units?arrow_forward
arrow_back_ios
SEE MORE QUESTIONS
arrow_forward_ios
Recommended textbooks for you
- Understanding Management (MindTap Course List)ManagementISBN:9781305502215Author:Richard L. Daft, Dorothy MarcicPublisher:Cengage Learning
Understanding Management (MindTap Course List)
Management
ISBN:9781305502215
Author:Richard L. Daft, Dorothy Marcic
Publisher:Cengage Learning