353-Quiz on Revenue Recognition
docx
School
University of British Columbia *
*We aren’t endorsed by this school
Course
FINANCIAL
Subject
Accounting
Date
Feb 20, 2024
Type
docx
Pages
5
Uploaded by MagistrateSeahorsePerson2333
Question 1
1 / 1 pts
A construction company has contracted with a major university to build a new sports complex. The contract calls for two sports arenas to be built in the next three years. The
company will receive $24,000,000 for the project and their engineers originally estimated a total cost to construct the two arenas of $20,400,000, starting in 2011. The two arenas are scheduled for completion in May of 2014. If an actual cost of $9,200,000
is expended in 2011, and the engineers estimate another $12,800,000 is to be expended to complete construction, how much income is to be recognized under the percentage-of-completion method in 2011?
$1,163,636
$2,000,000
$3,600,000
$ 836,364
Question 2
1 / 1 pts
(ASPE) Choose the correct statement concerning the percentage of completion method of accounting for a firm with only one current long-term construction contract in process (assume no loss is projected):
It is possible to have both a net current asset account and a net current liability account in this situation
If the construction in process account exceeds the billings account, total costs to date must exceed total cash received on the contract to date
If the construction in process account exceeds the billings account, total costs to date must exceed total billings to date
The net current asset account (CIP minus billings) exceeds that same account under the completed contract method
Question 3
1 / 1 pts
Under IFRS15, the new IFRS Revenue Recognition standard, which of the following is NOT an important step that needs to be met in order for revenue to be recognized.
Performance obligations must be identified.
A contract with a customer must be identified.
Costs associated with fulfilling the performance obligation must be measured reliably.
The transaction price must be determinable.
Incorrect
Question 4
0 / 1 pts
Under ASPE, which of the following is not a difference between the percentage-of- completion and completed contract methods of accounting for long-term construction contracts:
They report different inventory amounts during the construction period.
One records income (loss) each period during the construction period and the other does not.
One requires estimates of completion during the construction period and the other does not.
They cause a different cash inflow during the construction period.
Question 5
1 / 1 pts
Under the percentage of completion method, a company has recognized $40,000 of profit through to the beginning of the current year on a contract, and total estimated contract cost is $500,000 at that time. The contract price is $800,000. What is the percent of completion at the beginning of the current year?
8
%
15.
8%
Insufficient data
13.33%
Incorrect
Question 6
0 / 1 pts
A firm uses the installment method of revenue recognition on an item with a cash selling
price of $1,000 and cost of $600. During the year of sale, the firm received $250 from the customer. Therefore, the "deferred gross profit" equals which of the following amounts at the end of the year of sale?
$750
$300
$400
$450
Question 7
Your preview ends here
Eager to read complete document? Join bartleby learn and gain access to the full version
- Access to all documents
- Unlimited textbook solutions
- 24/7 expert homework help
1 / 1 pts
Under ASPE, when work to be done and costs to be incurred on a long-term contract cannot be reliably estimated, which of the following methods of revenue recognition is preferable?
Percentage-of-completion method
Completed contract method
Installment method
Sales method
Question 8
1 / 1 pts
In accounting for a long-term construction-type contract using the percentage-of-
completion method, the gross profit recognized during the first year would be the estimated total gross profit from the contract, multiplied by the ratio of the costs incurred
during the year divided by
total contract price.
unbilled portion of the contract price.
total estimated cost.
total costs incurred to date.
Question 9
1 / 1 pts
Under ASPE, during the period of construction, financial information related to a long-
term contract, which is being accounted for using, the completed contract method will (assume no loss is projected):
Appear on both the income statement and balance sheet during the construction period.
Not appear on the financial statements.
Appear only on the balance sheet during the period of construction.
Appear only on the income statement during the period of construction.
Question 10
1 / 1 pts
Under ASPE and IAS18 , a sale should NOT be recognized as revenue by the seller at the time of sale if
payment was made by cheque.
the goods are sold on instalment.
the buyer has a right to return the product and the amount of future returns cannot be reasonably estimated.
the selling price is less than the normal selling price.
Quiz Score:
8
out of 10
Submission Details:
Related Documents
Related Questions
c. The bridge project must that is estimated to require 2 years to complete is about to go underway. The bridge is projected to cost $48 million. It will need to begin construction in 18 months. Rights-of-way acquisition, surveying, and permitting have already been completed and paid for by the program. There will be 2 additional project phases: 1) planning & design, 2) construction. Each will require payment at the end of the phase. The projected cost of the 1st phase of the project is $5.5 million. The 1st phase is expected to need the entire 18 months prior to the start of construction and must be completed before construction can begin. The 2nd phase is projected to cost the remaining $42.5 million. Its construction is also expected to be completed at the end of the 2-year period following planning & design. There will need to be a payout of 30% of the cost of construction at the end of the 1st year of construction project. The remaining 70% will be paid at the completion…
arrow_forward
i need the answer quickly
arrow_forward
K
A highway bridge is being considered for replacement. The new bridge would cost $X and would last for 24 years.
Annual maintenance costs for the new bridge are estimated to be $27,000. People will be charged a toll of $0.22 per car
to use the new bridge. Annual car traffic is estimated at 360,000 cars. The cost of collecting the toll consists of annual
salaries for six collectors at $9,000 per collector. The existing bridge can be refurbished for $1,400,000 and would need
to be replaced in 24 years. There would be additional refurbishing costs of $80,000 every five years and regular annual
maintenance costs of $17,000 for the existing bridge. There would be no toll to use the refurbished bridge. If MARR is
10% per year, what is the maximum acceptable cost (X) of the new bridge?
Click the icon to view the interest and annuity table for discrete compounding when the MARR is 10per year.
Choose the correct answer below.
....
A. The maximum acceptable cost of the new bridge is $1,668,576.…
arrow_forward
QUESTION 1
A new production system for a factory is to be purchased and installed for $115,042. This systom will save approximately 300,000 kWh of electric power each year for a6-
year period. Assume the cost of electricity is $0.10 per kWh, and factory MARR is 15% per year, and the salvage value of the system wil be $9,196 at year 6. Using the
PW method to analyzes if this investment is economically justified
A- calculate the PW of the above investment and insert the result below
arrow_forward
R2
arrow_forward
Question 1.
a) A Construction Company has just purchased a fleet of five truck to be used for delivery
in a particular city. Initial cost was $3000 per truck and the expected life and salvage
value is 12 years and $700 respectively. The combine insurance, maintenance, gas and
lubrication cost are expected to be $1000 for the first year and to increase by $100 per
year thereafter, while delivery service will bring an extra $3000 (revenue) in every 2
years for the company. If the interest is 12% per year find the total cost of this investment.
b) Ten years ago today Thomas made the first annual deposit of $ 2000 into a fund paying
3% interest compounded semi-annually. Two years ago the interest rate was increased to
4% on all funds compounded annually. Find the current worth of Thomas deposits, the
last of which was made today.
arrow_forward
Please provide answer general accounting
arrow_forward
Question D
arrow_forward
A2
arrow_forward
19 A highwvay construction company is under contract to build a
new roadway through a scenic area and two rural towns in
Colorado. The road is expected to cost $18 million, with annual
upkeep estimated at S150,000 per. Additional income from
tourists of $900,000 per year is estimated If the road is
expected to have a useful commercial life of 20 years, use one
spreadsheet to determine if the highway should be constructed
at an interest rate of 696 per year by applying (a) the B-C
method, (b) the B/C method, and (c) the modified B C method.
W
VERON
SAN FRANCISCO
arrow_forward
6 points
American Construction Company has entered into a contract with American University in Cairo beginning January 1, 2017 to construct Digital Library
Building. It has been estimated that the costs of the building to be $2,100,000 and the contract price will be $3,265,000. It will take 3 years to construct the
building. The company uses cost recovery method.
If the following data pertain to the building during the construction period.
Save Answer
2017
$945,000
1,155,000
900,000
800,000
2018
$1,575,000
525,000
1,970,000
1,750,000
2019
$2,135,000
Costs to date
Estimated costs to complete
-0-
Progress billings to date
Cash collected to date
3,265,000
3,265,000
Requirements:
Required 1: Compute the gross profit of loss recognized each year.
Required 2: The balance of construction in process in 2017 and 2018 will be:
Required 3: Assume the same data for the digital library contract except that the estimated cost in 2018 was $1.050.000 instead of $525,000.
A. Compute the gross profit or…
arrow_forward
Ñ3
arrow_forward
Shanahan Construction Company has entered into a contract beginning January 1, 2020, to build a parking complex. It has been estimated that the complex will cost $600,000 and will take 3 years to construct. The complex will be billed to the purchasing company at $900,000. The following data pertain to the construction period.
2020
2021
2022
Costs to date
$270,000
$450,000
$610,000
Estimated costs to complete
330,000
150,000
–0–
Progress billings to date
270,000
550,000
900,000
Cash collected to date
240,000
500,000
900,000
Instructions
a. Using the percentage-of-completion method, compute the estimated gross profit that would be recognized during each year of the construction period.
b. Using the completed-contract method, compute the estimated gross profit that would be recognized during each year of the construction period.
arrow_forward
Question 1
Aguilera Acoustics, Inc. (AAI), projects unit sales for a new seven-octave voice emulation implant as follows:
Year
Unit Sales
1
8300
2
9200
3
10400
4
9800
5
8400
Production of the implants will require GH¢ 150,000 in net working capital to start and additional net working capital investments each year equal to 15 percent of the projected sales for that year. In the final year of the project, net working capital will decline to zero as the project is wound down. In other words, the investment in working capital is to be completely recovered by the end of the project’s life. Total fixed costs are GH¢ 240,000 per year, variable production costs are GH¢ 190 per unit, and the units are priced at GH¢ 345 each. The equipment needed to begin production has an installed cost of GH¢ 2,300,000. Because the implants are intended for professional singers, this equipment depreciated using the straight-line basis. In five years, this equipment…
arrow_forward
9
arrow_forward
Shanahan Construction Company has entered into a contract beginning January 1, 2020, to build a parking complex. It has been estimated that the complex will cost $609,000 and will take 3 years to construct. The complex will be billed to the purchasing company at $896,000. The following data pertain to the construction period. 2020 2021 2022 Costs to date $266,640 $412,080 $617,000 Estimated costs to complete 339,360 193,9200 –0– Progress billings to date 270,000 545,000 896,000 Cash collected to date 240,000 495,000 896,000 A/ Using the percentage-of-completion method, compute the estimated gross profit that would be recognized during each year of the construction period. Gross profit recognized in 2020: Gross profit recognized in 2021: Gross profit recognized in 2022: B/ Using the completed-contract method, compute the estimated gross profit that would be recognized during each year of the construction period. Gross profit recognized in 2020: Gross profit recognized in 2021: Gross…
arrow_forward
A3 9b
You are considering a project that will supply an automobile production facility with 35,000 tonnes of machine screws annually for five years. To get the project started, you will need an initial investment of $1,500,000 in threading equipment. The project will last for five years. The accounting department estimates that annual fixed costs will be $300,000 and that variable costs should be $200 per tonne. The CCA rate for threading equipment is 20%. Accounting estimates a salvage value of $500,000 after costs of dismantling. The marketing department estimates that the auto makers will accept the contract at a selling price of $250 per tonne. The engineering department estimates you will need an initial net working capital investment of $450,000. You require a 15% return and face a marginal tax rate of 38% on this project.
b. Suppose you believe that the accounting department’s initial cost and salvage projections are accurate only to within ±15%; the marketing department’s…
arrow_forward
please answer letters only
arrow_forward
Question 7
A construction company is deciding if they should make a new building bronze, silver, or gold
LEED-certified, or not at all. Regardless of the level of certification, this new building will
generate extra annual revenues of $40,000 starting at the end of the first year due to planned
business operation. In terms of operational cost, each option offers different levels of annual
energy savings (can be taken as annual incomes), but also different operation and maintenance
costs. Please also note that a building with no certification will have no energy savings, but full
energy costs. Further, the government offers different tax credits depending on the level of
environmental impact. Please note that all annual costs and savings begin at the end of year 3 and
extend until the end of the operation life. The buildings are intended to operate for 20 years, and
the company has a minimum attractive rate of return (MARR) of 5%. The following data is
available for each option:
Annual…
arrow_forward
SEE MORE QUESTIONS
Recommended textbooks for you


Accounting
Accounting
ISBN:9781337272094
Author:WARREN, Carl S., Reeve, James M., Duchac, Jonathan E.
Publisher:Cengage Learning,

Accounting Information Systems
Accounting
ISBN:9781337619202
Author:Hall, James A.
Publisher:Cengage Learning,

Horngren's Cost Accounting: A Managerial Emphasis...
Accounting
ISBN:9780134475585
Author:Srikant M. Datar, Madhav V. Rajan
Publisher:PEARSON

Intermediate Accounting
Accounting
ISBN:9781259722660
Author:J. David Spiceland, Mark W. Nelson, Wayne M Thomas
Publisher:McGraw-Hill Education

Financial and Managerial Accounting
Accounting
ISBN:9781259726705
Author:John J Wild, Ken W. Shaw, Barbara Chiappetta Fundamental Accounting Principles
Publisher:McGraw-Hill Education
Related Questions
- c. The bridge project must that is estimated to require 2 years to complete is about to go underway. The bridge is projected to cost $48 million. It will need to begin construction in 18 months. Rights-of-way acquisition, surveying, and permitting have already been completed and paid for by the program. There will be 2 additional project phases: 1) planning & design, 2) construction. Each will require payment at the end of the phase. The projected cost of the 1st phase of the project is $5.5 million. The 1st phase is expected to need the entire 18 months prior to the start of construction and must be completed before construction can begin. The 2nd phase is projected to cost the remaining $42.5 million. Its construction is also expected to be completed at the end of the 2-year period following planning & design. There will need to be a payout of 30% of the cost of construction at the end of the 1st year of construction project. The remaining 70% will be paid at the completion…arrow_forwardi need the answer quicklyarrow_forwardK A highway bridge is being considered for replacement. The new bridge would cost $X and would last for 24 years. Annual maintenance costs for the new bridge are estimated to be $27,000. People will be charged a toll of $0.22 per car to use the new bridge. Annual car traffic is estimated at 360,000 cars. The cost of collecting the toll consists of annual salaries for six collectors at $9,000 per collector. The existing bridge can be refurbished for $1,400,000 and would need to be replaced in 24 years. There would be additional refurbishing costs of $80,000 every five years and regular annual maintenance costs of $17,000 for the existing bridge. There would be no toll to use the refurbished bridge. If MARR is 10% per year, what is the maximum acceptable cost (X) of the new bridge? Click the icon to view the interest and annuity table for discrete compounding when the MARR is 10per year. Choose the correct answer below. .... A. The maximum acceptable cost of the new bridge is $1,668,576.…arrow_forward
- QUESTION 1 A new production system for a factory is to be purchased and installed for $115,042. This systom will save approximately 300,000 kWh of electric power each year for a6- year period. Assume the cost of electricity is $0.10 per kWh, and factory MARR is 15% per year, and the salvage value of the system wil be $9,196 at year 6. Using the PW method to analyzes if this investment is economically justified A- calculate the PW of the above investment and insert the result belowarrow_forwardR2arrow_forwardQuestion 1. a) A Construction Company has just purchased a fleet of five truck to be used for delivery in a particular city. Initial cost was $3000 per truck and the expected life and salvage value is 12 years and $700 respectively. The combine insurance, maintenance, gas and lubrication cost are expected to be $1000 for the first year and to increase by $100 per year thereafter, while delivery service will bring an extra $3000 (revenue) in every 2 years for the company. If the interest is 12% per year find the total cost of this investment. b) Ten years ago today Thomas made the first annual deposit of $ 2000 into a fund paying 3% interest compounded semi-annually. Two years ago the interest rate was increased to 4% on all funds compounded annually. Find the current worth of Thomas deposits, the last of which was made today.arrow_forward
- 19 A highwvay construction company is under contract to build a new roadway through a scenic area and two rural towns in Colorado. The road is expected to cost $18 million, with annual upkeep estimated at S150,000 per. Additional income from tourists of $900,000 per year is estimated If the road is expected to have a useful commercial life of 20 years, use one spreadsheet to determine if the highway should be constructed at an interest rate of 696 per year by applying (a) the B-C method, (b) the B/C method, and (c) the modified B C method. W VERON SAN FRANCISCOarrow_forward6 points American Construction Company has entered into a contract with American University in Cairo beginning January 1, 2017 to construct Digital Library Building. It has been estimated that the costs of the building to be $2,100,000 and the contract price will be $3,265,000. It will take 3 years to construct the building. The company uses cost recovery method. If the following data pertain to the building during the construction period. Save Answer 2017 $945,000 1,155,000 900,000 800,000 2018 $1,575,000 525,000 1,970,000 1,750,000 2019 $2,135,000 Costs to date Estimated costs to complete -0- Progress billings to date Cash collected to date 3,265,000 3,265,000 Requirements: Required 1: Compute the gross profit of loss recognized each year. Required 2: The balance of construction in process in 2017 and 2018 will be: Required 3: Assume the same data for the digital library contract except that the estimated cost in 2018 was $1.050.000 instead of $525,000. A. Compute the gross profit or…arrow_forwardÑ3arrow_forward
arrow_back_ios
SEE MORE QUESTIONS
arrow_forward_ios
Recommended textbooks for you
- AccountingAccountingISBN:9781337272094Author:WARREN, Carl S., Reeve, James M., Duchac, Jonathan E.Publisher:Cengage Learning,Accounting Information SystemsAccountingISBN:9781337619202Author:Hall, James A.Publisher:Cengage Learning,
- Horngren's Cost Accounting: A Managerial Emphasis...AccountingISBN:9780134475585Author:Srikant M. Datar, Madhav V. RajanPublisher:PEARSONIntermediate AccountingAccountingISBN:9781259722660Author:J. David Spiceland, Mark W. Nelson, Wayne M ThomasPublisher:McGraw-Hill EducationFinancial and Managerial AccountingAccountingISBN:9781259726705Author:John J Wild, Ken W. Shaw, Barbara Chiappetta Fundamental Accounting PrinciplesPublisher:McGraw-Hill Education


Accounting
Accounting
ISBN:9781337272094
Author:WARREN, Carl S., Reeve, James M., Duchac, Jonathan E.
Publisher:Cengage Learning,

Accounting Information Systems
Accounting
ISBN:9781337619202
Author:Hall, James A.
Publisher:Cengage Learning,

Horngren's Cost Accounting: A Managerial Emphasis...
Accounting
ISBN:9780134475585
Author:Srikant M. Datar, Madhav V. Rajan
Publisher:PEARSON

Intermediate Accounting
Accounting
ISBN:9781259722660
Author:J. David Spiceland, Mark W. Nelson, Wayne M Thomas
Publisher:McGraw-Hill Education

Financial and Managerial Accounting
Accounting
ISBN:9781259726705
Author:John J Wild, Ken W. Shaw, Barbara Chiappetta Fundamental Accounting Principles
Publisher:McGraw-Hill Education