PROJECT CHARTER AND SCOPE STATEMENT
1
Project Charter and Scope Statement
Kathleen McClain
PM-FP4020
Capella University
April 13, 2020
PROJECT CHARTER AND SCOPE STATEMENT
2
Project Selection and Business Case
Project Charter
Project Name: Evans/Michaels Wedding
Department: Wedding Planning
Focus Area: Wedding
Product/Process: Wedding/Reception Venue, Entertainment, Food and Beverage, and Invitations
Prepared By
Document Owner(s)
Project/Organization Role
Kathleen McClain
Project Manager/Wedding Planner
Project Charter Version Control
Version
Date
Author
Change Description
1.0
4/1/20
McClain
First Version
PROJECT CHARTER AND SCOPE STATEMENT
3
TABLE OF CONTENTS
Page
1.
Project Charter Purpose………………………………………………………………………………… 4
2.
Project Executive Summary…………………………………………………………………………….. 4
3.
Project Requirements…………………………………………………………………………………….4
4.
Business Needs………………………………………………………………………………………….. 4
5.
Milestones………………………………………………………………………………………………… 5
6.
Project Stakeholders…………………………………………………………………………………….. 6
7.
High Level Budget……………………………………………………………………………………….. 6
8.
Conditions………………………………………………………………………………………………….7
8.1
Project Assumptions…………………………………………………………………………….7
8.2
Project Risks……………………………………………………………………………………..7
8.3
Project Constraints………………………………………………………………………………7
9.
Business Case…………………………………………………………………………………………….8
10.
Approvals……………………………………………………………………………………………….….8
11.
Project Scope………..…………………………………………………………………………………… 8
11.1
In-Scope Deliverables…………………………………………………………………………..9
11.2
Out of Scope……………………………………………………………………………………..9
12.
WBS……………………………………………………………………………………………………….10
13.
References………………………………………………………………………………………………..11
PROJECT CHARTER AND SCOPE STATEMENT
4
.
PROJECT CHARTER PURPOSE
The project is the successful plan, preparation, and execution of the “Evans-Michaels Wedding and reception” the goal being a flawless event and lifetime memory of the occasion.
PROJECT EXECUTIVE SUMMARY
This project is designed for our clients Wedding project. The primary deliverable of the project is a
scenic, outdoor wedding venue in Las Vegas, Nevada accommodating one hundred total guests inclusive
of the wedding party and reception with a buffet dinner and live music immediately following. Budget for the project will be $25,500, which is in line with the average cost for this type of event in this area as verified through several resources and summarized in Value Penguin. (Value Penguin, 2019). The date of the event will be a Saturday in September 2020 dependent on the selected venue availability. As Project Manager, Kathleen McClain will meet with stakeholders bi-monthly in the first four months and weekly in the final two-months. Meetings will be with the bride, groom, and the families, as determined by stakeholders, to refine details of the wedding. The development of a Work Breakdown Structure will be completed in the first month of the project as specific details progress. PROJECT REQUIREMENTS
“Project manager has a 10% tolerance on budget and a 5% tolerance on schedule. Any deviation above these approved limits must be signed off by the project sponsor.” (Malsam, 2018).
BUSINESS NEEDS
Meeting with stakeholders to continue project development and an established payment source, credit card or account with PM signatory authority for deposits as indicated. Expedited Venue selection to facilitate further points of the project plan.
Your preview ends here
Eager to read complete document? Join bartleby learn and gain access to the full version
- Access to all documents
- Unlimited textbook solutions
- 24/7 expert homework help
Related Questions
1.Steps in Project Scope Management process
2. Define Scope Planning
3. Purpose of Scope Definition
arrow_forward
Create a Project Charter, a template is provided below
arrow_forward
a. Introduction PPE GLOVEb. Objective of Project/Manufacturing Processc. History of Company/Product (PPE GLOVE)
arrow_forward
Q3. What is Project Scope Management? Discuss Project Scope and Product Scope. Why do you think preparing project scope management plan is important to be made?
arrow_forward
Scope statement Which should include
-project justification
-product characteristics and requirements
-product user acceptance criteria
-project management related deliverables
-product related deliverables
arrow_forward
Program/Project Management PMO - Project Governance Summary and overview.
arrow_forward
Practice Question EVM:
A simple project consists of five tasks and is scheduled to take 13 weeks to complete. The actual
status of the project at the end of week 9 is given in the following table:
Project Plan
Task | Duration Start
(weeks)
Actual status
Actual
current cost complete
S350
S225
$475
$300
End
Budget
Percent
week week
$300
100%
100%
$250
$450
$600
$500
B
2
100%
75%
75%
C
4
4
7.
9.
13
D
3
6
8
$300
a) For each activity, compute the ACWP, BCWP, BCWS and add the columns to get the
projected total. Record your answers in the table below.
Task
ACWP
BCWP
BCWS
E
b) Calculate: CV,SV,CPI, and SPI:
arrow_forward
Define Project Scope, Project Deliverable and Project Scope Management.
Explain SIX (6) steps for Project Scope Management Processes.
Explain THREE (3) methods for collecting requirement in Project Scope Management.
arrow_forward
5
arrow_forward
Q1. Using a suitable example each, describe what the following project planning
process activities involve:
a. Establish project objective;
b. Define scope;
c. Create a Work Breakdown Structure (WBS);
d. Estimate activity durations;
e. Sequencing activities.
arrow_forward
I need help creating a project charter for a home renovation company-(completing a millionaires mansion) and it needs to include:
All 12 categories/sections of a Project Charter
Project overview/description
Purpose and justification
Objectives and success criteria
High level requirements
Assumptions and constraints
Risks
Milestone schedule
Budget summary
Stakeholders
Approval requirements
Project manager role and authority level
Sponsor and authority level
arrow_forward
Q3.When we start a project how we know this project or program is feasible for our future? Explain with help of diagram
arrow_forward
Project manager manage project budget in project-oriented organization.
1-TRUE
2-FALSE
arrow_forward
Q1. Using a suitable example each, describe what the following project planningprocess activities involve:a. Establish project objective;b. Define scope;c. Create a Work Breakdown Structure (WBS);d. Estimate activity durations;e. Sequencing activities.
arrow_forward
N5
Explain some of the basic principles of cost management, such as profits, life cycle costs, tangible and intangible costs and benefits, direct and indirect costs, and reserves. Why is defining activities a process of project time management instead of project scope management?
arrow_forward
Students shall, with a point of view of him/herself as project manager (PM), submit a Project Management Plan (PMP) for the given engineering project below: - “Procurement & Installation of Emergency Generator at Fire station” Students are allowed to propose their own project, given that the projects shall have enough scale to address the element described below:- a. Student should produce a project definition statement regarding the proposed project. b. Student should propose a suitable project team to carry out the project. Student should in the PMP describe the duties and power of different team memebrs in the project. c. The PMP shall include a risk management plan, which student shall identify, analyse and proposed mitigations measures for smooth delivery of the project deliverables. The risk manamgenet plan shall include a risk register d. The PMP shall include a quality management plan, which student shall propose a method statement to control the quality of the delivery of…
arrow_forward
Q1 ) Scenarios of a project activities (tables given below) and their required times to be completed in addition to their predecessors for developing a ‘Website’:
Activity
Description
Duration (weeks)
Preceding Activities
A
Determine user needs
8
--
B
Review s/w and languages
4
--
C
Purchase software
10
--
D
Design format and style
10
B
E
Write programs
6
A
F
Review outcome product with user
12
C
G
Make revisions
4
C
H
Select server site
8
E
I
Install on server
14
D,F
J
Test
8
G,H,I
Draw the path.
Calculate the early finishing time (forwards calculations)
Highlight the total time to complete the project (days)
Calculate the late finishing time (backwards calculations)
Calculate the slack time of the non-critical path activities
Identify the critical path (highlight critical path activities)
what would happen if activity D revised to take 14 instead of 10 days?
arrow_forward
Define project development life cycle with help of diagram
arrow_forward
Activity 3: Scenarios of a project activities (tables given below) and their required times to be
completed in addition to their predecessors for developing a Website":
Activity Description
Duration (days) Preceding Activities
A
Determine user needs
9
в
Review s/w and languages
7
Purchase software
9.
D
Design format and style
B.
E
Write programs
7
Review outcome product
with user
F
10
G
Make revisions
C
H
Select server site
8
E
Install on server
11
D, F
Test
G, H, I
1. Draw the path.
2. Calculate the carly finishing time (forwards calculations)
3. Highlight the total time to complete the project (days or weeks)
4. Calculate the late finishing time (backwards calculations)
5. Calculate the slack time of the non-critical path activities
6. Identify the critical path (highlight critical path activities)
7. what would happen if revised to take seven weeks instead of five weeks
arrow_forward
Project Duration=
Planning on spending per month
Project Budget (BAC)
Percent complete per month
Performance Analysis
% Complete
Planned Value (PV)
Actual Cost (AC)
Earned Value (EV)
Schedule Variance (SV)
Schedule Performance Index (SPI)
Cost Variance (CV)
Cost Performance Index (CPI)
Estimate at Completion (EAC)
Estimate to Complete (ETC)
Variance at Completion (VAC)
5 months
$300,000.00
$1,500,000.00
Month 1
20%
20% of work completed
15% of work completed
Spent additional $110,000
Month 2
Instructions: Utilizing the EVM cheat sheet provided by the instructor, complete the calculations i
formulas and functions to attain your answers. Please do not simply plug in numbers. This exerci
ability to use Excel. Finally, answer the questions below to explain your answers.
Question 1: What do your SV numbers tell you about the project schedule and how?
Answer 1:
Question 2: What do your SPI numbers tell you about the project schedule and how?
Answer 2:
arrow_forward
Project Termination Plans for manufacturing electric bus Project placement within a program (roadmap, core competencies)
arrow_forward
Q2: Explain briefly the concept of "Project", what can it create, and what are the
main examples of it ?
arrow_forward
Question 2a) Why is project charter an important project management tool? b) Explain how a project manager will go about incorporating project scheduling to guarantee your project success. c) At what stage is project needs assessment or appraisal needed? Explain
arrow_forward
c) Project life cycle diagrams
d) Selection method for project (Names and Formulas)
arrow_forward
TCO 9) Most projects completed using traditional project management are done in a weak matrix organization. Most projects completed in an agile project management framework use a strong matrix or pure project environment. Why is this so?
arrow_forward
Q)Project can involve a single individual or multiple individuals, a single
organizational unit, or multiple organizational units from multiple organizations and
a project can create following: (Discuss this argument )
Subject :: project management
arrow_forward
Case: Friendly Assisted Living Facility-3 (pg.104)
Q1: Define the deliverables for this project
Q2: Define the constraints and assumptions for this project
Q3: Develop a preliminary Level 1 WBS
Q4: Develop a RACI matrix for this project based on the level 1 WBS
Q5: Would a Project Charter have been useful here? Explain.
C
A
S
E
Friendly Assisted Living Facility-3
Continuing with the ALF Steering Committee meeting Fred led a discussion of all the major steps that must be included in the project plan, and inked each team member to identify the areas for which they would accept responsi bility. The hospital's Construction Project Manager took responsibility for the constructions of the facility, and the COO volunteered to oversee the building design, as well as define the needs for food services, housekeeping, staff ing, and policy and procedure development. The CFO agreed to develoys the budgets for each area of the project
as well as the operating budget for the facility.…
arrow_forward
2
The net present value method takes into account which of the following?
Cash Flow over Life of Project
Time Value of Money
A) No
Yes
B) No
No
C) Yes
No
D) Yes
Yes
Select one:
a. Option A
b. Option B
c. Option C
d. Option D
arrow_forward
Perform dependency and assumptions analysis
for a project charter for any topic. Should not be
related to project topic.
arrow_forward
SEE MORE QUESTIONS
Recommended textbooks for you
BUSN 11 Introduction to Business Student Edition
Business
ISBN:9781337407137
Author:Kelly
Publisher:Cengage Learning
Essentials of Business Communication (MindTap Cou...
Business
ISBN:9781337386494
Author:Mary Ellen Guffey, Dana Loewy
Publisher:Cengage Learning
Accounting Information Systems (14th Edition)
Business
ISBN:9780134474021
Author:Marshall B. Romney, Paul J. Steinbart
Publisher:PEARSON
International Business: Competing in the Global M...
Business
ISBN:9781259929441
Author:Charles W. L. Hill Dr, G. Tomas M. Hult
Publisher:McGraw-Hill Education
Related Questions
- 1.Steps in Project Scope Management process 2. Define Scope Planning 3. Purpose of Scope Definitionarrow_forwardCreate a Project Charter, a template is provided belowarrow_forwarda. Introduction PPE GLOVEb. Objective of Project/Manufacturing Processc. History of Company/Product (PPE GLOVE)arrow_forward
- Q3. What is Project Scope Management? Discuss Project Scope and Product Scope. Why do you think preparing project scope management plan is important to be made?arrow_forwardScope statement Which should include -project justification -product characteristics and requirements -product user acceptance criteria -project management related deliverables -product related deliverablesarrow_forwardProgram/Project Management PMO - Project Governance Summary and overview.arrow_forward
- Practice Question EVM: A simple project consists of five tasks and is scheduled to take 13 weeks to complete. The actual status of the project at the end of week 9 is given in the following table: Project Plan Task | Duration Start (weeks) Actual status Actual current cost complete S350 S225 $475 $300 End Budget Percent week week $300 100% 100% $250 $450 $600 $500 B 2 100% 75% 75% C 4 4 7. 9. 13 D 3 6 8 $300 a) For each activity, compute the ACWP, BCWP, BCWS and add the columns to get the projected total. Record your answers in the table below. Task ACWP BCWP BCWS E b) Calculate: CV,SV,CPI, and SPI:arrow_forwardDefine Project Scope, Project Deliverable and Project Scope Management. Explain SIX (6) steps for Project Scope Management Processes. Explain THREE (3) methods for collecting requirement in Project Scope Management.arrow_forward5arrow_forward
- Q1. Using a suitable example each, describe what the following project planning process activities involve: a. Establish project objective; b. Define scope; c. Create a Work Breakdown Structure (WBS); d. Estimate activity durations; e. Sequencing activities.arrow_forwardI need help creating a project charter for a home renovation company-(completing a millionaires mansion) and it needs to include: All 12 categories/sections of a Project Charter Project overview/description Purpose and justification Objectives and success criteria High level requirements Assumptions and constraints Risks Milestone schedule Budget summary Stakeholders Approval requirements Project manager role and authority level Sponsor and authority levelarrow_forwardQ3.When we start a project how we know this project or program is feasible for our future? Explain with help of diagramarrow_forward
arrow_back_ios
SEE MORE QUESTIONS
arrow_forward_ios
Recommended textbooks for you
- BUSN 11 Introduction to Business Student EditionBusinessISBN:9781337407137Author:KellyPublisher:Cengage LearningEssentials of Business Communication (MindTap Cou...BusinessISBN:9781337386494Author:Mary Ellen Guffey, Dana LoewyPublisher:Cengage LearningAccounting Information Systems (14th Edition)BusinessISBN:9780134474021Author:Marshall B. Romney, Paul J. SteinbartPublisher:PEARSON
- International Business: Competing in the Global M...BusinessISBN:9781259929441Author:Charles W. L. Hill Dr, G. Tomas M. HultPublisher:McGraw-Hill Education
BUSN 11 Introduction to Business Student Edition
Business
ISBN:9781337407137
Author:Kelly
Publisher:Cengage Learning
Essentials of Business Communication (MindTap Cou...
Business
ISBN:9781337386494
Author:Mary Ellen Guffey, Dana Loewy
Publisher:Cengage Learning
Accounting Information Systems (14th Edition)
Business
ISBN:9780134474021
Author:Marshall B. Romney, Paul J. Steinbart
Publisher:PEARSON
International Business: Competing in the Global M...
Business
ISBN:9781259929441
Author:Charles W. L. Hill Dr, G. Tomas M. Hult
Publisher:McGraw-Hill Education