M1_Activity_2
.docx
keyboard_arrow_up
School
Royal Melbourne Institute of Technology *
*We aren’t endorsed by this school
Course
DIPLOMA_OF
Subject
Civil Engineering
Date
Feb 20, 2024
Type
docx
Pages
9
Uploaded by ColonelOkapiMaster996
CPC40120/CPC50220 Module 1 – Assessment 2.5
Assessment Cover Sheet
The Cover Sheet must be completed before you start your assessment.
Student Surname
Narigi Reddy
Student Given
Name
Harish Reddy
Qualification
CPCC40120/CPC50220 CertIV/Diploma of Building and Construction (Building)
Module of Study
Module 1
Assessment Name
Activity 2.5 - Administering and Finalising the Contract
Trainer Name
KAAN
Student Statement
Plagiarism is a form of cheating. It is taking and using someone else’s thoughts or writings and
representing them as your own. Plagiarism is a serious act and may result in a participant’s exclusion
from a Unit of Competency or a course. This in turn may require for students to pay to re-complete the
module or course at a later date. The following list outlines some of the activities for which a participant can be accused of plagiarism:
1.
Presenting any work by another individual as one’s own unintentionally
2.
Handing in assessments markedly similar to or copied from another student
3.
Presenting the work of another individual or group as their own work.
4.
Handing up assessments without the adequate acknowledgement of sources used, including assessments taken totally or in part from the internet.
Many of the workbook activities are ‘open book’ yet should still be conducted under test conditions
without consultation with other students. If you are unsure of any assessment requirements you should
check with your Trainer / Assessor.
By submitting this assessment electronically you declare that all work for assessment tasks submitted for
this assessment is your own with no part of any assessment being copied/plagiarised from another
person’s work, except where authorised and listed / referenced.
© House of Learning Pty Ltd
M1 – Activity 2.5 - Answer Sheet – V1.0| 08.07.2021 | Page 1 of 9
CPC40120/CPC50220 Module 1 – Assessment 2.5
Use this space
1.
Process progress payments
Progress program are made under the Building & Construction Industry Security of Payment ACT 1999. As per agreed percentage of completion of projects. Process payments may be done at start, end or in installments as project goes on. For example; Deposit, Base or Slab , Frame, Lock-up, Fixing,and Practical Completion.
2.
Process application for extension of time
Unforeseeable delays are inevitable in construction projects and warrants and application for an extension of time. For example: Force Majeure, Strikes, Changes in the law or requirements, Political unrest or Terrorism, Delays from the part of subcontractor. In such cases, the contractor sends written notice to the project management or administrator with details of what caused the delay and
documents or evidence to support it.Filing for the extension of time must be done immediately, as the necessary claim for delays may be time consuming.
3.
Prepare a checklist ensuring that the organisation’s policies and procedures ensure that there are A policy pertains to a set of guidelines or course of actions to be enforced and should be followed in the workplace and organization. On the other hand, a procedure is a specific guideline or process that is done in order to follow and comply with a policy.
Policies and procedures vary widely depending on the organization, (every organization have different policies) as well as nature of the policy. In this context a dispute resolution policy of organization contains several procedures to properly address and resolve disputes and other related issues. 4.
Measures in place to prevent a breach of contract
Breach of contract; It is not uncommon for situations which constitute to a breach in contract;
Material Breach, Minor Breach, Anticipatory Breach, Actual Breach. Most contracts, will have one or another clause disclosing about breach of contract and process to overcome it. For example; performance obligation, payment by the client, contractor not completing work
.
5.
Prepare a checklist for issuing the final certificate
1. OCCUPANCY APPLICATION FORM (FORM 5)
2. PLUMBING CERTIFICATES This is includes plumbing works associated with roofing, water supply,
sewer, gas installation, water tank installation connected to flushing system, solar hot water system
© House of Learning Pty Ltd
M1 – Activity 2.5 - Answer Sheet – V1.0| 08.07.2021 | Page 2 of 9
CPC40120/CPC50220 Module 1 – Assessment 2.5
etc. 3. ELECTRICAL CERTIFICATE
4. INSULATION CERTIFICATE / DECLARATION A letter/certificate from the installer or builder
confirming thermal insulation has been installed within the floors, walls and roof in accordance with
the approved drawings and the NCC. 5. ENERGY RATING REPORT DECLARATION FROM THE OWNER / BUILDER Confirming that the 6
STAR ENERGY EFFICIENCY provisions as nominated by the First Rate Report have been installed in
accordance with the report, the endorsed plans and the building elements identified on the Detailed
House Data sheet. 6. GLAZING CERTIFICATE Confirming all glazing (glass) including shower/bath enclosures, glazed
doors, side panels and windows have been installed in accordance with AS 1288 – 2006 & AS 2047. 7. ENGINEERS INSPECTION REPORTS AND CERTIFICATES Required when any inspections were not
carried out by BSP MELBOURNE (if applicable). 8. TERMITE PROTECTION CERTIFICATE A Certificate of Installation (Part A & Part B) for the installation
of a required termite barrier in accordance with AS 3660 Part 1 or any other accredited barrier
system. 9. WATERPROOFING OF WET AREAS AND BALCONIES A letter from the installer or builder certifying
that the wet areas have been waterproofed in accordance with AS 3740. 10. PARTYWALL / FIRE RATED BOUNDARY WALL INSTALLATION DECLARATION A Letter from the
Builder certifying that the party wall / boundary fire rated wall system has been installed in
accordance with the building permit plans in respect to the required fire resistant levels, acoustic
levels and manufactures partywall system specifications. 11. FIRE PLACE INSTALLATION/ CONSTRUCTION A letter from the installer or builder certifying that
the solid fuel heater (fire place) has been installed in accordance with the building permit plans,
Section 3.7.3 of the BCA Vol. 2,and manufacturers installation specifications. 12. BUSHFIRE PRONE AREAS - ADDITIONAL CONSTRUCTION MEASURES A letter from the builder
certifying that the specified BAL construction requirements have been installed in accordance with
the building permit plans and the relevant BAL construction requirements specified under AS 3959-
2009. 13. COUNCIL SEPTIC TANK INSTALLATION APPROVAL (PERMIT TO USE) 14. OUTSTANDING FEES All outstanding fees which may include additional site inspections, building
notice/order costs, amendment/ variations to permit costs, etc. need to be paid before the
Occupancy Permit/ Final Certificate can be issued.
6.
Prepare a practical completion checklist
Practical completion depends on the type of contract used. It is the stage of construction when all the works described in the contract have been carried out
Checklist for Practical Completion Inspection
© House of Learning Pty Ltd
M1 – Activity 2.5 - Answer Sheet – V1.0| 08.07.2021 | Page 3 of 9
CPC40120/CPC50220 Module 1 – Assessment 2.5
1. Interior
Check all the tap ware
, flushes and plugs of every bath, shower, sink, etc.
See if any silicon is used in wet areas like baths, counter-tops
, sinks, and
taps. Also, make sure they are near and gaps-free. This is to ensure the areas
are correctly sealed.
Check the edges of the niches
See if the tiles are free from holes or gaps
Check all the electrical elements like light switches, power points, holders,
etc.
If there are dual switches, are sure they are wired correctly.
If you have a security system, test it properly.
Also check the smoke alarms.
Check skirting
, window sills, architraves, ceiling, and walls.
See if any cracks are there.
Also see if there are any uneven areas on the wall.
Check all the fittings,
fixtures
, and benchtops
Make sure the windows and doors are opening and closing correctly.
All drawers, doors, cupboards, cabinets, etc are opening easil
y.
2. Exterior
Check that the external windows and doors are free from damage
Also see they open and close smoothly
All the handles are in good condition.
See if the locks and keys are working properly.
Inspect the surroundings of windows and doors for damage.
See if all the tiles on the roof are free from damage
Check for broken, cracked, or missing tiles.
Check all the elements like gutters, valleys, fascias, down pipes
, eaves, etc
are free from damage.
Inspect weep holes, mortar joints, and brickwork for inconsistencies, cracks,
or stains.
Test the external power points or light switches.
.
7.
Issue completion certificates
A final certificate is issued by a contract administrator to show that the contract has been completely
fulfilled. It signifies the agreement of the final contract sum and defects has been fixed. This also
prevents any future disputes.
© House of Learning Pty Ltd
M1 – Activity 2.5 - Answer Sheet – V1.0| 08.07.2021 | Page 4 of 9
Your preview ends here
Eager to read complete document? Join bartleby learn and gain access to the full version
- Access to all documents
- Unlimited textbook solutions
- 24/7 expert homework help
Related Questions
Please explain the photo attached
Topic: STANDARD OF PROFESSIONAL PRACTICE (SPP) ON CONSTRUCTION MANAGEMENT SERVICES
arrow_forward
Can a graduate in civil engineering course sign plans and supervise construction projects, even though he/she did not pass the board exam? Explain.
arrow_forward
Your company, a G7 contractor is appointed as main contractor for construction of a new recreational building and facilities at Pantai Minyak Beku, Batu Pahat, Johor. You are chosen for a new position as Construction Contract Manager to administer the construction contract for those recreational buildings and facilities. Prepare your scope of work as a Construction Contract Manager for submission as part of the quality management system (QMS) documentation of the project. (C3) Open ended question.
arrow_forward
Given ann assessment on the role of the course in your education for CONSTRUCTION MATERIALS AND TESTING. No plagiarism and it must be not less than 10 sentences.
For strict compliance.
Thank you!
arrow_forward
What is stop notice release bond method?When is it used?
arrow_forward
Of the items listed below, identify which components are included in a scope of
work?
A) A description of the work.
OB) Technical requirements
Oc) Identification of major components
OD) A detailed schedule
OE) Basis for the scope
OF) Work Breakdown Structure Deliverables
OG) List appropriate quality standards
OH) A list of project participants
1) Exclusions
OJ) Detailed description of the work.
arrow_forward
Case study
The contractor received a submittal package from the curtain wall subcontractor. Per the specifications, product
data, shop drawings, finish samples, fabrication sample, product test reports, field test reports, and design
analysis are required.
The product data, shop drawings, and finish samples are specified as action submittals, the other submittals are
specified to be informational submittals. The curtain wall shown on the drawings was a generic system and the
specifications provided a list of three acceptable systems, which had slightly different methods of fabrication and
attachment to the building structure.
When the curtain wall installation is 10% complete, the specifications call for the contractor to perform water
spray and air leakage tests. The results of these tests are to be submitted to the architect. The curtain wall
manufacturer prepared the action submittals, the product test reports, and the design analysis and gave them to
the subcontractor to submit.…
arrow_forward
Is it the responsibility of the Resident Project Representative to review shop drawings, evaluate sample submittals, approve substitute materials, or interpret the intent of the contract plans and specifications?
arrow_forward
Please provide the enough information and definition of these construction terms:
Civil engineer
Clearing and grubbing
Client
Commercial availability
Commercial building
Compaction test
Concrete cover
Concrete curing
Concrete Hollow Block (CHB)
Confined Space
Construction built out
Construction estimate
Construction firm
Construction plan
Construction schedule
Construction site
Contingency plan
Contract formation
Convenience outlet
Conversion
Crane
Critical path
Cross sectional area
Cut and fill
Daily Activity Report (DAR)
arrow_forward
what is the document that identifies the documents and the specific preconstruction services that are to be performed.
a. AIA
b. RFP
c. short list
d. Award
arrow_forward
c) Discuss the complete process of pre-qualification of contractors
arrow_forward
- Present a design proposal, utilising a selected alternative construction method, and explain how it is ‘fit for purpose’ in the given context.
- Present a design proposal that utilises alternative methods of construction.
arrow_forward
A practicing civil engineer attached his signature and seal on a set of construction plans and documents. However, on the day he attached his signature and seal, his professional license as a civil engineer has already expired the day before, and his application for renewal is still pending upon submission of some requirements for renewal. Is the signature and seal valid and acceptable? Explain.
arrow_forward
It is ALWAYS best to wait until construction drawings and specifications are complete before contacting pertinent regulatory agencies; then to submit the documents with a request for expedited review and approval.
True
False
arrow_forward
Pls Answer briefly. Thank you
If you are the designer, how are you going to resolve disputes that may arise between the owner and the contractor.
arrow_forward
The CalOSHA Construction Safety Orders is an extensive regulatory program that cover all safety
concerns during construction operations. Check all the statements that are true about this regulatory
program.
a. It requires every employer to have a written IIPP
b. Regular safety meetings are part of the IIPP
C. It requires fall protection when working near the edge at or above 7 feet high
d. A permit may be needed to enter a confined space
e. When working in environments where lead emissions are possible, employers are required to
perform an employee exposure assessment
arrow_forward
- Present a design proposal, utilising a selected alternative construction method, and explain how it is ‘fit for purpose’ in the given context.
1- Produce a design proposal, using computer-aided drawing tools, utilising alternative construction methods.
2- Present a design proposal that utilises alternative methods of construction.
3- Evaluate the effectiveness of using computer-aided drawing software and BIM.
4- Justify the use of a chosen alternative construction method.
arrow_forward
3. (1) Define critical path, ES, EF, LS, LF, dummy activity and slack.
(2) Cables By Us is bringing a new product on line to be manufactured in their current facility in
existing space. The owners have identified 11 activities and their precedence relationships.
(a) Draw the network diagram of this project
(b) Calculate the project completion time
(c) Identify the critical path
日
OF 5
SONY
arrow_forward
Please explain the photo attached
Subject: Construction Management
arrow_forward
How are the Specifications important to the Inspectors?
arrow_forward
Please explain the photo attached
arrow_forward
1. What types of transactions between the contractor and the owner or engineer/architect should bedocumented?
2. What happens when the terms of the Supplementary General Conditions are in conflict with the GeneralConditions?
3. Under CSI Format, explain the difference between the documents referred to as “General Conditions” and“General Requirements.”
4. What are the three principles of lean construction and why are they relevant to the environment?
5. What purpose does an audit trail of documents or transactions provide?
6. Give an example of a process to demonstrate how workflow could be used for contract administration.
7. Under the CSI Format, the definition of Contract Documents does not include the Notice Inviting Bids,Instructions to Bidders, or the Bid itself. Name the principal exception to this rule, wherein the term Contract Documents may include the Notice Inviting Bids, Instructions to Bidders, and the Bid itself.
8. What is the value of having a project extranet track…
arrow_forward
Classify the under listed instances into the appropriate types of contracts.
a. A standard form of construction contract issued by the International
Federation of Consulting Engineer (FIDIC).
b. A verbal promise to buy a 25-year son a car.
c. A written promise to buy a 30-year-old daughter a house. The
promise has been written and signed and sealed and delivered to
the daughter.
d. The supply by a wholesaler of 10,000 bricks to site following a
telephone request from the site agent.
arrow_forward
When is the final certificate issued?
arrow_forward
Civil Engineering
Q4:-what are the common problem being faced in the construction site.briefly discuss.
arrow_forward
1. Construction Management can best be defined as
a. The art and science of coordinating equipment and personnel as well as money to complete a
project on time
b. The art and science of completing a project on time while coordinating resources
c. The management and coordination of resources to complete a project on time
d. The art and science of coordinating manpower, machines, materials, money and time to complete a
project on time and within approved costs
2. Which of the following is defined as meeting or exceeding the needs of the customer?
a. Productivity
b. Quality
c. Control
d. Assurance
e. Value
3. Which of the following is NOT considered to be a general type of construction?
a. Residential
b. Municipal
c. Commercial
d. Industrial
е. Нeavy
4. Which of the following is the representative term for converting an annual value to a future value?
a. Uniform-series, compound amount factor
b. Single-payment, present worth factor
c. Uniform-series, present worth factor
d.…
arrow_forward
Using the same CPM diagram, what is the total project duration?
Immediate
Estimated
Activity
Activity Description
Predecessors
Duration
A
Excavate
2 weeks
Lay the foundation
Put up the rough wall
Put up the roof
Install the exterior plumbing
Install the interior plumbing
Put up the exterior siding
Do the exterior painting
B
A
4 weeks
C
10 weeks
D
C
6 weeks
4 weeks
5 weeks
7 weeks
9 weeks
7 weeks
8 weeks
4 weeks
E
C
F
E
G
D
E, G
Do the electrical work
F, I
Put up the wallboard
Install the flooring
Do the interior painting
Install the exterior fixtures
K
5 weeks
M
2 weeks
N
Install the interior fixtures
K, L
6 weeks
Total = 79 weeks
arrow_forward
Explain the following statement:The LBSR project was a self-certified project.
arrow_forward
Write the legal and risk plan for a building materials company?
arrow_forward
SEE MORE QUESTIONS
Recommended textbooks for you
Architectural Drafting and Design (MindTap Course...
Civil Engineering
ISBN:9781285165738
Author:Alan Jefferis, David A. Madsen, David P. Madsen
Publisher:Cengage Learning
Related Questions
- Please explain the photo attached Topic: STANDARD OF PROFESSIONAL PRACTICE (SPP) ON CONSTRUCTION MANAGEMENT SERVICESarrow_forwardCan a graduate in civil engineering course sign plans and supervise construction projects, even though he/she did not pass the board exam? Explain.arrow_forwardYour company, a G7 contractor is appointed as main contractor for construction of a new recreational building and facilities at Pantai Minyak Beku, Batu Pahat, Johor. You are chosen for a new position as Construction Contract Manager to administer the construction contract for those recreational buildings and facilities. Prepare your scope of work as a Construction Contract Manager for submission as part of the quality management system (QMS) documentation of the project. (C3) Open ended question.arrow_forward
- Given ann assessment on the role of the course in your education for CONSTRUCTION MATERIALS AND TESTING. No plagiarism and it must be not less than 10 sentences. For strict compliance. Thank you!arrow_forwardWhat is stop notice release bond method?When is it used?arrow_forwardOf the items listed below, identify which components are included in a scope of work? A) A description of the work. OB) Technical requirements Oc) Identification of major components OD) A detailed schedule OE) Basis for the scope OF) Work Breakdown Structure Deliverables OG) List appropriate quality standards OH) A list of project participants 1) Exclusions OJ) Detailed description of the work.arrow_forward
- Case study The contractor received a submittal package from the curtain wall subcontractor. Per the specifications, product data, shop drawings, finish samples, fabrication sample, product test reports, field test reports, and design analysis are required. The product data, shop drawings, and finish samples are specified as action submittals, the other submittals are specified to be informational submittals. The curtain wall shown on the drawings was a generic system and the specifications provided a list of three acceptable systems, which had slightly different methods of fabrication and attachment to the building structure. When the curtain wall installation is 10% complete, the specifications call for the contractor to perform water spray and air leakage tests. The results of these tests are to be submitted to the architect. The curtain wall manufacturer prepared the action submittals, the product test reports, and the design analysis and gave them to the subcontractor to submit.…arrow_forwardIs it the responsibility of the Resident Project Representative to review shop drawings, evaluate sample submittals, approve substitute materials, or interpret the intent of the contract plans and specifications?arrow_forwardPlease provide the enough information and definition of these construction terms: Civil engineer Clearing and grubbing Client Commercial availability Commercial building Compaction test Concrete cover Concrete curing Concrete Hollow Block (CHB) Confined Space Construction built out Construction estimate Construction firm Construction plan Construction schedule Construction site Contingency plan Contract formation Convenience outlet Conversion Crane Critical path Cross sectional area Cut and fill Daily Activity Report (DAR)arrow_forward
- what is the document that identifies the documents and the specific preconstruction services that are to be performed. a. AIA b. RFP c. short list d. Awardarrow_forwardc) Discuss the complete process of pre-qualification of contractorsarrow_forward- Present a design proposal, utilising a selected alternative construction method, and explain how it is ‘fit for purpose’ in the given context. - Present a design proposal that utilises alternative methods of construction.arrow_forward
arrow_back_ios
SEE MORE QUESTIONS
arrow_forward_ios
Recommended textbooks for you
- Architectural Drafting and Design (MindTap Course...Civil EngineeringISBN:9781285165738Author:Alan Jefferis, David A. Madsen, David P. MadsenPublisher:Cengage Learning
Architectural Drafting and Design (MindTap Course...
Civil Engineering
ISBN:9781285165738
Author:Alan Jefferis, David A. Madsen, David P. Madsen
Publisher:Cengage Learning