Homework 5
.docx
keyboard_arrow_up
School
Morgan State University *
*We aren’t endorsed by this school
Course
650
Subject
Industrial Engineering
Date
Dec 6, 2023
Type
docx
Pages
2
Uploaded by jabro51
5a:
Project-level SV = SV1 + SV2 + SV3 = 10 - 5 + 0 = 5
Project-level CV = CV1 + CV2 + CV3 = 5 + 0 - 5 = 0
Average SPI = (SPI1 + SPI2 + SPI3) / 3 = (1.333 + 0.75 + 1) / 3 ≈ 1.028
Average CPI = (CPI1 + CPI2 + CPI3) / 3 = (1.143 + 1 + 0.667) / 3 ≈ 0.937
A positive variance indicates that the project is performing better than planned in terms of
schedule or budget. However, a performance index less than 1.0 indicates that the project's
efficiency in utilizing resources or time is lower than planned. These two conditions can occur
simultaneously when the project is ahead of schedule or under budget, but it is not as efficient
as it should be with the resources or time it has saved. In other words, even though the project
is doing well in terms of schedule or budget, it might not be as efficient as expected, which
could indicate inefficiencies or resource issues within the project.
5b:
At my organization, we place a strong emphasis on continuous improvement and proactive
project management. To ensure that we effectively respond to variances and deviations in our
projects, we utilize several methods and tools that align with industry best practices. These
methods include:
Lessons Learned Register: As outlined in Section 4.4.3.1 of our project management framework,
we maintain a robust Lessons Learned Register. This register serves as a repository of knowledge
gained from past projects. It contains valuable information on both successful and challenging
project experiences. When variances occur, our project teams refer to the Lessons Learned
Register to identify effective responses and best practices that were applied in similar situations.
This proactive approach helps us avoid recurring issues and optimize project outcomes.
Quality Reports: Section 8.2.3.1 of our project management guidelines emphasizes the
importance of quality management. We maintain detailed Quality Reports that capture quality-
related issues, recommendations for process enhancements, and corrective action
recommendations. These reports are instrumental in addressing any quality variances or
deviations that may arise during project execution. By promptly identifying and addressing
quality issues, we ensure that our projects meet or exceed the established quality standards.
Alternatives Analysis: When a deviation occurs, our organization employs an Alternatives
Analysis approach. This method allows us to assess various corrective actions and preventive
measures systematically. By considering a range of options, we can select the most appropriate
response strategy to address the specific deviation effectively. This approach aligns with our
commitment to evidence-based decision-making and ensures that corrective actions are well-
suited to the unique circumstances of each project.
5c:
The notes from this week provides insights into several statistical methods for forecasting the
Estimate at Completion (EAC) in Earned Value Management (EVM). Each of these methods
makes different assumptions about future cost performance. Here are the assumptions
associated with each statistical method mentioned in the reading:
Statistical Estimate 1:
Assumption: This method assumes that future cost performance will be in accordance with the
original plan, regardless of past performance. It assumes that any cost overruns or underruns
experienced in the past will not continue, and future performance will align with the original
budget.
Statistical Estimate 2:
Assumption: This method assumes that future cost performance will be the same as the cost
performance observed up to the present. It considers the current Cost Performance Index (CPI)
as a reliable indicator of future performance. Essentially, it assumes that past performance
trends will continue.
Statistical Method 3:
Assumption: This method assumes that future cost performance will be influenced by both past
cost and schedule performance. It considers that if the project is behind schedule (Schedule
Performance Index, SPI, less than 1.0), additional resources may be allocated, impacting cost.
Statistical Method 3a:
Assumption: This method is similar to Method 3 but assumes that future cost performance will
be influenced jointly by past cost and schedule performance in some proportion. It allows for a
more flexible adjustment based on the combination of cost and schedule performance trends.
Statistical Method 4:
Assumption: This method considers using an average of the most recent Cost Performance
Index (CPI) values to forecast future cost performance. It assumes that the average CPI over the
last several reporting periods is a good predictor of future cost efficiency.
Your preview ends here
Eager to read complete document? Join bartleby learn and gain access to the full version
- Access to all documents
- Unlimited textbook solutions
- 24/7 expert homework help