6/7/23, 11:11 PM
Practice Quiz: Attempt review
https://moodle.cqu.edu.au/mod/quiz/review.php?attempt=4272445&cmid=3155262
1/19
Started on
Wednesday, 7 June 2023, 11:02 PM
State
Finished
Completed on
Wednesday, 7 June 2023, 11:11 PM
Time taken
8 mins 28 secs
Marks
22/40
Grade
6
out of 10 (
55
%)
Question 1
Incorrect
Mark 0 out of 1
Dashboard
/
My units
/ 2023 Term 1
/
PPMP20009_2231
/ Assessment
/ Practice Quiz
329. Which Agile technique is best identified by the following statement?
"It defines what the solution is and what is not"
Select one:
a.
User Stories
b.
Product Roadmap
c.
Visioning
d.
Relative Estimation
The correct answer is: Product Roadmap
6/7/23, 11:11 PM
Practice Quiz: Attempt review
https://moodle.cqu.edu.au/mod/quiz/review.php?attempt=4272445&cmid=3155262
2/19
Question 2
Incorrect
Mark 0 out of 1
Question 3
Incorrect
Mark 0 out of 1
Question 4
Correct
Mark 1 out of 1
261. Determine TRUE or FALSE
The following describes SCRUM event - Sprint:
"Product owner and development team negotiate which product backlog to be included in the
sprint"
Select one:
True
False
The correct answer is 'False'.
360. Determine TRUE or FALSE "Agile technique - VISIONING
consists of simple statements usually either with image or words to describe the greater purpose of the
software development work"
Select one:
True
False
The correct answer is 'True'.
327. Which Agile technique is best identified by the following statement?
"Measures progress of the vision through meeting the expectations of the stakeholders"
a.
Product Roadmap
b.
Relative Estimation
c.
User Stories
d.
Visioning
The correct answer is: Product Roadmap
6/7/23, 11:11 PM
Practice Quiz: Attempt review
https://moodle.cqu.edu.au/mod/quiz/review.php?attempt=4272445&cmid=3155262
3/19
Question 5
Incorrect
Mark 0 out of 1
Question 6
Incorrect
Mark 0 out of 1
320. Determine TRUE or FALSE The following are Agile Techniques:
Story Mapping
User Stories
Value Decomposition
Visioning
Select one:
True
False
The correct answer is 'False'.
33. The following are activities that would be undertaken in
IMPLEMENT
phase of the change management framework EXCEPT
Select one:
a.
Prepare organisation for change
b.
Clarify risks to the change plan
c.
Deliver project outputs
d.
Mobilise stakeholders
The correct answer is: Clarify risks to the change plan
6/7/23, 11:11 PM
Practice Quiz: Attempt review
https://moodle.cqu.edu.au/mod/quiz/review.php?attempt=4272445&cmid=3155262
4/19
Question 7
Correct
Mark 1 out of 1
Question 8
Correct
Mark 1 out of 1
384. The following are Stakeholder Analysis techniques EXCEPT:
Select one:
a.
Impact vs Interest Grid
b.
Power vs Influence Grid
c.
Power vs Interest Grid
d.
Impact vs Influence Grid
The correct answer is: Impact vs Interest Grid
31. The following are activities that would be undertaken in FORMULATE phase of the change management framework EXCEPT
Select one:
a.
Define the measures of benefits realisation
b.
Begin effective change communications
c.
Identify stakeholders and their expectations in the change
d.
Identify the resources required
The correct answer is: Define the measures of benefits realisation
6/7/23, 11:11 PM
Practice Quiz: Attempt review
https://moodle.cqu.edu.au/mod/quiz/review.php?attempt=4272445&cmid=3155262
5/19
Question 9
Incorrect
Mark 0 out of 1
Question 10
Incorrect
Mark 0 out of 1
39. Determine (TRUE or FALSE)
The following activities are undertaken during MANAGE TRANSITION
phase of the change management framework
Measure outcome and benefits
Mobilise stakeholders
Measure adoption rate
Transition output into business
Select one:
True
False
The correct answer is 'False'.
38. Determine (TRUE or FALSE)
The following activities are undertaken during IMPLEMENT
phase of the change management framework
Prepare organisation for change
Mobilise stakeholders
Clarify risks to the change plan
Deliver project outputs
Select one:
True
False
The correct answer is 'False'.
6/7/23, 11:11 PM
Practice Quiz: Attempt review
https://moodle.cqu.edu.au/mod/quiz/review.php?attempt=4272445&cmid=3155262
6/19
Question 11
Correct
Mark 1 out of 1
Question 12
Correct
Mark 1 out of 1
311. Which leadership style is best identified by the following statement?
"Encourages collaboration through interactive meetings, dialogs and knowledge sharing sessions"
Select one:
a.
Transformational
b.
Transactional
c.
Servant Leader
d.
Lasisez - Faire
The correct answer is: Servant Leader
312. Which leadership style is best identified by the following statement?
"Collaboration model versus the command-control model"
Select one:
a.
Servant Leader
b.
Laissez - Faire
c.
Transactional
d.
Transformational
The correct answer is: Servant Leader
Your preview ends here
Eager to read complete document? Join bartleby learn and gain access to the full version
- Access to all documents
- Unlimited textbook solutions
- 24/7 expert homework help
Related Questions
nity College | Pima x
B Module 12 Practice Assignment
6 Question 1- Module 12 Practice x
A ezto.mheducation.com/ext/map/index.html?_con=con&external_browser=D0&launchUrl=https%253A%252F%252Flms.mheducation.com%252Fmghmiddleware%252Fr
ediStay v4
E New Scorpion
O Redistay - (Unknown) U Ulitpro -New
e Scorpion (UAT)
5) Springfield - Home
inContact
Dashboards
RediStay v4 (UAT) -...
lodule 12 Practice Assignment_Ch.17 i
Saved
1
Challenge Problem 17-25 (Static) [LU 17-2 (2)]
A delivered price (including attachments) of a crawler dozer tractor is $135,000 with a residual value of 35%. The useful life of the
tractor is 7,700 hours
eBook
Print
a. What is total amount of depreciation allowed?
References
Total amount
b. What is the amount of depreciation per hour? (Round your answer to the nearest cent.)
Amount of depreciation
per hour
arrow_forward
Question 9
arrow_forward
time (hours)
pH
7.00
7.30
6.99
7.00
Assignment
1
2
7.12
7.25
7.12
7.20
3
720
7.16
720
7.16
4
6.98
7.00
6.94
7.00
5
6.99
6.99
6.99
6.98
6
7.00
6.93
7.02
6.93
7
6.92
7.00
6.92
7.02
Construct the X-Bar
charts and R- charts
6.88
6.82
6.94
6.99
7.10
7.00
7.00
7.00
for reporting your
results
10
721
7.02
721
7.04
11
7.01
6.86
7.01
6.90
12
6.86
6.98
6.90
6.98
13
6.90
7.00
6.87
7.00
14
7.01
7.04
7.01
7.05
15
7.00
6.95
7.00
6.99
16
7.09
7.20
7.03
7.20
17
6.89
7.14
6.87
7.15
18
6.98
6.80
6.98
6.89
19
7.00
6.90
7.00
6.90
20
7.20
7.00
723
7.00
21
7.04
7.03
7.08
7.00
22
6.90
6.92
6.98
6.92
23
7.00
7.00
7.00
7.00
24
7.00
6.97
7.01
6.98
arrow_forward
solve this i want now before 11 clock
arrow_forward
What term is used to describe the checkpoints (Go/No-go decision points) that occur during a project that also represent critical success factors (CSFs) for the project?
Question 14 options:
Work Breakdown Structures
Variance Reports
Feasibility Studies
Project Milestones
arrow_forward
Question 41
A ________ provides a translation of the project scope into specific activities.
Group of answer choices
Work breakdown structure (WBS)
Dependency matrix
Crashing plan
Resource
arrow_forward
Ongoing Clients 75
Client Attrition Rate for MRR: 30%
Avg MRR from New Business per Rep $ 15,000
Average Deal Size (MRR) $ 12,000
% of SQLs that Close 16%
% MQLs that Become SQLs 9%
# of Reps on Team 5
Avg Growth Deals per Rep per Month 2
Avg MQL per Month 600
Avg MRR from Growth Deals per Rep $ 20,000
What is the NEW BUSINESS MRR Current Year $ per Rep?
arrow_forward
Lenovo
Barmaining Time: 30 minutes, 26 seconds.
Question Completion Status:
Consider the following payoff Table
Decision Alternative
D1
D2
The State of Nature
0.79
1-0.79-
S1
52
5
8
8
4
D3
14
4
What is the payoff value for the D2 under S2 should be to keep the optimal solution always
optimal?(Do not writ the sign > or <)
(Round your answer to 2 decimal places)
Save and Submit to save and submit. Click Save All Answers to save all answers.
Save All Answers
arrow_forward
Example 2.39
Table 2.119 provides normal and crash times as well as normal and crash costs for the activities of
a project.
Table 2.119 Project activity details
Activity Normal Time (Weeks) Normal Cost (Lakhs) Crash Time (Weeks)
1-2
3
5
2-3
4
8
2-4
3
4
2-5
8
S
3-6
4
3
4-6
6
2
5-7
5
10
6-7
3
7
1
3
2
7
2
4
4
1
Crash Cost (Lakhs)
9
14
6
6
5
3
14
10
Project Network Analysis-1 | 141
(a) Draw the network and find the critical path.
(b) Using the above information, crash or shorten the activities step by step until the shortest
duration is reached.
MMM, VI Sem, Mumbai Univ, 2006
arrow_forward
Do it with refrences
arrow_forward
Question 6
6. Why does new product development theory show the process as an inverted triargle, with the first stage at the top of the triangle?
O Because the number of ideas that will result in viable new products decreases as the process progresses.
O Because there are more stage gates in the early stages of the process.
O Because more money is spent in the early stages of the process than at later stages.
O Because each project's potential revenue decreases as it progresses through the process
Question 8
8. Southwest Airlines screens potential employees rigorously and uses several unique interview processes to hire the right people. Southwest also has an extensive training progran for new employees
These tactics reduce
in service delivery,
O Varlability
O Overtead costs
O Search qualities
O Corsintence
Question 10
2 pts
10. Ambient Management, Inc was experiencing a gap in the services it was providing. It dosed the gap by ensuring that its customer-facing staff had the skills,…
arrow_forward
Question b. is the one academic question that is being inquired about.
arrow_forward
#3
Question 30
WBS stands for which of the following project management tools?
O work break schedule
O work breakdown schedule
O work break status
work breakdown structure
O work breakdown status
* Previous
MacBook Air
000
F2
08
000
F5
DD
F8
$
4
%23
%
&
5.
9
8.
arrow_forward
QUESTION 2
Three estimates were 15, 1, and 24, not given in any order. What is the Three-point estimate? Pick closest answer.
O 13
14
O 15
O 28
arrow_forward
A ng.cengage.com
earning
Bb https://learn-us-east-1-prod-fleet01-xythos.content.blackboardcdn.com/blackboard.learn.xythos
AP
Q Se.
E AA
Review
ritical Thinking Activities
Module 2 Critical Thinking Activities
Assignment Score: 0.00%
Save
Submit Assignment
Questions
ca2ce01h_Module2.03
« Question 3 of 5 »
1.
2.
Emma Jackson is thinking of starting a retail business with two friends who have extensive experience in
sales and business organization. They want to determine whether they should run the business as an e-
commerce website or a brick-and-mortar store. Research the pros and cons of e-commerce for businesses
o and recommend an option to Emma.
3.
4.
5.
MacBook Air
DII
DD
O O O O0
arrow_forward
Q1 LAB2
subject : production and operation management
please answer ASAP
arrow_forward
The unit of measure that is chosen for tracking schedule progress can affect the quality of the work.
Question 16 options:
True
False
arrow_forward
Q15. How the performance on a task is evaluated?
arrow_forward
10:15
←
Assignment for chapter One.pdf
Operation Research
Assignment for Chapter One
Instructor: Wehliye
Operation Research
K 7
ку
5. Operation research analysis does not:
a) Predict future operation
b) Collect the relative data
4G 83%
个
Part One: Multiple Choice
1. A feasible solution to an lp problem
a) Must satisfy all of the problems constraints simultaneously
b) Need not satisfy all of the constraints, only some of them
c) Must be a corner point of the feasible region
d) Must optimize the value of the objective function
2. Which of the following statements is true with respect to the optimal solution
of an LP problem?
|||
L
a) Every LP problem has an optimal solution b) Optimal solution of an LP
problem always occur at an extreme point c) At optimal solution, all
resources are completely used d) If an optimal solution exists, there will
always be at least one at a corner
3. While plotting constraints on a graph paper, terminal points on both the axes
are connected by straight line…
arrow_forward
* Question Completion Status:
QUESTION 7
The following is a simplex tableau:
Basis
Св
7.72X1
4.5X2
6.19X3
S1
S2
аз
RHS
X3
6.19
-1.25
1
-0.125
-0.75
12.5
S2
11.25
X1
7.72
1.25
1
-2.5
10.5
1
1
6.
6.19
-0.75
0.5
?
C-Z
0.75
-0.5
What is the value of Z
QUESTION 8
Minimize z = 4.5x1 + 4.5x2 + 4.28x3
(hundreds of dollars)
s.t:
?x1 + ?x2 + ?x3 > 140
(production capacity; hours)
arrow_forward
Instruction: Prepare a check sheet to analyze the data below from customer complaints, then prepare a list of recommendations that will address these complaints.
Case: Tip Top Markets
Tip Top Markets is a regional chain of supermarkets located in the southeastern United States. Karen Martin, manager of one of the stores, was disturbed by the large number of complaints from customers at her store, particularly on Tuesdays, so she obtained complaint records from the store’s customer service desk for the last nine Tuesdays.
arrow_forward
SEE MORE QUESTIONS
Recommended textbooks for you
Understanding Business
Management
ISBN:9781259929434
Author:William Nickels
Publisher:McGraw-Hill Education
Management (14th Edition)
Management
ISBN:9780134527604
Author:Stephen P. Robbins, Mary A. Coulter
Publisher:PEARSON
Spreadsheet Modeling & Decision Analysis: A Pract...
Management
ISBN:9781305947412
Author:Cliff Ragsdale
Publisher:Cengage Learning
Management Information Systems: Managing The Digi...
Management
ISBN:9780135191798
Author:Kenneth C. Laudon, Jane P. Laudon
Publisher:PEARSON
Business Essentials (12th Edition) (What's New in...
Management
ISBN:9780134728391
Author:Ronald J. Ebert, Ricky W. Griffin
Publisher:PEARSON
Fundamentals of Management (10th Edition)
Management
ISBN:9780134237473
Author:Stephen P. Robbins, Mary A. Coulter, David A. De Cenzo
Publisher:PEARSON
Related Questions
- nity College | Pima x B Module 12 Practice Assignment 6 Question 1- Module 12 Practice x A ezto.mheducation.com/ext/map/index.html?_con=con&external_browser=D0&launchUrl=https%253A%252F%252Flms.mheducation.com%252Fmghmiddleware%252Fr ediStay v4 E New Scorpion O Redistay - (Unknown) U Ulitpro -New e Scorpion (UAT) 5) Springfield - Home inContact Dashboards RediStay v4 (UAT) -... lodule 12 Practice Assignment_Ch.17 i Saved 1 Challenge Problem 17-25 (Static) [LU 17-2 (2)] A delivered price (including attachments) of a crawler dozer tractor is $135,000 with a residual value of 35%. The useful life of the tractor is 7,700 hours eBook Print a. What is total amount of depreciation allowed? References Total amount b. What is the amount of depreciation per hour? (Round your answer to the nearest cent.) Amount of depreciation per hourarrow_forwardQuestion 9arrow_forwardtime (hours) pH 7.00 7.30 6.99 7.00 Assignment 1 2 7.12 7.25 7.12 7.20 3 720 7.16 720 7.16 4 6.98 7.00 6.94 7.00 5 6.99 6.99 6.99 6.98 6 7.00 6.93 7.02 6.93 7 6.92 7.00 6.92 7.02 Construct the X-Bar charts and R- charts 6.88 6.82 6.94 6.99 7.10 7.00 7.00 7.00 for reporting your results 10 721 7.02 721 7.04 11 7.01 6.86 7.01 6.90 12 6.86 6.98 6.90 6.98 13 6.90 7.00 6.87 7.00 14 7.01 7.04 7.01 7.05 15 7.00 6.95 7.00 6.99 16 7.09 7.20 7.03 7.20 17 6.89 7.14 6.87 7.15 18 6.98 6.80 6.98 6.89 19 7.00 6.90 7.00 6.90 20 7.20 7.00 723 7.00 21 7.04 7.03 7.08 7.00 22 6.90 6.92 6.98 6.92 23 7.00 7.00 7.00 7.00 24 7.00 6.97 7.01 6.98arrow_forward
- solve this i want now before 11 clockarrow_forwardWhat term is used to describe the checkpoints (Go/No-go decision points) that occur during a project that also represent critical success factors (CSFs) for the project? Question 14 options: Work Breakdown Structures Variance Reports Feasibility Studies Project Milestonesarrow_forwardQuestion 41 A ________ provides a translation of the project scope into specific activities. Group of answer choices Work breakdown structure (WBS) Dependency matrix Crashing plan Resourcearrow_forward
- Ongoing Clients 75 Client Attrition Rate for MRR: 30% Avg MRR from New Business per Rep $ 15,000 Average Deal Size (MRR) $ 12,000 % of SQLs that Close 16% % MQLs that Become SQLs 9% # of Reps on Team 5 Avg Growth Deals per Rep per Month 2 Avg MQL per Month 600 Avg MRR from Growth Deals per Rep $ 20,000 What is the NEW BUSINESS MRR Current Year $ per Rep?arrow_forwardLenovo Barmaining Time: 30 minutes, 26 seconds. Question Completion Status: Consider the following payoff Table Decision Alternative D1 D2 The State of Nature 0.79 1-0.79- S1 52 5 8 8 4 D3 14 4 What is the payoff value for the D2 under S2 should be to keep the optimal solution always optimal?(Do not writ the sign > or <) (Round your answer to 2 decimal places) Save and Submit to save and submit. Click Save All Answers to save all answers. Save All Answersarrow_forwardExample 2.39 Table 2.119 provides normal and crash times as well as normal and crash costs for the activities of a project. Table 2.119 Project activity details Activity Normal Time (Weeks) Normal Cost (Lakhs) Crash Time (Weeks) 1-2 3 5 2-3 4 8 2-4 3 4 2-5 8 S 3-6 4 3 4-6 6 2 5-7 5 10 6-7 3 7 1 3 2 7 2 4 4 1 Crash Cost (Lakhs) 9 14 6 6 5 3 14 10 Project Network Analysis-1 | 141 (a) Draw the network and find the critical path. (b) Using the above information, crash or shorten the activities step by step until the shortest duration is reached. MMM, VI Sem, Mumbai Univ, 2006arrow_forward
- Do it with refrencesarrow_forwardQuestion 6 6. Why does new product development theory show the process as an inverted triargle, with the first stage at the top of the triangle? O Because the number of ideas that will result in viable new products decreases as the process progresses. O Because there are more stage gates in the early stages of the process. O Because more money is spent in the early stages of the process than at later stages. O Because each project's potential revenue decreases as it progresses through the process Question 8 8. Southwest Airlines screens potential employees rigorously and uses several unique interview processes to hire the right people. Southwest also has an extensive training progran for new employees These tactics reduce in service delivery, O Varlability O Overtead costs O Search qualities O Corsintence Question 10 2 pts 10. Ambient Management, Inc was experiencing a gap in the services it was providing. It dosed the gap by ensuring that its customer-facing staff had the skills,…arrow_forwardQuestion b. is the one academic question that is being inquired about.arrow_forward
arrow_back_ios
SEE MORE QUESTIONS
arrow_forward_ios
Recommended textbooks for you
- Understanding BusinessManagementISBN:9781259929434Author:William NickelsPublisher:McGraw-Hill EducationManagement (14th Edition)ManagementISBN:9780134527604Author:Stephen P. Robbins, Mary A. CoulterPublisher:PEARSONSpreadsheet Modeling & Decision Analysis: A Pract...ManagementISBN:9781305947412Author:Cliff RagsdalePublisher:Cengage Learning
- Management Information Systems: Managing The Digi...ManagementISBN:9780135191798Author:Kenneth C. Laudon, Jane P. LaudonPublisher:PEARSONBusiness Essentials (12th Edition) (What's New in...ManagementISBN:9780134728391Author:Ronald J. Ebert, Ricky W. GriffinPublisher:PEARSONFundamentals of Management (10th Edition)ManagementISBN:9780134237473Author:Stephen P. Robbins, Mary A. Coulter, David A. De CenzoPublisher:PEARSON
Understanding Business
Management
ISBN:9781259929434
Author:William Nickels
Publisher:McGraw-Hill Education
Management (14th Edition)
Management
ISBN:9780134527604
Author:Stephen P. Robbins, Mary A. Coulter
Publisher:PEARSON
Spreadsheet Modeling & Decision Analysis: A Pract...
Management
ISBN:9781305947412
Author:Cliff Ragsdale
Publisher:Cengage Learning
Management Information Systems: Managing The Digi...
Management
ISBN:9780135191798
Author:Kenneth C. Laudon, Jane P. Laudon
Publisher:PEARSON
Business Essentials (12th Edition) (What's New in...
Management
ISBN:9780134728391
Author:Ronald J. Ebert, Ricky W. Griffin
Publisher:PEARSON
Fundamentals of Management (10th Edition)
Management
ISBN:9780134237473
Author:Stephen P. Robbins, Mary A. Coulter, David A. De Cenzo
Publisher:PEARSON