a) The Newmont Mining Company at Ahafo in the Bono region of Ghana requested a dedicated power supply line from Kumasi in the Ashanti region of Ghana to feed its mining roller mills. The World Bank helped the Government of Ghana to fund the project. A company won the bid and came up with the design specifications as follows: The system would be a three-phase 138-KV transmission line and the total power to be connected to the line is 49-MV and would be operating at a 0.85 lagging power factor due to the large rotating motors in the roller mills. The line constants would have length of 120km long line with Z = 95∟78ºΩ and Y = 0.001∟90ºS. They are proposing to use nominal -T circuit representation in their analysis. If they are to provide: (i) The A, B, C and D constants of the line. (ii) The voltage from Kumasi to the Newmont

Power System Analysis and Design (MindTap Course List)
6th Edition
ISBN:9781305632134
Author:J. Duncan Glover, Thomas Overbye, Mulukutla S. Sarma
Publisher:J. Duncan Glover, Thomas Overbye, Mulukutla S. Sarma
Chapter8: Symmetrical Components
Section: Chapter Questions
Problem 8.42P
icon
Related questions
icon
Concept explainers
Question

a) The Newmont Mining Company at Ahafo in the Bono region of Ghana requested a
dedicated power supply line from Kumasi in the Ashanti region of Ghana to feed its
mining roller mills. The World Bank helped the Government of Ghana to fund the
project. A company won the bid and came up with the design specifications as follows:
The system would be a three-phase 138-KV transmission line and the total power to be
connected to the line is 49-MV and would be operating at a 0.85 lagging power factor
due to the large rotating motors in the roller mills. The line constants would have length
of 120km long line with Z = 95∟78ºΩ and Y = 0.001∟90ºS.
They are proposing to use nominal -T circuit representation in their analysis. If they are
to provide:
(i) The A, B, C and D constants of the line.
(ii) The voltage from Kumasi to the Newmont
What are the values you think the company that won the bid would provide?


b) Using the information provided in a) above, Newmont Mining Company wants to know:
(i) The total current(I) they would be drawing from kumasi.
(ii) The power factor the system would be operating at from Kumasi.
(iii) The effectiveness of the transmission line design
What values from your understanding would the transmission line company provide to
Newmont Mining Company?


c) Two power system transmission engineers designed a transmission system. One used
the lumped parameters and the other used distributed parameters in their transmission
line analysis. Could you kindly evaluate the differences of these parameters chosen by
the two engineers?

Expert Solution
steps

Step by step

Solved in 3 steps

Blurred answer
Knowledge Booster
Transmission line parameter
Learn more about
Need a deep-dive on the concept behind this application? Look no further. Learn more about this topic, electrical-engineering and related others by exploring similar questions and additional content below.
Similar questions
  • SEE MORE QUESTIONS
Recommended textbooks for you
Power System Analysis and Design (MindTap Course …
Power System Analysis and Design (MindTap Course …
Electrical Engineering
ISBN:
9781305632134
Author:
J. Duncan Glover, Thomas Overbye, Mulukutla S. Sarma
Publisher:
Cengage Learning