An engineering plant has developed the accompanying supply, demand, cost and inventory data. The engineering plant has a constant workforce and meets all its demands. Allocate production capacity to satisfy demand at a minimum cost. What is the cost of this plan? (Assume that back ordering is not a viable alternative for the plant) Demand forecast Period Demand (Unit) 1 650 2 700 3 900 Supply Capacity available (units) Period Regular time Overtime Subcontract 1 350 100 250 2 450 100 250 3 500 100 250 Other Data Initial Inventory 100 units Regular-time cost per unit R 50 Overtime cost per unit R 65 Subcontract cost per unit R 80 Carrying cost per unit per period R 1 Back order cost per unit per period R 4
An engineering plant has developed the accompanying supply, demand, cost and inventory data. The engineering plant has a constant workforce and meets all its demands. Allocate production capacity to satisfy demand at a minimum cost. What is the cost of this plan? (Assume that back ordering is not a viable alternative for the plant) Demand forecast Period Demand (Unit) 1 650 2 700 3 900 Supply Capacity available (units) Period Regular time Overtime Subcontract 1 350 100 250 2 450 100 250 3 500 100 250 Other Data Initial Inventory 100 units Regular-time cost per unit R 50 Overtime cost per unit R 65 Subcontract cost per unit R 80 Carrying cost per unit per period R 1 Back order cost per unit per period R 4
Practical Management Science
6th Edition
ISBN:9781337406659
Author:WINSTON, Wayne L.
Publisher:WINSTON, Wayne L.
Chapter2: Introduction To Spreadsheet Modeling
Section: Chapter Questions
Problem 33P: Assume the demand for a companys drug Wozac during the current year is 50,000, and assume demand...
Related questions
Question
An engineering plant has developed the accompanying supply, demand, cost and inventory data. The engineering plant has a constant workforce and meets all its demands. Allocate production capacity to satisfy demand at a minimum cost. What is the cost of this plan?
(Assume that back ordering is not a viable alternative for the plant)
Demand
Period |
Demand (Unit) |
1 |
650 |
2 |
700 |
3 |
900 |
Supply Capacity available (units)
Period |
Regular time |
Overtime |
Subcontract |
1 |
350 |
100 |
250 |
2 |
450 |
100 |
250 |
3 |
500 |
100 |
250 |
Other Data
Initial Inventory |
100 units |
Regular-time cost per unit |
R 50 |
Overtime cost per unit |
R 65 |
Subcontract cost per unit |
R 80 |
Carrying cost per unit per period |
R 1 |
Back order cost per unit per period |
R 4 |
Expert Solution
This question has been solved!
Explore an expertly crafted, step-by-step solution for a thorough understanding of key concepts.
Step by step
Solved in 2 steps with 5 images
Knowledge Booster
Learn more about
Need a deep-dive on the concept behind this application? Look no further. Learn more about this topic, operations-management and related others by exploring similar questions and additional content below.Recommended textbooks for you
Practical Management Science
Operations Management
ISBN:
9781337406659
Author:
WINSTON, Wayne L.
Publisher:
Cengage,
Practical Management Science
Operations Management
ISBN:
9781337406659
Author:
WINSTON, Wayne L.
Publisher:
Cengage,