Effort Task Deck Predecessors (Days) Plan A Design deck 40 Buy materials 24 A Construction Dig holes 8 A Cut posts 4 E Install posts 4 C, D F Pour concrete 2 E Cut wood for floor B H Install floor 8 Cut wood for railing D Install railing 12 K Paint deck F, Н, Ј B. 4.

Management, Loose-Leaf Version
13th Edition
ISBN:9781305969308
Author:Richard L. Daft
Publisher:Richard L. Daft
Chapter7: Planning And Goal Setting
Section: Chapter Questions
Problem 2ED
icon
Related questions
icon
Concept explainers
Topic Video
Question
100%

Given the data (see table below):

  • Draw a network diagram
  • Determine the duration of the project
  • Indicate the critical path
  • Determine the float for each task
  • Describe possible ways to reduce the duration of the project

 

Effort
Task
Deck
Predecessors
(Days)
Plan
Design deck
40
Buy materials
24
Construction
C
Dig holes
8
A
Cut posts
4
E
Install posts
4
C, D
F
Pour concrete
E
Cut wood for floor
4
Install floor
8
G
Cut wood for railing
D
Install railing
12
K
Paint deck
F, H, J
B.
2.
2.
2.
Transcribed Image Text:Effort Task Deck Predecessors (Days) Plan Design deck 40 Buy materials 24 Construction C Dig holes 8 A Cut posts 4 E Install posts 4 C, D F Pour concrete E Cut wood for floor 4 Install floor 8 G Cut wood for railing D Install railing 12 K Paint deck F, H, J B. 2. 2. 2.
Expert Solution
trending now

Trending now

This is a popular solution!

steps

Step by step

Solved in 2 steps with 4 images

Blurred answer
Knowledge Booster
Inventory management
Learn more about
Need a deep-dive on the concept behind this application? Look no further. Learn more about this topic, management and related others by exploring similar questions and additional content below.
Similar questions
  • SEE MORE QUESTIONS
Recommended textbooks for you
Management, Loose-Leaf Version
Management, Loose-Leaf Version
Management
ISBN:
9781305969308
Author:
Richard L. Daft
Publisher:
South-Western College Pub