Question
Chapter 10, Problem 20P
(a):
To determine
Calculated the incremental benefit cost ratio.
(b):
To determine
Calculated the new incremental cost benefit ratio
(c):
To determine
Selection of the project.
Expert Solution & Answer
Want to see the full answer?
Check out a sample textbook solutionStudents have asked these similar questions
which projects should be considered as the base alternative and the first-choice alternative.
Is the Benefit-cost analysis a decision-making tool for systematically developing useful information about the desirable and undesirable effects of public projects?
Describe the difficulties involved in the public-project analysis?
Chapter 10 Solutions
Pearson eText for Engineering Economy -- Instant Access (Pearson+)
Ch. 10 - Prob. 1PCh. 10 - Prob. 2PCh. 10 - Prob. 3PCh. 10 - A retrofitted space-heating system is being...Ch. 10 - Prob. 5PCh. 10 - Prob. 6PCh. 10 - Prob. 7PCh. 10 - Prob. 8PCh. 10 - Prob. 9PCh. 10 - Prob. 10P
Ch. 10 - Prob. 11PCh. 10 - Prob. 12PCh. 10 - Prob. 13PCh. 10 - Prob. 14PCh. 10 - Prob. 15PCh. 10 - Prob. 16PCh. 10 - Four mutually exclusive projects are being...Ch. 10 - Two municipal cell tower designs are being...Ch. 10 - Prob. 19PCh. 10 - Prob. 20PCh. 10 - Prob. 21PCh. 10 - Prob. 22PCh. 10 - You have been requested to recommend one of the...Ch. 10 - Prob. 24PCh. 10 - Prob. 25PCh. 10 - Prob. 26FECh. 10 - Prob. 27FECh. 10 - Prob. 28FECh. 10 - Prob. 29FECh. 10 - Prob. 30FECh. 10 - Prob. 31FE
Knowledge Booster
Similar questions
- The citizen-based Capital Improvement Projects (CIP) Committee for the city of Dundee has recommended a $25 million bond issue for the purchase of greenbelt/floodplain land to preserve low-lying green areas and wildlife habitat. Developers oppose the proposal due to the reduction of available land for commercial development. The city engineer and economic development director have made preliminary estimates for some obvious areas over a projected 15-year planning horizon. The inaccuracy of these estimates is made very clear in a report to the Dundee City Council. The estimates are not yet classified as costs, benefits, or disbenefits.arrow_forwardWhat is the essential difference between the conventional and modified versions of the benefit–cost ratio? Is it possible for these two measures to provide conflicting recommendations regarding invest/do-not-invest decisions?arrow_forwardThe Texas Department of Transportation is considering in improving accident prevention countermeasures on the state's accident-prone public highways and bridges. The following set of projects has been recommended for evaluation at three different locations and assumes the budget is $20 million. All alternatives are mutually independent projects. Determine the best combination of projects within the budget constraint.(a) II-Band III-B only(b) I-A, II-A, and III-B(c) 1-B, III-A, and III-B(d) 11-B and IIl-Barrow_forward
- The two alternatives shown are under consideration for improving security at a facility. Determine which one should be selected, if any, based on a B/C analysis. Consider an interest rate of 7% per year and a 10-year study period. Additional information is provided in Table Q 6(b). Page 4 of 5 Table Q 6(b) Alternative 1: Extra Cameras | Alternative 2: New Sensors First cost, $ Annual O&M cost, $ 38000 87000 49000 64000 Annual benefits, $ Annual disbenefits, $ 110000 160000 26000arrow_forwardWith interest at 10%, what is the benefit-cost ratio for this government project? Initial Cost $201,767 Additional costs at the end of year 1 and year 2 Benefits at end of year 1 and year 2 Annual benefits at end of year 3 through year 10 Enter your answer as follow: 12.34 $28,755/year $0/year $108,308/yeararrow_forwardThe city of Jefferson is reviewing the benefits and costs of a potential universal water-metering program. Two options are considered:• Option I: Treated Surface Water Only Benefits of Deferring/DownsizingWater and Sewer Projects-$28.l millionCosts of Metering-$9.3 million Benefit-Cost Ratio-3.02• Option 2: Treated Surface Water Supplemented By 40 MUDay Groundwater Benefits of Deferring/Downsizing Water and Sewer Projects-$38.9 millionCosts of Metering (and groundwater development)-$14.7 millionBenefit-Cost Ratio-2.65 Which option should the city implement, assuming that the city has enough money to fund either project?(a) Option 1.(b) Option 2.(c) Neither.( d) Both options.arrow_forward
- Your employer is trying to select from a list of possible capital projects. The projects, along with their cost and benefits, are listed below. The capital budget available is $1 million. In addition to spending constraints, your employer would like to select at least 2 projects. Projects 4 and 1 cannot both be selected together. Formulate the problem as a linear program and determine the optimal solution. Project Cost Net Present Value $260, 000 $290, 000 1 $750,000 2 $740.000 3 $225,000 $550,000 4 $260,000 $760,000 $300,000 $780,000 Which projects should be selected? Project 1 will Project 2 will Project 3 will Project 4 will Project 5 will What is the total net present value of these projects? Total net present valuearrow_forwardCost-benefit analysis is used to determine the desirability of investing in a project (such as a dam, factory, or public park) by figuring whether its present and future economic benefits outweigh its present and future economic costs. True Falsearrow_forwardFor each of the following problems, (a) draw the cash flow diagram; (b) present clean and clear manual solutions to the problem; (c) highlight the final answer (only the final answer as required by the problem) by enclosing it within a box. NO EXCEL To provide drinking water as part of its 60-year plan, a west coast city is considering constructing a pipeline for importing water from a nearby community that has a plentiful supply of brackish groundwater. A full-sized pipeline can be constructed at a cost of $100 million now. Alternatively, a smaller pipeline can be constructed now for $60 million and enlarged 25 years from now for another $100 million. The pumping cost will be $20,000 per year higher for the smaller pipeline during the first 25 years but will be approximately the same thereafter. Both pipelines are expected to have the same useful life with no salvage value. At an interest rate of 10% per year compounded semiannually, which alternative is more economical?arrow_forward
- List two advantages of a public-private partnership (PPP).arrow_forwardRecent development near Eugene, Oregon, has identified a need for improved access to Interstate 5 at one location. Civil engineers and public planners are considering three alternative access plans. Benefits are estimated for the public in general; disbenefits primarily affect some local proprietors who will see traffic pattern changes as undesirable. Costs are monetary for construction and upkeep, and savings are a reduction in cost of those operations today that will not be necessary in the future. All figures are relative to the present situation, retention of which is still an alternative, and are annualized over the 20-year planning horizon. Solve, a. What is the B/C ratio for each of these alternatives? b. Using incremental B/C ratio analysis, which alternative should be selected? c. Determine the value of B − C for each alternative.arrow_forwardA local government is considering promoting to urism in the city. It will cost$8,000 to develop a plan. The anticipated annual benefits and costs are as follows:Annual benefits: Increased local income and tax collections $ 125,000Annual support service: Parking lot expansion, rest room. $50,000patrol car, and street repairIf the city government uses a discount rate of 8% and a study period of fiveyears. is this tourism project justifiable according to the benefit-cost analysis?arrow_forward
arrow_back_ios
SEE MORE QUESTIONS
arrow_forward_ios
Recommended textbooks for you
- Principles of Economics (12th Edition)EconomicsISBN:9780134078779Author:Karl E. Case, Ray C. Fair, Sharon E. OsterPublisher:PEARSONEngineering Economy (17th Edition)EconomicsISBN:9780134870069Author:William G. Sullivan, Elin M. Wicks, C. Patrick KoellingPublisher:PEARSON
- Principles of Economics (MindTap Course List)EconomicsISBN:9781305585126Author:N. Gregory MankiwPublisher:Cengage LearningManagerial Economics: A Problem Solving ApproachEconomicsISBN:9781337106665Author:Luke M. Froeb, Brian T. McCann, Michael R. Ward, Mike ShorPublisher:Cengage LearningManagerial Economics & Business Strategy (Mcgraw-...EconomicsISBN:9781259290619Author:Michael Baye, Jeff PrincePublisher:McGraw-Hill Education
Principles of Economics (12th Edition)
Economics
ISBN:9780134078779
Author:Karl E. Case, Ray C. Fair, Sharon E. Oster
Publisher:PEARSON
Engineering Economy (17th Edition)
Economics
ISBN:9780134870069
Author:William G. Sullivan, Elin M. Wicks, C. Patrick Koelling
Publisher:PEARSON
Principles of Economics (MindTap Course List)
Economics
ISBN:9781305585126
Author:N. Gregory Mankiw
Publisher:Cengage Learning
Managerial Economics: A Problem Solving Approach
Economics
ISBN:9781337106665
Author:Luke M. Froeb, Brian T. McCann, Michael R. Ward, Mike Shor
Publisher:Cengage Learning
Managerial Economics & Business Strategy (Mcgraw-...
Economics
ISBN:9781259290619
Author:Michael Baye, Jeff Prince
Publisher:McGraw-Hill Education