Textbook Question
Chapter 10, Problem 29FE
A flood control project with a life of 16 years will require an investment of $60,000 and annual maintenance costs of $5,000. The project will provide no benefits for the first two years but will save $24,000 per year in flood damage starting in the third year. The appropriate MARR is 12% per year. Use this information to answer problems 10-29 and 10-30. Select the closest answer.
10-29. What is the conventional B–C ratio for the flood control project?
- (a) 1.53
- (b) 1.33
- (c) 1.76
- (d) 2.20
- (e) 4.80
Expert Solution & Answer
Want to see the full answer?
Check out a sample textbook solutionStudents have asked these similar questions
The estimated negative cash flows for three design alternatives are shown below. The MARR is 13%
per year and the study period is four years. Which alternative is best based on the IRR method?
Doing nothing is not an option.
Capital
investment
Annual expenses
EOY
0
A. Alternative B
B. Alternative A
C. Alternative C
1-4
A
$82,400
6,200
Alternative
B
$64,500
12,100
с
$71,900
9,550
Which alternative would you choose as a base one? Choose the correct answer below.
The estimated negative cash flows for three design alternatives are shown below. The MARR is 10% per year and the study period is four years.
Which alternative is best based on the IRR method? Doing nothing is not an option.
Capital
investment
Annual expenses
OA. Alternative B
OB. Alternative C
OC. Alternative A
EOY
0
1-4
A
$85,700
8,500
Alternative
B
$64,500
Which alternative would you choose as a base one? Choose the correct answer below.
15,150
C
$71,900
12,450
The estimated negative cash flows for three design alternatives are shown below. The MARR is 14% per year and the
study period is five years. Which alternative is best based on the IRR method? Doing nothing is not an option.
Capital
investment
Annual expenses
EOY
0
A. Alternative C
B. Alternative B
OC. Alternative A
1-5
CLEAN
A
$81,500
7,500
Alternative
B
$64,400
12,620
Which alternative would you choose as a base one? Choose the correct answer below.
Analyze the difference between the base alternative and the second-choice alternative.
C
$71,000
10,420
Chapter 10 Solutions
EBK ENGINEERING ECONOMY
Ch. 10 - The Adams Construction Company is bidding on a...Ch. 10 - Prob. 2PCh. 10 - Prob. 3PCh. 10 - A retrofitted space-heating system is being...Ch. 10 - Prob. 5PCh. 10 - Prob. 6PCh. 10 - Prob. 7PCh. 10 - Prob. 8PCh. 10 - Prob. 9PCh. 10 - Prob. 10P
Ch. 10 - Prob. 11PCh. 10 - Prob. 12PCh. 10 - Prob. 13PCh. 10 - Prob. 14PCh. 10 - Prob. 15PCh. 10 - Prob. 16PCh. 10 - Four mutually exclusive projects are being...Ch. 10 - Two municipal cell tower designs are being...Ch. 10 - Prob. 19PCh. 10 - Prob. 20PCh. 10 - Prob. 21PCh. 10 - Prob. 22PCh. 10 - You have been requested to recommend one of the...Ch. 10 - Prob. 24PCh. 10 - Prob. 25PCh. 10 - Prob. 26FECh. 10 - Prob. 27FECh. 10 - Prob. 28FECh. 10 - A flood control project with a life of 16 years...Ch. 10 - Prob. 30FECh. 10 - Prob. 31FE
Knowledge Booster
Learn more about
Need a deep-dive on the concept behind this application? Look no further. Learn more about this topic, economics and related others by exploring similar questions and additional content below.Similar questions
- Alternative 3 is incorrect EUAC=( Equivalent Annaul COst of Initial Investment)+ (Expected Moderate annaual flood damage cost )+ (expected severe annaual flood cost )arrow_forwardA new manufacturing line is being built and your team has narrowed it down to 2 options. Which one is the best option using a 20% rate to evaluate each option? Answer the question by entering the amount of savings by choosing the best option. Margin of error: +/- 10 Enter your answer as a positive number representing savings from one option to another. Hint: When you use Net present Worth Analysis you must must LCM of the lives to assess each option over the same period. Option A B Operating First and Salvage Cost Maintenance Value Cost/Yr $18M $5M $25M $3M 501,025 $4M $6M Life 10 years 20 yearsarrow_forwardOptions for iii are "knows" and "doesn't know"arrow_forward
- The following four alternative investments are being compared at MARR of 12%. Which investment is the most economical over the entire service life? Alt. L Alt. W 10 10 $590,000 $645,000 Alt. D 10 $495,000 14.2% 9 13.4% 15% 6 5 Service life (years) Net PW IRR Disc payback period (yrs) Alt. X 10 $533,000 16.2% 8 OA. Alternative D because it has the longest payback period OB. Alternative W because it has the highest net PW OO C. Alternative L because it has the shortest payback period OD. Alternative X because it has the highest IRRarrow_forwardA major equipment purchase is being considered by Metro Atlanta. The initial cost is determined to be $1,000,000. It is estimated that this new equipment will save $100,000 the first year and increase gradually by $50,000 every year for the next 6 years. MARR=10% a. Using Benefit- Cost analysis, what is the Benefit/Cost ratio for this equipment purchase? b. Based on the Benefit/Cost analysis should Metro Atlanta purchase the equipment?arrow_forwardIC OM B D Life/years X Z Y X $320,000 $45,000 $110,000 $20,000 10 W Y $540,000 $35,000 $150,000 $45,000 20 Based on the above ME alternatives and using the B/C analysis, which alternative we should select?i=10%. Z $300,000 $50,000 $80,000 $10,000 10 W $330,000 $20,000 $95,000 $30,000 20 V $250,000 $40,000 $90,000 $10,000 15arrow_forward
- Which one of the following descriptions is correct according to this extensive form? (I think it's 3rd option but unsure)arrow_forwardThe estimated negative cash flows for three design alternatives are shown below. The MARR is 10% per year and the study period is four years. Which alternative is best based on the IRR method? Doing nothing is not an option. A. Alternative B OB. Alternative C OC. Alternative A Capital investment Annual expenses EOY 0 IRR A( 1-4 A $85,700 8,500 Alternative B $64,500 Which alternative would you choose as a base one? Choose the correct answer below. 15,150 Analyze the difference between the base alternative and the second-choice alternative. 7)=[ %. (Round to two decimal places.) C $71,900 12,450arrow_forwardPROBLEM #7: Three alternatives to incorporate improved techniques to manufacture Vertical Axis Wind Turbine have been developed and costed. Compare the alternatives below using capitalized cost and an interest rate of 12% per 4,55 and determine the best alternative among the following: First Alternative Second Alternative Third Alternative First Cost Php. 2,000.000 Php 3,000,000 Php 10,000,000 Net income per quarter Php. 300.000 Php 100,000 Php 400,000 Salvage value Php. 50.000 Php 70,000 N/A Life years 4 8 00arrow_forward
- Alternative Annualized first cost. $/year Annual M&O cost. $/year Annual benefits, $/year Annual disbenefits, $/year Life, years Multiple Choice O O fund both X and Y fund neither fund Y fund X 60,000 90.000 45,000 35,000 110.000 150.000 20,000 45,000 Show Transcribed Text for the two independent projects shown determine which if any should be funded i=10% per year using B/C ratio method.arrow_forwardA city government feels that the energy production capacity must be expanded to meet anticipated demands for energy. There are three alternatives to consider: @A nuclear facility with an investment of $250 million, operating costs of $3 million per year and life of 20 years. @ A coal plant with an investment of $200 million operating costs of $10 million per year and a life of 20 years. 26°C I P Type here to searcharrow_forwardEngineering Economics Bawal gumamit ng excel( Don't use Excel) A small company has P20,000 in surplus capital that it wishes to invest in new revenue producing projects. Three independent sets of mutually exclusive projects have been developed. The useful life of each is five years and all market values are zero. You have been asked to perform an IRR analysis to select the best combination of projects. If the MARR is 12% per year, which combination of projects would you recommend?arrow_forward
arrow_back_ios
SEE MORE QUESTIONS
arrow_forward_ios
Recommended textbooks for you
- Principles of Economics (12th Edition)EconomicsISBN:9780134078779Author:Karl E. Case, Ray C. Fair, Sharon E. OsterPublisher:PEARSONEngineering Economy (17th Edition)EconomicsISBN:9780134870069Author:William G. Sullivan, Elin M. Wicks, C. Patrick KoellingPublisher:PEARSON
- Principles of Economics (MindTap Course List)EconomicsISBN:9781305585126Author:N. Gregory MankiwPublisher:Cengage LearningManagerial Economics: A Problem Solving ApproachEconomicsISBN:9781337106665Author:Luke M. Froeb, Brian T. McCann, Michael R. Ward, Mike ShorPublisher:Cengage LearningManagerial Economics & Business Strategy (Mcgraw-...EconomicsISBN:9781259290619Author:Michael Baye, Jeff PrincePublisher:McGraw-Hill Education
Principles of Economics (12th Edition)
Economics
ISBN:9780134078779
Author:Karl E. Case, Ray C. Fair, Sharon E. Oster
Publisher:PEARSON
Engineering Economy (17th Edition)
Economics
ISBN:9780134870069
Author:William G. Sullivan, Elin M. Wicks, C. Patrick Koelling
Publisher:PEARSON
Principles of Economics (MindTap Course List)
Economics
ISBN:9781305585126
Author:N. Gregory Mankiw
Publisher:Cengage Learning
Managerial Economics: A Problem Solving Approach
Economics
ISBN:9781337106665
Author:Luke M. Froeb, Brian T. McCann, Michael R. Ward, Mike Shor
Publisher:Cengage Learning
Managerial Economics & Business Strategy (Mcgraw-...
Economics
ISBN:9781259290619
Author:Michael Baye, Jeff Prince
Publisher:McGraw-Hill Education
Valuation Analysis in Project Finance Models - DCF & IRR; Author: Financial modeling;https://www.youtube.com/watch?v=xDlQPJaFtCw;License: Standard Youtube License