Question
Chapter 10, Problem 29P
a)
Summary Introduction
To determine: The standard time for the operation
Introduction: Time study is the basis that helps set the standard time; it would time a sample of the performance of the worker.
b)
Summary Introduction
To determine: The number of sample sizes required.
Introduction: Thesample size is required to determine the number of observations that are necessary to find the true cycle time.
Expert Solution & Answer
Want to see the full answer?
Check out a sample textbook solutionStudents have asked these similar questions
Question text
Which of the following detail the exact manner in which any work is to be performed?
a.
Methods
b.
Procedures
c.
Programmes
d.
Purpose
Question 6
Tasty Tim’s
Tasty Tim’s is a specialty taco restaurant. The following tasks are required for the successful assembly of a Tasty taco (times are in seconds per taco):
Chop and trim meat – 30
Chop vegetables – 20
Grill meat – 240
Grill vegetables – 180
Prepare toppings
- Lettuce - 10
- Tomato - 15
- Guacamole - 40
Assemble taco
- Add meat - 5
- Add vegetables - 5
- Add cheese - 5
- Add toppings - 10
Wrap taco - 20
During the lunch hour, Tasty Tim’s encounters demand for 120 tacos.
During off-peak afternoon hours, demand at Tasty Tim’s drops to 40 tacos each hour. How many employees should Tim schedule to work during the afternoon? Again, ignore any effects of idle time or inefficiency due to poor line balancing.
Question 5
Tasty Tim’s
Tasty Tim’s is a specialty taco restaurant. The following tasks are required for the successful assembly of a Tasty taco (times are in seconds per taco):
Chop and trim meat – 30
Chop vegetables – 20
Grill meat – 240
Grill vegetables – 180
Prepare toppings
- Lettuce - 10
- Tomato - 15
- Guacamole - 40
Assemble taco
- Add meat - 5
- Add vegetables - 5
- Add cheese - 5
- Add toppings - 10
Wrap taco - 20
During the lunch hour, Tasty Tim’s encounters demand for 120 tacos.
In an ideal world, how many workers should Tim hire to make tacos?
Chapter 10 Solutions
Principles of Operations Management: Sustainability and Supply Chain Management (10th Edition)
Ch. 10 - Prob. 1EDCh. 10 - Prob. 1DQCh. 10 - Prob. 2DQCh. 10 - Prob. 3DQCh. 10 - Prob. 4DQCh. 10 - Prob. 5DQCh. 10 - Prob. 6DQCh. 10 - Prob. 7DQCh. 10 - Prob. 8DQCh. 10 - Prob. 9DQ
Ch. 10 - Prob. 10DQCh. 10 - Prob. 11DQCh. 10 - Prob. 12DQCh. 10 - Prob. 13DQCh. 10 - Prob. 14DQCh. 10 - Prob. 1PCh. 10 - Prob. 2PCh. 10 - Prob. 3PCh. 10 - Prob. 4PCh. 10 - Prob. 5PCh. 10 - Prob. 6PCh. 10 - Prob. 7PCh. 10 - Prob. 8PCh. 10 - Prob. 9PCh. 10 - Prob. 10PCh. 10 - Prob. 11PCh. 10 - Prob. 12PCh. 10 - Prob. 13PCh. 10 - Prob. 14PCh. 10 - Prob. 15PCh. 10 - Prob. 16PCh. 10 - Prob. 17PCh. 10 - Prob. 18PCh. 10 - Prob. 19PCh. 10 - Prob. 20PCh. 10 - Prob. 21PCh. 10 - Prob. 22PCh. 10 - Virginia College promotes a wide variety of...Ch. 10 - Prob. 24PCh. 10 - Prob. 25PCh. 10 - Prob. 26PCh. 10 - Prob. 27PCh. 10 - Prob. 28PCh. 10 - Prob. 29PCh. 10 - Prob. 30PCh. 10 - Prob. 31PCh. 10 - Prob. 32PCh. 10 - Prob. 33PCh. 10 - Prob. 34PCh. 10 - Prob. 35PCh. 10 - Prob. 36PCh. 10 - Prob. 37PCh. 10 - Prob. 38PCh. 10 - Prob. 1CSCh. 10 - Prob. 2CSCh. 10 - Prob. 3CSCh. 10 - Prob. 4CSCh. 10 - Prob. 1.1VCCh. 10 - Prob. 1.2VCCh. 10 - Prob. 1.3VCCh. 10 - Prob. 2.1VCCh. 10 - Prob. 2.2VCCh. 10 - Prob. 2.3VCCh. 10 - Prob. 2.4VC
Knowledge Booster
Similar questions
- Question 2 Mr Letsomane is the supervisor in fast growing company that manufactures and assembles office furniture. Since the inception of the company, they have been using job specialisation to accomplish their tasks. However, of late there have been delays in finished goods, morale is low and returns have increased. Explain to Mr Letsomane the advantages and disadvantages of job specialisation and further discuss with him the three methods of job design that can help reverse the problems caused by job specialisation.arrow_forwardQ15. How the performance on a task is evaluated?arrow_forwardQUESTION 15 are a type of standing plan that are designed to give explicit instructions on how to complete a recurring task. A. Guidelines B. Rules C. Policies D. Proceduresarrow_forward
- QUESTION 5a. A Chef bakes and decorates cakes in a two-stage process. The cakes are baked and once cooledthey are then decorated based on the clients’ requirements. The Chef received seven orders forfully decorated cakes and has documented the orders with respective processing times for bakingand decorating, as shown in Table 7 that follows:.Table 7. Cake Job Orders received by the Chef with the respective processing times for Baking andDecoratingCake Job Order Baking Processing Time Decorating Processing TimeA 2 1B 8 5C 4 6D 9 7E 7 8F 9 6G 3 5 (ii) Illustrate the flow (throughput) times to complete the baking and decorating on atimeline chart.arrow_forwardQUESTION 5a. A Chef bakes and decorates cakes in a two-stage process. The cakes are baked and once cooledthey are then decorated based on the clients’ requirements. The Chef received seven orders forfully decorated cakes and has documented the orders with respective processing times for bakingand decorating, as shown in Table 7 that follows:.Table 7. Cake Job Orders received by the Chef with the respective processing times for Baking andDecoratingCake Job Order Baking Processing Time Decorating Processing TimeA 2 1B 8 5C 4 6D 9 7E 7 8F 9 6G 3 5 (i) Using Johnson’s Rule, determine the optimum sequence for processing the cake joborders through the baking and decorating stages.arrow_forwardQuestion-2 What kind of issues can arise in consultant-client relationships in OD? What should be done to manage these relations appropriately? (Maximum 200 words)arrow_forward
- Question 5The management of CDC Construction Pioneers have decided to build 900 new apartments in the Kasoa area due to the influx of immigrant workers into the country. Two Architectural Companies have provided building plans and technical schematics for the project. Management are happy with the proposals of both Standard apartment and Deluxe apartment. After investigating the steps involved in construction, management determined that each apartment complex built will require some resources. Management analysed each of the bids and concluded that if the plans of Standard apartment are built, it requires 0.7 days in foundation works, 0.5 days in the masonry, 1 day in finishing, and 0.1 days in painting works. Deluxe apartment will require 1 day in foundation works, 0.83 days in the masonry, 0.67 days in finishing, and 0.25 days in the painting works. Management estimate that, 630 days for foundation works, 600 days for masonry, 708 days for finishing and 135 days for 11painting works…arrow_forward1) Job design specifies the tasks that constitute a job for an individual or a group. Briefly describe the five components of job design?arrow_forwardQUESTION 1: Differentiate between a project and a program and highlight two major characteristics of a PROJECTarrow_forward
- What are the differences among job enrichment, job enlargement, job rotation, job specialization, and employee empowerment?arrow_forwardQuestion: You are working as a Project Manager for a leading IT Service Provider company. During the deployment of one of the optical fiber cabling project, your team required a testing equipment called fluke. This machine is used for testing the termination of copper and optical fiber nodes. The machine cost approximately PKR 450,000/- plus you need to a hire a technician to handle the equipment. Technician would be hired for 3 months at a salary of Rs. 30,000/- per month (For 2 months). The total number of nodes to be tested are 345. Another solution is to outsource this project to a subcontractor which will charge Rs. 1,500/- per network node. As a project manager, what will be your decision (based on your experience), whether to buy the device or go for outsourcing this job to the subcontractor? Give justification to support your decision.arrow_forwardQuestion 2: Organising Write a short essay (250 words) explaining how job specialisation could be used to design a McDonald’s worker’s job. Using examples explain two disadvantages of such a job design.arrow_forward
arrow_back_ios
SEE MORE QUESTIONS
arrow_forward_ios
Recommended textbooks for you
- Practical Management ScienceOperations ManagementISBN:9781337406659Author:WINSTON, Wayne L.Publisher:Cengage,Operations ManagementOperations ManagementISBN:9781259667473Author:William J StevensonPublisher:McGraw-Hill EducationOperations and Supply Chain Management (Mcgraw-hi...Operations ManagementISBN:9781259666100Author:F. Robert Jacobs, Richard B ChasePublisher:McGraw-Hill Education
- Purchasing and Supply Chain ManagementOperations ManagementISBN:9781285869681Author:Robert M. Monczka, Robert B. Handfield, Larry C. Giunipero, James L. PattersonPublisher:Cengage LearningProduction and Operations Analysis, Seventh Editi...Operations ManagementISBN:9781478623069Author:Steven Nahmias, Tava Lennon OlsenPublisher:Waveland Press, Inc.
Practical Management Science
Operations Management
ISBN:9781337406659
Author:WINSTON, Wayne L.
Publisher:Cengage,
Operations Management
Operations Management
ISBN:9781259667473
Author:William J Stevenson
Publisher:McGraw-Hill Education
Operations and Supply Chain Management (Mcgraw-hi...
Operations Management
ISBN:9781259666100
Author:F. Robert Jacobs, Richard B Chase
Publisher:McGraw-Hill Education
Purchasing and Supply Chain Management
Operations Management
ISBN:9781285869681
Author:Robert M. Monczka, Robert B. Handfield, Larry C. Giunipero, James L. Patterson
Publisher:Cengage Learning
Production and Operations Analysis, Seventh Editi...
Operations Management
ISBN:9781478623069
Author:Steven Nahmias, Tava Lennon Olsen
Publisher:Waveland Press, Inc.