Question
Chapter 10, Problem 37P
Summary Introduction
To determine: The delay and
Introduction: Sample size refers to the number of observations that are necessary to determine the cycle time. The major goal of sample size is to determine inferences about the population from the observations.
Expert Solution & Answer
Want to see the full answer?
Check out a sample textbook solutionStudents have asked these similar questions
Supervisor Tom Choi at Tempe Equipment Companyis concerned that material is not arriving as promptly as needed atwork cells. A new kanban system has been insta lled, but there seemsto be some delay in getting the material moved to the work cells sothat the job can begin promptly. Choi is interested in determininghow much delay there is on the part of his highly paid machinists.Ideally, the delay would be close to zero. He has asked his assistantto determine the delay factor among his 10 work cells. The assistantcollects the data on a random basis over the next 2 weeks anddetermines that of the 1,200 observations, 105 were made while theoperators were waiting for materials. Use a 95% confidence leveland a ±3% acceptable error. What report does he give to Choi?
upervisor Tom Choi at Tempe EquipmentCompany is concerned that material is not arriving aspromptly as needed at work cells. A new kanban system hasbeen installed, but there seems to be some delay in getting thematerial moved to the work cells so that the job can beginpromptly. Choi is interested in determining how much delaythere is on the part of his highly paid machinists. Ideally, thedelay would be close to zero. He has asked his assistant todetermine the delay factor among his 10 work cells. The assistant collects the data on a random basis over the next 2 weeksand determines that of the 1,200 observations, 105 were madewhile the operators were waiting for materials. Use a 95% confidence level and a {3% acceptable error. What report does hegive to Choi?
Recently, some operations management experts have begun insisting that simply maximizing process velocity, which actually means minimizing the time it takes to process something through the system, is the single most important measure for improving a process. Can you think of a situation in which this might not be true?
Chapter 10 Solutions
Principles of Operations Management: Sustainability and Supply Chain Management, Student Value Edition (10th Edition)
Ch. 10 - Prob. 1EDCh. 10 - Prob. 1DQCh. 10 - Prob. 2DQCh. 10 - Prob. 3DQCh. 10 - Prob. 4DQCh. 10 - Prob. 5DQCh. 10 - Prob. 6DQCh. 10 - Prob. 7DQCh. 10 - Prob. 8DQCh. 10 - Prob. 9DQ
Ch. 10 - Prob. 10DQCh. 10 - Prob. 11DQCh. 10 - Prob. 12DQCh. 10 - Prob. 13DQCh. 10 - Prob. 14DQCh. 10 - Prob. 1PCh. 10 - Prob. 2PCh. 10 - Prob. 3PCh. 10 - Prob. 4PCh. 10 - Prob. 5PCh. 10 - Prob. 6PCh. 10 - Prob. 7PCh. 10 - Prob. 8PCh. 10 - Prob. 9PCh. 10 - Prob. 10PCh. 10 - Prob. 11PCh. 10 - Prob. 12PCh. 10 - Prob. 13PCh. 10 - Prob. 14PCh. 10 - Prob. 15PCh. 10 - Prob. 16PCh. 10 - Prob. 17PCh. 10 - Prob. 18PCh. 10 - Prob. 19PCh. 10 - Prob. 20PCh. 10 - Prob. 21PCh. 10 - Prob. 22PCh. 10 - Virginia College promotes a wide variety of...Ch. 10 - Prob. 24PCh. 10 - Prob. 25PCh. 10 - Prob. 26PCh. 10 - Prob. 27PCh. 10 - Prob. 28PCh. 10 - Prob. 29PCh. 10 - Prob. 30PCh. 10 - Prob. 31PCh. 10 - Prob. 32PCh. 10 - Prob. 33PCh. 10 - Prob. 34PCh. 10 - Prob. 35PCh. 10 - Prob. 36PCh. 10 - Prob. 37PCh. 10 - Prob. 38PCh. 10 - Prob. 1CSCh. 10 - Prob. 2CSCh. 10 - Prob. 3CSCh. 10 - Prob. 4CSCh. 10 - Prob. 1.1VCCh. 10 - Prob. 1.2VCCh. 10 - Prob. 1.3VCCh. 10 - Prob. 2.1VCCh. 10 - Prob. 2.2VCCh. 10 - Prob. 2.3VCCh. 10 - Prob. 2.4VC
Knowledge Booster
Learn more about
Need a deep-dive on the concept behind this application? Look no further. Learn more about this topic, operations-management and related others by exploring similar questions and additional content below.Similar questions
- Mr. Aris Benn manages an assembly line that produces a piece of equipment that is used to clean floors. The process to produce this piece of equipment consists of 10 steps. 1. set up a numerical example of the line balancing problem at hand.arrow_forward3-Step Process with Rework Consider the following three-step assembly operation with quality problems. All resources are staffed by one employee. The first resource has a processing time of 7 minutes per unit. The second resource has a processing time of 6 minutes per unit. The third resource has a processing time of 5 minutes per unit. With a 40% probability, the flow unit coming out of the third resource has to be reworked. In that case, the operations at the second and third resources are repeated. You can assume that (a) rework always succeeds (i.e. a unit going through the rework loop will always work after the third resource),and (b) the processing times for units in rework are the same as for regular units. A) For every unit of demand, how many units have to flow through the second step in the process? B) Where in the process is the bottleneck? Step 1, 2 or 3?arrow_forwardA serial process has 5 steps – A (4), B(5), C(2), D(6), and E(3) – that have to be performed in this order. The numbers in parentheses are the times (in minutes) needed to process a unit. For each unit produced by this process, the process has a total idle time of: Group of answer choices 1 min 10 mins 6 mins 3 minsarrow_forward
- Cubway, the sandwich shop, is run by Jim, Tim and Kim. When a customer arrives, Jim spends 5 minutes taking order from the customer. After this, Tim prepares bread and Kim prepares filling for the order. These activities are performed in parallel, and take 6 and 12 minutes respectively. Jim then assembles the bread and filling, which takes 4 minutes of his time. Finally, Tim spends 1 minutes in delivering the order and taking payment. What is maximum number of sandwiches Cubway can make per hour? (In other words, what is the capacity of the process in sandwiches per hour?)arrow_forwardConsider a production line, such as the one at Chipotle Mexican Grill for burritos. While one server may manage assembly during slow periods of the day, having multiple servers would be prudent during really busy periods. Justify why neither approach would work 100% of the time and the benefit of adjusting the server count to the rate of customer arrivals.arrow_forwardSmartphones are made on a 40-step assembly process. All 40 steps are connectedthrough a conveyor belt and all of the 40 steps must work at the same rate even if someof them have more capacity than others. Is this process a machine-paced process or aworker-paced process?a. Machine-pacedb. Worker-pacedarrow_forward
- Balancing a process with a fixed sequence of activities will achieve a higher average labor utilization than balancing a process with no fixed sequence of activities. True or False?arrow_forwardConsider the following two production processes making an electronic component for a navigation system. Both processes consist of 20 stations and operate at a cycletime of 1 minute/unit. Their most error-prone operation is step 9:• Process 1 has a final inspection at the end of the process and has about 300 units of inventory between step 9 and the inspection.• Process 2 has each worker check the work of the previous steps and about 50 units ofinventory between step 9 and the end of the process, roughly equally distributed across theremainder of the process.What would be the information turnaround time for a defect made at station 9?arrow_forward. A small, privately owned Asian company is producing a private-label soft drink calledYoggo. A bottling line puts the soft drinks into plastic bottles and then packagesthe bottles into boxes holding 10 bottles each. The bottling line is comprised of thefollowing four steps: (1) the bottling machine takes 1 second to fill a bottle, (2) the lidmachine takes 3 seconds to cover the bottle with a lid, (3) a labeling machine takes3 seconds per bottle, and (4) the packaging machine takes 4 seconds to place a bottleinto a box. When a box has been filled with 10 bottles, a worker tending the packagingmachine removes the filled box and replaces it with an empty box. Assume that thetime for the worker to remove a filled box and replace it with an empty box is negligibleand hence does not affect the capacity of the line. Problem data are summarized in thefollowing table. a. Draw a process flow diagram of this process. b. What is the capacity (bottles/hour) at the resource “Apply a lid”? c. What…arrow_forward
- An average of 1200 parts arrive to the EP chamber during an 8-hour workday. Each part goes through two stages of processing. At each stage, a single product is processed at a time, and processing takes an average of 15 seconds at the first station and 12 seconds at the second station. Inter-arrival times and service times are exponentially distributed. At the end of the second step, the product goes through a quality check. 5% of the parts fail the quality check and are sent back to the second stage of service. Parts exit the system only after they pass the quality check. Ignoring the time required to perform the quality check or in moving the part through the facility, what is the average cycle time for parts?arrow_forwardDrawing blood was Kara’s favorite skill she learned in clinical medical assistant school. She is pleased that Greenland Family Care Clinic draws lab work onsite rather than sending patients to an outpatient laboratory for phlebotomy procedures. Lindsay reviewed all of the procedures with her before she left on vacation, knowing that Kara would have the opportunity to perform phlebotomy on several patients. Dr. Dean has ordered lab tests on Mr. Jose M. Garcia, and Kara will need to draw his blood. This is her first “real” patient since completing her externship, and she is a little nervous. Kara looks at the lab requisition form and learns Dr. Dean has ordered a CBC with Diff, Serum Fasting Glucose, and Basic Metabolic Panel. Kara gathers the supplies and enters Mr. Garcia’s exam room with a smile. Do not forget to ask yourself questions like these: What should Kara do next? What is the appropriate color of tube(s) Kara needs to draw? Will Kara need to change tubes during this…arrow_forward. Consider the following four-step assembly operation with quality problems. Allresources are staffed by one employee.• The first resource has a processing time of 5 minutes per unit.• The second resource has a processing time of 6 minutes per unit.• The third resource has a processing time of 3 minutes per unit. With a 30 percent probability, the flow unit coming out of the third resource has to be reworked. In that case,the operations at the first, second, and third resources are repeated. You can assumethat (a) rework always succeeds (i.e., a unit going through the rework loop will alwayswork after the third resource) and (b) the processing times for units in rework are thesame as for regular units.• The fourth resource has a processing time of 4 minutes per unit.a. Where in the process is the bottleneck?b. What is the capacity of the process?arrow_forward
arrow_back_ios
SEE MORE QUESTIONS
arrow_forward_ios
Recommended textbooks for you
- Practical Management ScienceOperations ManagementISBN:9781337406659Author:WINSTON, Wayne L.Publisher:Cengage,Operations ManagementOperations ManagementISBN:9781259667473Author:William J StevensonPublisher:McGraw-Hill EducationOperations and Supply Chain Management (Mcgraw-hi...Operations ManagementISBN:9781259666100Author:F. Robert Jacobs, Richard B ChasePublisher:McGraw-Hill Education
- Purchasing and Supply Chain ManagementOperations ManagementISBN:9781285869681Author:Robert M. Monczka, Robert B. Handfield, Larry C. Giunipero, James L. PattersonPublisher:Cengage LearningProduction and Operations Analysis, Seventh Editi...Operations ManagementISBN:9781478623069Author:Steven Nahmias, Tava Lennon OlsenPublisher:Waveland Press, Inc.
Practical Management Science
Operations Management
ISBN:9781337406659
Author:WINSTON, Wayne L.
Publisher:Cengage,
Operations Management
Operations Management
ISBN:9781259667473
Author:William J Stevenson
Publisher:McGraw-Hill Education
Operations and Supply Chain Management (Mcgraw-hi...
Operations Management
ISBN:9781259666100
Author:F. Robert Jacobs, Richard B Chase
Publisher:McGraw-Hill Education
Purchasing and Supply Chain Management
Operations Management
ISBN:9781285869681
Author:Robert M. Monczka, Robert B. Handfield, Larry C. Giunipero, James L. Patterson
Publisher:Cengage Learning
Production and Operations Analysis, Seventh Editi...
Operations Management
ISBN:9781478623069
Author:Steven Nahmias, Tava Lennon Olsen
Publisher:Waveland Press, Inc.