Chapter 10, Problem 38P

a)

Summary Introduction

To determine: Theminutes per day of actual room cleaning can be done by each housekeeper

Introduction: Work sampling is the technique, which helps to estimate the percentage of time that was spent by the worker on different kind of tasks assigned to him. Random observations help to record the performance of the worker on various activities.

b)

Summary Introduction

To determine: Minutes of room cleaning that the hotel requires for the present day

Introduction: Work sampling is the technique, which helps to estimate the percentage of time that was spent by the worker on different kind of tasks assigned to him. Random observations help to record the performance of the worker on various activities.

c)

Summary Introduction

To determine: Number of housekeepers required to clean the hotel for the present day

Introduction: Work sampling is the technique, which helps to estimate the percentage of time that was spent by the worker on different kind of tasks assigned to him. Random observations help to record the performance of the worker on various activities.

d)

Summary Introduction

To determine: Number of housekeepers required to clean the hotel if all the guests check out.

Introduction: Work sampling is the technique, which helps to estimate the percentage of time that was spent by the worker on different kind of tasks assigned to him. Random observations help to record the performance of the worker on various activities.

Blurred answer
Students have asked these similar questions
The higher levels of the work breakdown structure (WBS) represent increasing amounts of detail while the lower levels represent broad categories of activities.   Question 18 options:   True   False
Question 12 Which of the following statements regarding PERT times is true? Pessimistic time estimate is an estimate of the minimum time an activity will require Optimistic time estimate is an estimate of the minimum time an activity will require Most likely time estimate is an estimate of the maximum time an activity will require Optimistic time estimate is an estimate of the maximum time an activity will require
Work measurement as a source of job standards includes time study and work sampling, but not the use of historical data.   Question 17 options:   True   False
Knowledge Booster
Background pattern image
Similar questions
SEE MORE QUESTIONS
Recommended textbooks for you
Text book image
Practical Management Science
Operations Management
ISBN:9781337406659
Author:WINSTON, Wayne L.
Publisher:Cengage,
Text book image
Operations Management
Operations Management
ISBN:9781259667473
Author:William J Stevenson
Publisher:McGraw-Hill Education
Text book image
Operations and Supply Chain Management (Mcgraw-hi...
Operations Management
ISBN:9781259666100
Author:F. Robert Jacobs, Richard B Chase
Publisher:McGraw-Hill Education
Text book image
Business in Action
Operations Management
ISBN:9780135198100
Author:BOVEE
Publisher:PEARSON CO
Text book image
Purchasing and Supply Chain Management
Operations Management
ISBN:9781285869681
Author:Robert M. Monczka, Robert B. Handfield, Larry C. Giunipero, James L. Patterson
Publisher:Cengage Learning
Text book image
Production and Operations Analysis, Seventh Editi...
Operations Management
ISBN:9781478623069
Author:Steven Nahmias, Tava Lennon Olsen
Publisher:Waveland Press, Inc.