Draw an activity chart for a machine operator with the following operation. The relevant times are as follows:
Prepare mill for loading (cleaning, oiling, and so on) | .50 min |
Load mill | 1.75 min |
Mill operating (cutting material) | 2.25 min |
Unload mill | .75 min |
Expert Solution & Answer
Want to see the full answer?
Check out a sample textbook solutionStudents have asked these similar questions
What is the bottleneck of the process is which worker ?
A work sampling study was conducted to establish the standard time for an operation The
observation of the study is givein below:
• Total number of observations 220 .
Manual (Hand controiled work) = 34
%3D
Machine controlled work = 126
Machine idle time = 60
Average performance rating 80%
No. of parts produced during the study 36
Allowance for personal needs and fatigue 10%
Study conducted for 3 days
Availsble working hours / day 8 hrs
Calculáte the Standard time for this operation?
%3D
7- Assume that as a method engineer, we suspect that a worker walks more than normal during a production process.
Hence, we are interested in the detailed movements of the worker to test our doubt. Then which tool would exactly
help us?
a)
Cause and Effect Chart
2056
b)
Flow Diagram
c)
Flow Process Chart
d)
Process Maps
e)
Activity Chart for One Worker
Chapter 10 Solutions
Operations Management
Ch. 10 - Prob. 1DQCh. 10 - Prob. 2DQCh. 10 - Prob. 3DQCh. 10 - Prob. 4DQCh. 10 - Prob. 5DQCh. 10 - Prob. 6DQCh. 10 - Prob. 7DQCh. 10 - Prob. 8DQCh. 10 - Prob. 9DQCh. 10 - Prob. 10DQ
Ch. 10 - Prob. 11DQCh. 10 - Prob. 12DQCh. 10 - Prob. 13DQCh. 10 - Prob. 14DQCh. 10 - Prob. 2PCh. 10 - Draw an activity chart for a machine operator with...Ch. 10 - Prob. 4PCh. 10 - Prob. 5PCh. 10 - Prob. 6PCh. 10 - Prob. 1PCh. 10 - Prob. 7PCh. 10 - Prob. 8PCh. 10 - Prob. 9PCh. 10 - Prob. 10PCh. 10 - Prob. 11PCh. 10 - Prob. 12PCh. 10 - Prob. 13PCh. 10 - Prob. 14PCh. 10 - Prob. 15PCh. 10 - Prob. 16PCh. 10 - Prob. 17PCh. 10 - Prob. 18PCh. 10 - Prob. 19PCh. 10 - Prob. 20PCh. 10 - Prob. 21PCh. 10 - Prob. 22PCh. 10 - Prob. 23PCh. 10 - Prob. 24PCh. 10 - Prob. 25PCh. 10 - Prob. 26PCh. 10 - Prob. 27PCh. 10 - Prob. 28PCh. 10 - Prob. 29PCh. 10 - Prob. 30PCh. 10 - Prob. 31PCh. 10 - Prob. 32PCh. 10 - Prob. 34PCh. 10 - Prob. 35PCh. 10 - Prob. 36PCh. 10 - Prob. 37PCh. 10 - Prob. 33PCh. 10 - Prob. 39PCh. 10 - Prob. 40PCh. 10 - Prob. 41PCh. 10 - Prob. 42PCh. 10 - Prob. 44PCh. 10 - Prob. 1CSCh. 10 - Prob. 2CSCh. 10 - Prob. 3CSCh. 10 - Prob. 4CSCh. 10 - Prob. 2.1VCCh. 10 - Prob. 2.2VCCh. 10 - Prob. 2.3VCCh. 10 - Prob. 2.4VCCh. 10 - Prob. 1.1VCCh. 10 - Prob. 1.2VCCh. 10 - Prob. 1.3VC
Knowledge Booster
Learn more about
Need a deep-dive on the concept behind this application? Look no further. Learn more about this topic, operations-management and related others by exploring similar questions and additional content below.Similar questions
- 1. A job has 48 seconds tact time generates an hourly output of?2. An MTM study indicated that an operation accumulates a total of 4,725 TMU. Find the standardtime of the operation, in seconds, if it given 12% allowance added to normal time.3. The time study of a work operation yielded an average observed cycle time of 4.0 minutes. IEAnalyst rated the observed worker at 85%. RNav Firm allowance factor is 13%. Compute for thestandard time.4. Mancio Manufacturing Co. has asked you, as their IE, to check a labor standard prepared by arecently resigned analyst. Determine the sample size you need considering your accuracy is to bewithin 5%, standard deviation of the sample is 1.0 and the mean is 3.0.arrow_forward1. A job has 48 seconds tact time generates an hourly output of?2. An MTM study indicated that an operation accumulates a total of 4,725 TMU. Find the standardtime of the operation, in seconds, if it given 12% allowance added to normal time.3. The time study of a work operation yielded an average observed cycle time of 4.0 minutes. IEAnalyst rated the observed worker at 85%. RNav Firm allowance factor is 13%. Compute for thestandard time.arrow_forwardRock View Restaurant is a new fast-food restaurant chain. The Operations Manager has dividedits normal drive-through service process into the following tasks: Tasks Description Task Time (In Seconds) Predecessors A Take Order 25 None B Receive payment 20 A C Gather drinks 35 A D Gather Food 32 A E Put food etc. In bag 25 C,D F Give food to Customer 10 B,E Currently, Rock View Restaurant has a single window with one person who takes the order,gather the food, collects the money and gives the food to the customer. This takes an average of147 seconds per customer so only 25.5 cars can be served. Rock View Restaurant wants toincrease its drive-through capacity to 60 cars per hour by forming a multi-window line.1. Calculate the efficiency of the newly design process.arrow_forward
- Rock View Restaurant is a new fast-food restaurant chain. The Operations Manager has dividedits normal drive-through service process into the following tasks: Tasks Description Task Time (In Seconds) Predecessors A Take Order 25 None B Receive payment 20 A C Gather drinks 35 A D Gather Food 32 A E Put food etc. In bag 25 C,D F Give food to Customer 10 B,E Currently, Rock View Restaurant has a single window with one person who takes the order,gather the food, collects the money and gives the food to the customer. This takes an average of147 seconds per customer so only 25.5 cars can be served. Rock View Restaurant wants toincrease its drive-through capacity to 60 cars per hour by forming a multi-window line.i. Using the LOT heuristic, assign the tasks to the windows to produce the desiredservice rate making sure that the precedence relationship is maintained.arrow_forwardRock View Restaurant is a new fast-food restaurant chain. The Operations Manager has dividedits normal drive-through service process into the following tasks: Tasks Description Task Time (In Seconds) Predecessors A Take Order 25 None B Receive payment 20 A C Gather drinks 35 A D Gather Food 32 A E Put food etc. In bag 25 C,D F Give food to Customer 10 B,E Currently, Rock View Restaurant has a single window with one person who takes the order,gather the food, collects the money and gives the food to the customer. This takes an average of147 seconds per customer so only 25.5 cars can be served. Rock View Restaurant wants toincrease its drive-through capacity to 60 cars per hour by forming a multi-window line.1. Draw the precedence diagram to represent the process at Rock view restaurant.arrow_forwardRock View Restaurant is a new fast-food restaurant chain. The Operations Manager has dividedits normal drive-through service process into the following tasks: Tasks Description Task Time (In Seconds) Predecessors A Take Order 25 None B Receive payment 20 A C Gather drinks 35 A D Gather Food 32 A E Put food etc. In bag 25 C,D F Give food to Customer 10 B,E Currently, Rock View Restaurant has a single window with one person who takes the order,gather the food, collects the money and gives the food to the customer. This takes an average of147 seconds per customer so only 25.5 cars can be served. Rock View Restaurant wants toincrease its drive-through capacity to 60 cars per hour by forming a multi-window line.1. Calculate the cycle time in seconds.arrow_forward
- Rock View Restaurant is a new fast food restaurant chain. The Operations Manager has dividedits normal drive-through service process into the following tasks:Tasks Description Task Time(InSeconds)PredecessorsA Take order 25 NoneB Receive payment 20 AC Gather drinks 35 AD Gather food 32 AE Put food etc. in bag 25 C,DF Give food to customer 10 B,E Currently, Rock View Restaurant has a single window with one person who takes the order, gather the food, collects the money and gives the food to the customer. This takes an average of 147 seconds per customer so only 25.5 cars can be served.…arrow_forwardRock View Restaurant is a new fast food restaurant chain. The Operations Manager has dividedits normal drive-through service process into the following tasks:Tasks Description Task Time(InSeconds)PredecessorsA Take order 25 NoneB Receive payment 20 AC Gather drinks 35 AD Gather food 32 AE Put food etc. in bag 25 C,DF Give food to customer 10 B,E Currently, Rock View Restaurant has a single window with one person who takes the order, gather the food, collects the money and gives the food to the customer. This takes an average of 147 seconds per customer so only 25.5 cars can be served.…arrow_forwardThe Questions below pertain to PROCESS ANALYSIS Process Metrics (Throughput Time, Cycle Time, Flow Rate, Inventory, Little's Law, Processing Time, Activity Capacity, Bottleneck, Capacity of Activity, Capacity Utilization) Question 1 The process for handling insurance claims at a branch of the Green Insurance Company has an average flow rate of 1 claim per minute. Branch manager Shauna Green has measured the average time spent by a claim in this process from start to end to be 1.5 hours. How many claims are in the process on average? Show your work including any formula you use. Round your answer to the nearest whole number. Question 2 In Children’s Hospital in Seattle, there are, on average, 84 births per week. Mothers stay, on average, 3 days before they leave the hospital. On average, how many mothers are staying in Children’s Hospital? Show your work including any formula you use. Round your answer to the nearest whole number. The information in this paragraph applies to this…arrow_forward
- Rockness Recycling refurbishes rundown business students. The process uses a moving belt, which carries each student through the five steps of the process in sequence. The five steps are as follows: STEP DESCRIPTION TIME REQUIREDPER STUDENT 1 Unpack and place on belt 1.2 minutes 2 Strip off bad habits 1.0 minutes 3 Scrub and clean mind 1.5 minutes 4 Insert modern methods 0.8 minute 5 Polish and pack 1.0 minutes One faculty member is assigned to each of these steps. Faculty members work a 40-hour week and rotate jobs each week. Mr. Rockness has been working on a contract from General Eclectic, which requires delivery of 2,000 refurbished students per week. A representative of the human resources department has just called complaining that the company hasn’t been receiving the agreed-upon number of students. A check of finished goods inventory by Mr. Rockness reveals that there is no stock left. a. Calculate the maximum output for each step. b. Which step…arrow_forwardCourse: work study and method engineering Describe Learning curve and its types along with graph?arrow_forwardEddys Pizza is currently redesigning its order-processing and pizza-making procedures for itsoperations which usually start at 5pm and close at 2am. For Eddys to meet customers’ speedydelivery requirement, six elements must be completed as summarised in the table below.WorkElementDescription Precedence Time (Mins)1 Receive customer order - 32 Shape dough 1 23 Prepare toppings 1 34 Assemble Pizza 2, 3 45 Bake pizza 4 46 Select complementary drink - 17 Deliver pizza 5, 6 4i. Draw the precedence diagram for the pizza making process.ii. If the demand for pizza is 90 pieces during the operating time, calculate the desired cycletime iii. Balance the line and calculate its efficiencyarrow_forward
arrow_back_ios
SEE MORE QUESTIONS
arrow_forward_ios
Recommended textbooks for you
- Practical Management ScienceOperations ManagementISBN:9781337406659Author:WINSTON, Wayne L.Publisher:Cengage,Operations ManagementOperations ManagementISBN:9781259667473Author:William J StevensonPublisher:McGraw-Hill EducationOperations and Supply Chain Management (Mcgraw-hi...Operations ManagementISBN:9781259666100Author:F. Robert Jacobs, Richard B ChasePublisher:McGraw-Hill Education
- Purchasing and Supply Chain ManagementOperations ManagementISBN:9781285869681Author:Robert M. Monczka, Robert B. Handfield, Larry C. Giunipero, James L. PattersonPublisher:Cengage LearningProduction and Operations Analysis, Seventh Editi...Operations ManagementISBN:9781478623069Author:Steven Nahmias, Tava Lennon OlsenPublisher:Waveland Press, Inc.
Practical Management Science
Operations Management
ISBN:9781337406659
Author:WINSTON, Wayne L.
Publisher:Cengage,
Operations Management
Operations Management
ISBN:9781259667473
Author:William J Stevenson
Publisher:McGraw-Hill Education
Operations and Supply Chain Management (Mcgraw-hi...
Operations Management
ISBN:9781259666100
Author:F. Robert Jacobs, Richard B Chase
Publisher:McGraw-Hill Education
Purchasing and Supply Chain Management
Operations Management
ISBN:9781285869681
Author:Robert M. Monczka, Robert B. Handfield, Larry C. Giunipero, James L. Patterson
Publisher:Cengage Learning
Production and Operations Analysis, Seventh Editi...
Operations Management
ISBN:9781478623069
Author:Steven Nahmias, Tava Lennon Olsen
Publisher:Waveland Press, Inc.
Inventory Management | Concepts, Examples and Solved Problems; Author: Dr. Bharatendra Rai;https://www.youtube.com/watch?v=2n9NLZTIlz8;License: Standard YouTube License, CC-BY