a)
Summary Introduction
To determine: The standard time for the operation.
Introduction: Time study is the basis that helps set the standard time; it would time a sample of the performance of the worker.
b)
Summary Introduction
To determine: The number of
Introduction: Thesample size is required to determine the number of observations that are necessary to find the true cycle time.
Expert Solution & Answer
Want to see the full answer?
Check out a sample textbook solutionStudents have asked these similar questions
Installing mufflers at the O'Sullivan Garage in Golden, Colorado, involves five work elements. Jill O'Sull ivanhas timed workers performing these tasks seven times, with the results shown in the following table: By agreement with her workers, Jill allows a 10% fatigue factor and a 10% personal-time factor, but no time for delay. To compute standard time for the work operatio n, Jill excludes all observations that a ppear to be unusual or nonrecurring. She does not want an error of mo re than ±5%.a) What is the standard time for the task?b) How many observations are needed to assu re a 95% confidence level?
Installing mufflers at the Stanley Garage in Golden, Colorado, involves five work elements. Linda Stanley has timed workers performing these tasks seven times, with the results shown in the following table.
Job elements
OBSERVATIONS (MINUTES)
Performance rating (%)
1
2
3
4
5
6
7
1
Select correct mufflers
4
5
4
6
4
15
4
100
2
Remove muffler
6
8
7
6
7
6
7
90
3
Weld/install new muffler
15
14
14
12
15
16
13
105
4
Check/inspect work
3
4
24
5
4
3
18
100
5
Complete paperwork
5
6
8
-
7
6
7
130
By agreement with her workers, Stanley allows a 10% fatigue factor and a 10% personal-time factor. To compute standard time for the work operation, Stanley excludes all observations that appear to be unusual or nonrecurring. She does not want an error of more than 5%.
What is the standard time for the task?
How many observations are needed to assure a 95.45%…
The owner of Kat Motel wants to develop a time standard for the task of cleaning a cat cage. In
a preliminary study, she observed one of her workers perform this task six times, with the
following results:
Observation
1
2
3
4
5
6
Time (seconds) 52.7
70
53.3
90.3
80.6
86.7
If the employee performance rating is 1.50, what is the standard time for this task with an
allowance of 20 percent of job time is used?
seconds.
Chapter 10 Solutions
Operations Management
Ch. 10 - Prob. 1DQCh. 10 - Prob. 2DQCh. 10 - Prob. 3DQCh. 10 - Prob. 4DQCh. 10 - Prob. 5DQCh. 10 - Prob. 6DQCh. 10 - Prob. 7DQCh. 10 - Prob. 8DQCh. 10 - Prob. 9DQCh. 10 - Prob. 10DQ
Ch. 10 - Prob. 11DQCh. 10 - Prob. 12DQCh. 10 - Prob. 13DQCh. 10 - Prob. 14DQCh. 10 - Prob. 2PCh. 10 - Draw an activity chart for a machine operator with...Ch. 10 - Prob. 4PCh. 10 - Prob. 5PCh. 10 - Prob. 6PCh. 10 - Prob. 1PCh. 10 - Prob. 7PCh. 10 - Prob. 8PCh. 10 - Prob. 9PCh. 10 - Prob. 10PCh. 10 - Prob. 11PCh. 10 - Prob. 12PCh. 10 - Prob. 13PCh. 10 - Prob. 14PCh. 10 - Prob. 15PCh. 10 - Prob. 16PCh. 10 - Prob. 17PCh. 10 - Prob. 18PCh. 10 - Prob. 19PCh. 10 - Prob. 20PCh. 10 - Prob. 21PCh. 10 - Prob. 22PCh. 10 - Prob. 23PCh. 10 - Prob. 24PCh. 10 - Prob. 25PCh. 10 - Prob. 26PCh. 10 - Prob. 27PCh. 10 - Prob. 28PCh. 10 - Prob. 29PCh. 10 - Prob. 30PCh. 10 - Prob. 31PCh. 10 - Prob. 32PCh. 10 - Prob. 34PCh. 10 - Prob. 35PCh. 10 - Prob. 36PCh. 10 - Prob. 37PCh. 10 - Prob. 33PCh. 10 - Prob. 39PCh. 10 - Prob. 40PCh. 10 - Prob. 41PCh. 10 - Prob. 42PCh. 10 - Prob. 44PCh. 10 - Prob. 1CSCh. 10 - Prob. 2CSCh. 10 - Prob. 3CSCh. 10 - Prob. 4CSCh. 10 - Prob. 2.1VCCh. 10 - Prob. 2.2VCCh. 10 - Prob. 2.3VCCh. 10 - Prob. 2.4VCCh. 10 - Prob. 1.1VCCh. 10 - Prob. 1.2VCCh. 10 - Prob. 1.3VC
Knowledge Booster
Similar questions
- tof instion The owner of Kat Motel wants to develop a time standard for the task of cleaning a cat cage. In a preliminary study, she observed one of her workers perform this task six times, with the following results: Observation 1 2 3 5 6 Time (seconds) 58 51 62 70 4 64 40 What is the standard time for this task if the employee performance rating is 3, and an allowance of (n) percent of job time is used? minutes. Qu 1 Finis Time:arrow_forward5. The manager of Asombrado Bounty Office, Charles Badillo, estimates his employees are idle 25%of the time. With that problem, how many work samples are needed to consider within 3%accuracy and have 95.45% confidence level. 6. At ASP Micro Manufacturing, Inc. workers press semiconductor into predrilled slots on printed-circuit boards. Determine the normal time of the operation in seconds. The elemental motions for normal time used by the company are as follows:• Reach 6 inches for semiconductors 10.5 TMU• Grasp the semiconductors 8.0 TMU• Move semiconductor to printed-circuit board 9.5 TMU• Position semiconductor 20.1 TMU• Press semiconductor into slots 20.3 TMU• Move board aside 15.8 TMU 7. The semiconductor used in Costin Calculator has 5 components with the consistency of 90%, 95%,98%, 90%, and 99%, respectively. How reliable is one product of calculator?arrow_forwardA worker-machine operation was found to involve 3.3 minutes of machine time per cycle in the course of 40 cycles of stopwatch study. The worker's time-averaged 1.9 minutes per cycle, and the worker was given a rating of 120% (machine rating is 100%). Midway through the study, the worker took a 10-minute rest break. Assuming an allowance factor of 12% of work time, determine the standard time for this job. Hints: you should consider both machine time and machine time together. Also, Allowance only applies to the man, not a machine.arrow_forward
- The owner of mid-sized cat motel wants to develop a time standard for the task of cleaning a cat cage. In a preliminary study, she observed one of her workers perform this task six times, with the following results: Observation 1 2 3 4 5 6 Time(Seconds) 99 87 90 81 93 90 What is the standard time for this task if the employee worked at a 50 percent faster pace than average, and an allowance of 10 percent of the workday is used?arrow_forwardClaudine Soosay recorded the following times assemblinga watch. Determine (a) the average time, (b) the normaltime, a nd (c) the standard time taken by her, using a performancerating of95% and a personal allowance of 8%.arrow_forwardDefine ergonomics. Discuss the role of ergonomics in job design.arrow_forward
- TOYS AND JOB DESIGN AT THE HOVEY AND BEARD COMPANY The following is a situation that occurred in the Hovey and Beard Company, as reported by J. V. Clark. This company manufactured a line of wooden toys. One part of the process involved spray painting partially assembled toys, after which the toys were hung on moving hooks that carried them through a drying oven. The operation, staffed entirely by women, was plagued with absenteeism, high turnover, and low morale. Each woman at her paint booth would take a toy from the tray beside her, position it in a fixture, and spray on the color according to the required pattern. She then would release the toy and hang it on the conveyor hook. The rate at which the hooks moved had been calculated so that each woman, once fully trained, would be able to hang a painted toy on each hook before it passed beyond her reach. The women who worked in the paint room were on a group incentive plan that tied their earnings to the…arrow_forwardAfter training, Mary Fernandez, a computer technician,had an average observed time for memory-chip tests of12 seconds. Mary's performance rating is I 00%. The firm has apersonal fatigue and delay allowance of 15%.a) Find the normal time for this process.b) Find the standard time for this process.arrow_forwardHow many work cycles should be timed to estimate the average cycle time to within 2 percent ofthe sample mean with a confidence of 99 percent if a pilot study yielded these times (minutes):5.2, 5.5, 5.8, 5.3, 5.5, and 5.1? The standard deviation is .253 minutes per cycle.arrow_forward
- A Methods and Measurements Analyst needs to develop a time standard for a certain task. The task involves use of a ruler, square, and portable electric saw to mark and cut the "notch" in a rafter (a standard carpentry task of home construction). In a preliminary study, he observed one of his workers performing this task five times. The observations were made in an air-conditioned, well-lit training facility, at ground level, with all tools and equipment clean and readily available. Observation: 1 2 3 4 5 Task time (seconds): 82 74 80 88 76 (a) What is the actual average time for this task? (b) What is the normal time for this task if the employee worked at a 10% faster pace than is typical for adequately trained workers? (c) What is standard time for this task if allowances sum to 12%? (d) If the analyst then thought more carefully about his experiment and decided that the allowances needed to be increased to match the real (outside, not…arrow_forwardThe war between Ukraine and Russia has placed additional demands on the planning and operation departments to increase oil output. To meet deadlines, the departments proposed that the training be deferred until next year, in order to meet increased demands. Should there be an accident, list 1 measure that the training would have mitigated against, in this circumstance, for both departments.arrow_forwardUse the data in the table below to answer questions 1 to 3. Observation 1 2 3 4 5 6 7 8 Time (seconds) 17 18 15 14 13 15 16 2 1. Using the data above, calculate the observed time for the task. 2. If the person observed worked at a pace that is 80% of normal, what should be the normal timefor this task? 3. If the person observed worked at a pace that is 80% of normal, and if the appropriate allowance for this task is 25% of job time, what should be the standard time?arrow_forward
arrow_back_ios
SEE MORE QUESTIONS
arrow_forward_ios
Recommended textbooks for you