Question
Chapter 11, Problem 11.38BE
1.
To determine
To compute: Direct material price and quantity variance and to indicate if it is favorable or unfavorable.
2.
To determine
To indicate: The reasons for variance derived in the previous scenario.
3.
To determine
To compute: The direct labor rate and efficiency variance & to indicate if they are favorable or unfavorable.
4.
To determine
To indicate: Whether the reasons for the labor variance are same as of the material variance.
Expert Solution & Answer
Want to see the full answer?
Check out a sample textbook solutionStudents have asked these similar questions
LearnCo manufactures and sells one product, an abacus for classroom use, with two models, the Basic model and the Deluxe model. The company began operations on January 1, 20Y1, and is planning for 20Y2, its second year of operations, by preparing budgets from its master budget.
The company is trying to decide how many units to manufacture, how much it might spend on direct materials and direct labor, and what their factory overhead expenses might be. In addition, the company is interested in budgeting for selling and administrative costs, and in creating a budgeted income statement showing a prediction of net income for 20Y2.
You have been asked to assist the controller of LearnCo in preparing the 20Y2 budgets.
The sales budget often uses the prior year’s sales as a starting point, and then sales quantities are revised for various factors such as planned advertising and promotion, projected pricing changes, and expected industry and general economic conditions. LearnCo has…
MANAGEMENT ACCOUNTING & CONTROL
STANDARD COSTS AND VARIANCE ANALYSIS
LEARNING ACTIVITY 1
Torres Company has established standard costs for the cabinet department, in which one size of MX cabinet is made. The standard costs of producing one of these MX cabinets are shown below:
Standard Cost Card – MX Cabinet
Direct Material: Lumber 50 board ft at P 4
200
Direct Labor: 8 hours at P 10
80
Overhead Costs: Variable – 8 hrs at P5
40
Fixed – 8 hrs at P3
24
Total Standard Unit Cost
344
During June 2018, 500 of these cabinets were produced. The cost of operations during the month are shown below. There is no work in process at the beginning and end of the month.
Direct material purchased: 30,000 bf at P4.10
123,000
Direct materials used: 24,000 board ft
Direct labor: 4,200 hrs at P9.50
39,900
Overhead Costs : Variable Costs
22,000
Fixed Costs
11,000…
Esteban Products produces instructional aids, including white boards, which use colored markers instead of chalk. These are particularly popular for conference rooms in educational institutions and executive offices of large corporations. The standard cost of materials for this product is 10 pounds at $8.50 per pound.
During the first month of the year, 3,600 boards were produced. Information concerning actual costs and usage of materials follows:
Materials purchased
35,600 lbs. @ $8.60
Materials used
35,100 lbs.
Required:
1.
Compute the materials price and usage variances.
2.
Prepare journal entries on Jan. 31 for all activity relating to materials.
Chapter 11 Solutions
Managerial Accounting, Student Value Edition Plus MyLab Accounting with Pearson eText -- Access Card Package (5th Edition)
Ch. 11 - (Learning Objective 1) Which of the following is...Ch. 11 - (Learning Objective 2) The direct material price...Ch. 11 - Prob. 3QCCh. 11 - Prob. 4QCCh. 11 - Prob. 5QCCh. 11 - (Learning Objective 4) Which of the following is...Ch. 11 - Prob. 7QCCh. 11 - (Learning Objective 6) Which of the following is...Ch. 11 - Prob. 9QCCh. 11 - (Learning Objective 7Appendix) Which of the...
Ch. 11 - Compute the standard cost of direct materials...Ch. 11 - Compute the standard cost of direct labor...Ch. 11 - Explain a direct material variance (Learning...Ch. 11 - Prob. 11.4SECh. 11 - Calculate direct material variances when the...Ch. 11 - Calculate direct labor variances (Learning...Ch. 11 - Prob. 11.7SECh. 11 - Prob. 11.8SECh. 11 - Calculate fixed overhead variances (Learning...Ch. 11 - Calculate and interpret fixed overhead variances...Ch. 11 - Prob. 11.11SECh. 11 - Calculate and interpret overhead variances...Ch. 11 - Record costing transactions (Learning Objective 7)...Ch. 11 - Record standard costing transactions (Learning...Ch. 11 - Identify ethical standards violated (Learning...Ch. 11 - Vocabulary (Learning Objectives 1, 2, 3, 4, 5, 6)...Ch. 11 - Calculate standard cost and gross profit per unit...Ch. 11 - Calculate standard cost per unit (Learning...Ch. 11 - Calculate and explain direct material variances...Ch. 11 - Calculate missing direct material variables...Ch. 11 - Calculate and explain direct labor variances...Ch. 11 - Calculate and interpret direct material and direct...Ch. 11 - Calculate the material and labor variances...Ch. 11 - Record materials and labor transactions (Learning...Ch. 11 - Calculate the standard cost of a product before...Ch. 11 - Recognize advantages and disadvantages of standard...Ch. 11 - Compute and interpret overhead variances (Learning...Ch. 11 - Data Set for E11-28A through E11-32A Country...Ch. 11 - Data Set for E11-28A through E11-32A Country...Ch. 11 - Data Set for E11-28A through E11-32A Country...Ch. 11 - Make journal entries in a standard costing system...Ch. 11 - Prepare a standard cost income statement (Learning...Ch. 11 - Calculate standard cost and gross profit per unit...Ch. 11 - Calculate the standard cost per unit (Learning...Ch. 11 - Calculate and explain direct material variances...Ch. 11 - Calculate missing direct material variables...Ch. 11 - Calculate and explain direct labor variances...Ch. 11 - Prob. 11.38BECh. 11 - Prob. 11.39BECh. 11 - Prob. 11.40BECh. 11 - Prob. 11.41BECh. 11 - Recognize advantages and disadvantages of standard...Ch. 11 - Calculate and interpret overhead variances...Ch. 11 - Prob. 11.44BECh. 11 - Prob. 11.45BECh. 11 - Prob. 11.46BECh. 11 - Prob. 11.47BECh. 11 - Prob. 11.48BECh. 11 - Prob. 11.49APCh. 11 - Comprehensive standards and variances problem...Ch. 11 - Comprehensive standards and variances problem...Ch. 11 - Prob. 11.52APCh. 11 - Prob. 11.53APCh. 11 - Prob. 11.54BPCh. 11 - Comprehensive standards and variances problem...Ch. 11 - Comprehensive standards and variances problem...Ch. 11 - Work backward through labor variances (Learning...Ch. 11 - Determine all variances and make journal entries...Ch. 11 - Calculate labor variances in a hotel (Learning...
Knowledge Booster
Learn more about
Need a deep-dive on the concept behind this application? Look no further. Learn more about this topic, accounting and related others by exploring similar questions and additional content below.Similar questions
- Esteban Products produces instructional aids, including white boards, which use colored markers instead of chalk. These are particularly popular for conference rooms in educational institutions and executive offices of large corporations. The standard cost of materials for this product is 12 pounds at $8.75 per pound. During the first month of the year, 3,700 boards were produced. Information concerning actual costs and usage of materials follows: Materials purchased 44,000 lbs. @ $8.85 Materials used 43,500 lbs. Required: 1. Compute the materials price and usage variances. 2. Prepare journal entries on Jan. 31 for all activity relating to materials. CHART OF ACCOUNTS General Ledger ASSETS 110 Cash 120 Accounts Receivable 131 Supplies 132 Prepaid Insurance 141 Materials 142 Work in Process 143 Overhead Control 144 Finished Goods 170 Land 180 Equipment 181 Accumulated Depreciation LIABILITIES 210…arrow_forwardYour company has received an order for 20 units of aproduct. Th e labor cost to produce the item is $9.50 per hour. Th esetup cost for the item is $60 and material costs are $25 per unit. Th e item is sold for $92. Th e learning rate is 80 percent. Overheadis assessed at a rate of 55 percent of unit labor cost.(a) Determine the average unit cost for the 20 units if the fi rstunit takes four hours.(b) Determine the minimum number of units that need to bemade before the selling price meets or exceeds the averageunit cost.arrow_forwardSharon Glessing, controller for Janson Company, has noticed that the company faces a 80 percent learning rate for its specialty design line. In planning the cost of the latest design, Sharon assumed that the first set of units would take 1,100 direct labor hours. She decided to use this information in budgeting for the cost of the total project, which would involve the manufacture of 16 sets. Direct labor is paid $40 per hour. 1. Complete the table below showing results by row for total production of: one unit, two units, four units, eight units, and sixteen units. (Round hour answers to two significant digits.) (Round Cumulative Total Time answers to the nearest whole number.) 2. What is the total labor cost if Janson Company makes eight sets? Sixteen sets? (Use the rounded answers in the subsequent computations). 3. Using the logarithmic function, complete the table below showing results by row for each of unit sets one through eight. (Round hour answers to two significant digits.)…arrow_forward
- Bordner Company manufactures HVAC (heating, ventilation, and air conditioning) systems for commercial buildings. For each new design, Bordner faces a 90 percent learning rate. On average, the first unit of a new design takes 600 hours. Direct labor is paid 25 per hour. Required: 1. Set up a table with columns showing: the cumulative number of units, cumulative average time per unit in hours, and cumulative total time in hours. Show results by row for total production of one unit, two units, four units, eight units, and sixteen units. (Round hour answers to two significant digits.) 2. What is the total labor cost if Bordner makes the following number of units: one, four, sixteen? What is the average cost per system for the following number of systems: one, four, or sixteen? (Round your answers to the nearest dollar.) 3. Using the logarithmic function, set up a table with columns showing: the cumulative number of units, cumulative average time per unit in hours, cumulative total time in hours, and the time for the last unit. Show results by row for each of units one through eight. (Round answers to two significant digits.)arrow_forwardShorts Manufacturing, Inc., has implemented lean manufacturing in its Kansas City plant as a pilot program. One of its value streams produces a family of small electric tools. The value-stream team managers were quite excited about the results, as some of their efforts to eliminate waste were proving to be effective. During the most recent three weeks, the following data pertaining to the electric tool value stream were collected: Week 1: Demand = 90 units @ 40 Beginning inventory = 10 units @ 20 (5 materials and 15 conversion) Production = 90 units using 450 of material and 1,350 of conversion cost Week 2: Demand = 100 units @ 40 Beginning inventory = 10 units @ 20 (5 materials and 15 conversion) Production = 90 units using 450 of material and 1,350 of conversion cost Week 3: Demand = 90 units @ 40 Beginning inventory = 0 Production = 100 units using 500 of material and 1,500 of conversion cost Required: 1. Prepare a traditional income statement for each week. 2. Calculate the average value-stream product cost for each week. What does this cost signal, if anything? 3. Prepare a value-stream income statement for each week. Assume that any increase in inventory is valued at average cost. Comment on the financial performance of the value stream and its relationship to traditional income measurement.arrow_forwardLearnCo LearnCo manufactures and sells one product, an abacus for classroom use, with two models, the Basic model and the Deluxe model. The company began operations on January 1, 20Y1, and is planning for 20Y2, its second year of operations, by preparing budgets from its master budget. The company is trying to decide how many units to manufacture, how much it might spend on direct materials and direct labor, and what their factory overhead expenses might be. In addition, the company is interested in budgeting for selling and administrative costs, and in creating a budgeted income statement showing a prediction of net income for 20Y2. You have been asked to assist the controller of LearnCo in preparing the 20Y2 budgets. Sales Budget The sales budget often uses the prior year’s sales as a starting point, and then sales quantities are revised for various factors such as planned advertising and promotion, projected pricing changes, and expected industry and general economic conditions.…arrow_forward
- Can you answer question #4? Highland Company produces a lightweight backpack that is popular with college students. Standard variable costs relating to a single backpack are given below: Standard Quantity or Hours Standard Price or Rate Standard Cost Direct materials ? $ 5.00 per yard $ ? Direct labor ? ? ? Variable manufacturing overhead ? $ 2 per direct labor-hour ? Total standard cost per unit $ ? Overhead is applied to production on the basis of direct labor-hours. During March, 780 backpacks were manufactured and sold. Selected information relating to the month’s production is given below: Materials Used Direct Labor Variable Manufacturing Overhead Total standard cost allowed* $ 15,600 $ 13,104 $ 2,496 Actual costs incurred $ 13,112 ? $ 5,491 Materials price variance ? Materials quantity variance $ 790 U Labor rate variance ? Labor efficiency variance ? Variable overhead rate variance ?…arrow_forwardAverage labor cost for the first 700 units of a product is RO 50 and the average labor cost of first 1400 units is RO 45. Average time per unit is 100 minutes. The learning ratio and the average labour cost for first 2800 units will be: a. 80% and RO 36.000 b. 90% and RO 40.500 c. 85% and RO 38.250 d. 95% and RO 42.750arrow_forwardThe Terminator Inc. provides on-site residential pest extermination services. The company has several mobile teams who are dispatched from a central location in company-owned trucks. The company uses the number of jobs to measure activity. At the beginning of April, the company budgeted for 100 jobs, but the actual number of jobs turned out to be 105. A report comparing the budgeted revenues and costs to the actual revenues and costs appears below: (picture) Required:Is the above variance report useful for evaluating how well revenues and costs were controlled during April? Why, or why not?arrow_forward
- The Beacon Hills High School entered into a contract with Beacon Printing Services which stipulates that the latter shall produce 10,000 sets of modules to be distributed to learners during the 1st quarter of the school year. The contract further states that Beacon Printing Services shall charge Beacon Hills High School at 20% above cost. Overhead costs are applied at the rate of P 10.00 per hour. After the job was completed, it was found out that 2,000 sets were determined to be spoiled due to significant errors. Fortunately, the 2,000 spoiled sets can be sold to a scrap buyer for P 3.00 per set. Direct costs charged to the job are: Materials – P 300,000 and Direct Labor (P15.00 per hour) – P 60,000. Only 8,000 sets were delivered to Beacon Hills High School. FIND: How much should be charged to Work In Process to record production cost? How much should be charged to Spoiled Good Inventory? What is the total cost of the finished goods inventory assuming that spoilage is to be…arrow_forwardHighland Company produces a lightweight backpack that is popular with college students. Standard variable costs relating to a single backpack are given below: Standard Quantity Hours Standard Price or Rate Standard Cost Direct materials ? $7.5 per yard $? Direct labor ? ? ? Variable manufacturing overhead ? $3.6 per direct labor-hour ? Total standard cost $? Overhead is applied to production on the basis of direct labor-hours. During March, 1,000 backpacks were manufactured and sold. Selected information relating to the month's production is given below: Materials Used Direct Labor Variable Manufacturing Overhead Total standard cost allowed (for the month's production) $22,500 $16,600 $7,200 Actual costs incurred $21,942 ? $6,600 Direct materials price variance ? Direct materials quantity variance $1,350 U Direct labor rate variance ? Diret labor efficiency variance Variable overhead rate variance ? Variable overhead efficiency variance ? The following additional…arrow_forwardShawnTech is a for-profit vocational school. The school bases its budgets on two measures of activity (i.e., cost drivers), namely student and course. The school uses the following data in its budgeting: Fixed element per month variable element per student variable element per course revenue $0 $354 $0 faculty wages $0 $0 $2,300 course supplies $0 $48 $40 administrative expenses $41,700 $13 $21 In October, the school budgeted for 1,400 students and 127 courses. The actual activity for the month was 1,500 students and 129 courses. Prepare a report showing the school's activity variances for October. Label each variance as favorable (F) or unfavorable (U).arrow_forward
arrow_back_ios
SEE MORE QUESTIONS
arrow_forward_ios
Recommended textbooks for you
- Cornerstones of Cost Management (Cornerstones Ser...AccountingISBN:9781305970663Author:Don R. Hansen, Maryanne M. MowenPublisher:Cengage Learning
Cornerstones of Cost Management (Cornerstones Ser...
Accounting
ISBN:9781305970663
Author:Don R. Hansen, Maryanne M. Mowen
Publisher:Cengage Learning
What is variance analysis?; Author: Corporate finance institute;https://www.youtube.com/watch?v=SMTa1lZu7Qw;License: Standard YouTube License, CC-BY