Question
Chapter 11, Problem 4P
Summary Introduction
To calculate: The payback period for the given project.
Introduction:
Payback Period:
It refers to the time period that is required to get an amount invested in a project with some return on the project. In other words, it is the time that a project takes to repay the amount invested with some return attached to the project.
Expert Solution & Answer
Want to see the full answer?
Check out a sample textbook solutionStudents have asked these similar questions
i) Calculate the payback period for each project.
ii) Calculate the net present value (NPV) for each project.
Determine the payback period for each project (project A and B)
a) Calculate the discounted payback period for the project.
b) Calculate the Net Present Value of the project.
Chapter 11 Solutions
Fundamentals of Financial Management (MindTap Course List)
Ch. 11 - How are project classifications used in the...Ch. 11 - Prob. 2QCh. 11 - Why is the NFV of a relatively long-term project...Ch. 11 - Prob. 4QCh. 11 - If two mutually exclusive projects were being...Ch. 11 - Discuss the following statement: If a firm has...Ch. 11 - Why might it be rational for a small firm that...Ch. 11 - Project X is very risky and has an NPV of 3...Ch. 11 - Prob. 9QCh. 11 - A firm has a 100 million capital budget. It is...
Ch. 11 - NPV Project L costs 65,000, its expected cash...Ch. 11 - IRR Refer to problem 11-1. What is the projects...Ch. 11 - MIRR Refer to problem 11-1. What is the projects...Ch. 11 - Prob. 4PCh. 11 - DISCOUNTED PAYBACK Refer to problem 11-1. What is...Ch. 11 - NPV Your division is considering two projects with...Ch. 11 - CAPITAL BUDGETING CRITERIA A firm with a 14% WACC...Ch. 11 - Prob. 8PCh. 11 - CAPITAL BUDGETING CRITERIA: ETHICAL CONSIDERATIONS...Ch. 11 - CAPITAL BUDGETING CRITERIA: MUTUALLY EXCLUSIVE...Ch. 11 - CAPITAL BUDGETING CRITERIA: MUTUALLY EXCLUSIVE...Ch. 11 - Prob. 12PCh. 11 - MIRR A firm is considering two mutually exclusive...Ch. 11 - CHOOSING MANDATORY PROJECTS ON THE BASIS OF LEAST...Ch. 11 - NPV PROFILES: TIMING DIFFERENCES An oil-drilling...Ch. 11 - Prob. 16PCh. 11 - CAPITAL BUDGETING CRITERIA A company has an 11%...Ch. 11 - NPV AND IRR A store has 5 years remaining on its...Ch. 11 - Prob. 19PCh. 11 - NPV A project has annual cash flows of 5,000 for...Ch. 11 - Prob. 21PCh. 11 - MIRR A project has the following cash flows: This...Ch. 11 - CAPITAL BUDGETING CRITERIA Your division is...Ch. 11 - BASICS OF CAPITAL BUDGETING You recently went to...
Knowledge Booster
Similar questions
- Calculate the project cash flows for each year. Based on these cash flows and the average project cost of capital, what are the projects NPV, IRR, MIRR, PI, payback, and discounted payback? Do these indicators suggest that the project should be undertaken?arrow_forwardWhat is the payback period of each project?arrow_forwardCalculate the Rate of Return of the project. Explain, how and why? Rate of interest = 10%arrow_forward
- Calculate the internal rate of return for project Barrow_forwardRequired: Calculate the projects approximate payback periodarrow_forward9-9 What is the discounted payback period for each project? What is the NPV for each project? What is the IRR for each project? What is the profitability index for each project? Which project would you finally choose?arrow_forward
- Calculate the net present value of each project (project A and B)arrow_forwardUsing image: a-1. What is the payback period for each project a-2. If you apply the payback criterion, which investment will you choose? b-1. What is the discounted payback period for each project? b-2. If you apply the discounted payback criterion, which investment will you choose? c-1. What is the NPV for each project? c-2. If you apply the NPV criterion, which investment will you choose? d-1. What is the IRR for each project? d-2. If you apply the IRR criterion, which investment will you choose? e-1. What is the profitability index for each project? e-2. If you apply the profitability index criterion, which investment will you choose? f. Based on your answers in (a) through (e), which project will you finally choose?arrow_forwardSolve c) What is the payback period (PB) for this project?arrow_forward
arrow_back_ios
SEE MORE QUESTIONS
arrow_forward_ios
Recommended textbooks for you
- Intermediate Financial Management (MindTap Course...FinanceISBN:9781337395083Author:Eugene F. Brigham, Phillip R. DavesPublisher:Cengage Learning
Intermediate Financial Management (MindTap Course...
Finance
ISBN:9781337395083
Author:Eugene F. Brigham, Phillip R. Daves
Publisher:Cengage Learning