Suppose you are assigned to supervise a construction site. The contractor bought cement and you are asked to advise them on how to store the cement. So as a professional who knows about the properties of cement and their storage cares, what will be your advice to the contractor?
A simple platform having a stair will be constructed, as an estimator, your boss gave you an assignment to estimate the concrete works needed for the stairs only. The width of the stair is exactly 1 meter.
Using Class "A" concrete mixture, how many 40 kg bags of cement is required?
if you have a delivery of 255 m3 of concrete how many samples do you have?
Knowledge Booster
Learn more about
Need a deep-dive on the concept behind this application? Look no further. Learn more about this topic, civil-engineering and related others by exploring similar questions and additional content below.Similar questions
- Please describe the requirements for the concrete transportation.arrow_forwardshow complete solution and fbd asaparrow_forwardAnswer the following, a) Given a Concrete Mix Ratio of 1:2:3, what is the computed number of cement bags per cubic meter of concrete? b) Given a Concrete Mix Ratio of 1:2:4, what is the computed required volume of gravel for 1 cubic meter of concrete? c) A team of 2 skilled mason and 4 laborers are assigned to work on a 20 cubic meter volume of concreting work. They finished the job in 5 days, working 8 hours a day. What is there Productivity rate for the activity? d) A concrete vibrator was rented for concreting works. Rent is at 750 Pesos per day. Concrete pouring was computed to be completed in 5 days, but was actually finished in 4 days. How much was budgeted for equipment rental? e) My database for Formworks and Falseworks Unit cost is Php 1, 040 per sq. m. If I am to Construct 4 columns with height of 2.5 meters per column and Cross section of 0.3m x 0.4m, How much should my budget be for my formworks and falsework- based on the Unit cost?arrow_forward
- Calculate the cost per cubic yard to place concrete using each of the alternatives described. The work in both cases consists of placing 140 cubic yards of concrete in footings. a. Using a crane and bucket at a price of $225 per hour, including an operator, with a crew consisting of 6 laborers, a cement finisher, and a foreman. The concrete will be placed in 7 hours using this setup, and transportation of the crane costs $390. b. Using a concrete pump at a price of $295 per hour, including an operator and a crew consisting of 5 laborers, a cement finisher, and a foreman. With this setup, concrete is placed in 6 hours and transportation of the pump costs $290.arrow_forwardDerive the labor and equipment cost for a 1,000 sq.m 4" thick masonry wall using 1:5 mortar mixture based from the following crew team composition, output and given prices. 1. Team and Daily Rates 1- Project Engineer (P 2000/day) 1 - Construction Foreman (P 1000/day) 6 - Mason (P800/day) 12 - Laborer (P500/day) 2. Output of team is 13.5 cu.m per day. 3. Equipment (minor tools) is 10% of the labor cost.arrow_forwardSuppose you are assigned as a material engineer for a construction of a dam that requires mass-concrete construction.a) Which type of cement will you recommend? Explain your answer in detail.b) If the cement you selected is not available, what other construction methods will you recommend?arrow_forward
- A bill of quantity of a project includes 500m2 of masonry work. The work will be done by one crew with a production rate of 50 m2/day and consists of: Crew member No Price rate Brick layer 2 50$/day Assistant 1 25 Labor 2 12 Vendor price of 1000 bricks = 160$. Each 55 bricks are estimated to make one square meter of masonry. Each one cubic meter of mortar is used to join brick area of 50 m2 and consists of: Quantity Material Primary quotation form vendor One cubic meter Sand 15$/m3 6 sacks (50 kg each) Cement 240$/ton As a contractor, it is required to estimate the work unit price and the work price. Assume all material waste as 10% and assume overheads and markup as 20% of total cost. (WRITE THE ANSWER ONLY)arrow_forwardDiscuss the problem of disposal of waste water from ready-mixed concrete oper-ations. State three alternate methods that can be used to alleviate this problem.arrow_forwardDerive the labor and equipment cost for a 1,000 sq.m 4" thick masonry wall using 1:5 mortar mixture based from the following crew team composition, output and given prices.1. Team and Daily Rates1- Project Engineer (P 2000/day)1 - Construction Foreman (P 1000/day)6 - Mason (P800/day)12 - Laborer (P500/day)2. Output of team is 13.5 cu.m per day.3. Equipment (minor tools) is 10% of the labor cost.arrow_forward
- A labor crew for placing concrete consists of one labor foreman at $27.69 per hour, one cement finisher at $29.30 per hour, 4 laborers at $24.45 per hour each, and one equipment operator at $34.3 per hour. Such a crew, called a C20 crew, can place 156 cubic yards of concrete per 8-hour day. Determine the cost of C20 crew per cubic yard of concrete. The cost of C20 crew per cubic yard of concrete is determined to be $arrow_forwardplease calculate GLA(Gross Lettable Area) for this industrial building with all calculations.arrow_forwardshow complete solution. need asaparrow_forward
arrow_back_ios
SEE MORE QUESTIONS
arrow_forward_ios
Recommended textbooks for you
- Fundamentals Of Construction EstimatingCivil EngineeringISBN:9781337399395Author:Pratt, David J.Publisher:Cengage,
Fundamentals Of Construction Estimating
Civil Engineering
ISBN:9781337399395
Author:Pratt, David J.
Publisher:Cengage,
Pricing Concrete Jobs - 24' X 24' Concrete Floor (Prep, Pour, Finish); Author: Mike Day Concrete;https://www.youtube.com/watch?v=V-fgI1Hiu9w;License: Standard Youtube License