Can the optimal stocking level in the single-period model ever be less than expected demand? Explain briefly.
Expert Solution & Answer
Want to see the full answer?
Check out a sample textbook solutionStudents have asked these similar questions
Can the optimal stocking level in the single-period model ever be less than expected demand?Explain briefly.
Electro Fans has just received an order for one thousand 20˝ fans due in week 7. Each fan consists of a housing assembly, two grills and a fan assembly. The housing assembly consists of a frame, two supports and a handle. The following table gives lead times, on-hand inventory, and scheduled receipts.
Table 1.1: Lead time and quantity on hand
Item
Lead Time
Qty on hand
Lot size#
Scheduled receipt
20˝ Fan
Housing
Frame
Supports (2)
Handle
Grills (2)
Fan Assembly
1
1
2
1
1
2
3
80
90
-
50
400
200*
150
-
-
-
100
400
450
-
50 fan assembly in week 2
* In week 3 it was found that 50% of the on hand inventory of the grills was damaged.
# Items without any lot size given should be considered as lot-for-lot.
(i) Construct a product structure.
(ii) Construct a time-phased product structure.
(iii) Prepare a net requirement plan.
A initially assume that Phi wants to minimize his inventory requirements. Assume that each order will be only for what is required for a single period. Calculate the net requirements and planned order releases for the gear boxes and input shafts. Assume that lot sizing is done using a lot-for-lot (L4L).
Gear box requirements
Week 1 2 3 4 5 6 7 8 9 10 11 12
Gross requirements
Scheduled receipts
Projected available balance
Net requirements
Planned order receipt
Planned order release
Input shaft requirements
Week 1 2 3 4 5 6 7 8 9 10 11 12
Gross requirements
Scheduled receipts
Projected available balance
Net requirements
Planned order receipt
Planned order release
Chapter 12 Solutions
EBK OPERATIONS MANAGEMENT
Ch. 12.3 - Prob. 1RQCh. 12 - What are the primary reasons for holding...Ch. 12 - What are the requirements for effective inventory...Ch. 12 - Briefly describe each of the costs associated with...Ch. 12 - What potential benefits and risks do RFID tags...Ch. 12 - Prob. 5DRQCh. 12 - Prob. 6DRQCh. 12 - a. List the major assumptions of the EOQ model. b....Ch. 12 - Explain briefly how a higher carrying cost can...Ch. 12 - What is safety stock, and what is its purpose?
Ch. 12 - Prob. 10DRQCh. 12 - What is meant by the term service level? Generally...Ch. 12 - Describe briefly the A-B-C approach to inventory...Ch. 12 - The purchasing agent for a company that assembles...Ch. 12 - Explain how a decrease in setup time can lead to a...Ch. 12 - What is the single-period model, and under what...Ch. 12 - Can the optimal stocking level in the...Ch. 12 - Prob. 17DRQCh. 12 - What trade-offs are involved in each of these...Ch. 12 - Who needs to be involved in inventory decisions...Ch. 12 - How has technology aided inventory management? How...Ch. 12 - To be competitive, many fast-food chains began to...Ch. 12 - As a supermarket manager, how would you go about...Ch. 12 - Sam is at the post office to mail a package. After...Ch. 12 - Give two examples of unethical conduct involving...Ch. 12 - Prob. 1PCh. 12 - a. The following table contains figures on the...Ch. 12 - A bakery buys flours in 25-pound bags. The bakery...Ch. 12 - A large law firm uses an average of 40 boxes of...Ch. 12 - Garden Variety Flower Shop uses 750 clay pots a...Ch. 12 - A produce distributor uses 800 packing crates a...Ch. 12 - A manager receives a forecast for next year....Ch. 12 - A food processor uses approximately 27,000 glass...Ch. 12 - The Friendly Sausage Factory (FSF) can produce hot...Ch. 12 - A chemical firm produces sodium bisulfate in...Ch. 12 - A company is about to begin production of a new...Ch. 12 - Prob. 12PCh. 12 - A mail-order house uses 18,000 boxes a year....Ch. 12 - A jewelry firm buys semiprecious stones to make...Ch. 12 - A manufacturer of exercise equipment purchases the...Ch. 12 - A company will begin stocking remote control...Ch. 12 - A manager just received a new price list from a...Ch. 12 - A newspaper publisher uses roughly 800 feet of...Ch. 12 - Given this information: Expected demand during...Ch. 12 - Given this information: Lead-time demand = 600...Ch. 12 - Demand for walnut fudge ice cream at the Sweet...Ch. 12 - The injection molding department of a company uses...Ch. 12 - A company uses 85 circuit boards a day in a...Ch. 12 - One item a computer store sells is supplied by a...Ch. 12 - The manager of a car wash received a revised price...Ch. 12 - A small copy center uses five 500-sheet boxes of...Ch. 12 - Ned's Natural Foods sells unshelled peanuts by the...Ch. 12 - Regional Supermarket is open 360 days per year....Ch. 12 - A service station uses 1,200 cases of oil a year....Ch. 12 - Caring Hospital's dispensary reorders doses of a...Ch. 12 - A drugstore uses fixed-order cycles for many of...Ch. 12 - Prob. 32PCh. 12 - Prob. 33PCh. 12 - Demand for jelly doughnuts on Saturdays at Don's...Ch. 12 - A public utility intends to buy a turbine as part...Ch. 12 - Skinner's Fish Market buys fresh Boston bluefish...Ch. 12 - A small grocery store sells fresh produce, which...Ch. 12 - Demand for devil's food whipped-cream layer cake...Ch. 12 - Prob. 39PCh. 12 - Demand for rug-cleaning machines at Clyde's...Ch. 12 - A manager is going to purchase new processing...Ch. 12 - A Las Vegas supermarket bakery must decide how...Ch. 12 - Offwego Airlines has a daily flight from Chicago...Ch. 12 - UPD Manufacturing produces a range of health care...Ch. 12 - Prob. 1.2CQCh. 12 - Prob. 2.1CQCh. 12 - SARAH LUBBERS AND CHRIS RUSCHE, GRAND VALLEY STATE...Ch. 12 - SARAH LUBBERS AND CHRIS RUSCHE, GRAND VALLEY STATE...Ch. 12 - Prob. 3.3CQCh. 12 - SARAH LUBBERS AND CHRIS RUSCHE, GRAND VALLEY STATE...Ch. 12 - Prob. 3.5CQCh. 12 - Prob. 1OTQCh. 12 - Prob. 2OTQCh. 12 - Prob. 3OTQCh. 12 - Prob. 4OTQ
Knowledge Booster
Learn more about
Need a deep-dive on the concept behind this application? Look no further. Learn more about this topic, operations-management and related others by exploring similar questions and additional content below.Similar questions
- Explore the concept of dynamic order quantity in the Wilson approach and how it adapts to changing demand patterns. Provide examples.arrow_forwardDemand for a power steering gear assembly is given by Period 1 2 3 4 5 6 7 8 9 10 Gear 14 12 12 13 5 90 20 20 20 20 Currently there are 50 parts on hand. The lot-sizing rule is, again, fixed order period using two periods. Lead time is three periods. Determine the planned order release schedule for the gear. Suppose each gear assembly requires two pinions. Currently there are 100 pinions on hand, the lot-sizing rule is lot-for-lot, and the lead time is one period. Determine the gross requirement and then the planned order release schedule for pinions.arrow_forwarda. Discuss why the EOQ formula may give poor results for determining planned order releases.b. If the forecasted demand for the end item is the same each period, will the EOQ formula result in optimal lot sizing at each level of the product structure? Explain.arrow_forward
- [item no. 11] In a single period inventory model, the demand is assumed to follow a normal distribution. The value of ML/(ML+MP) is 0.6. The company used marginal analysis with the normal distribution to determine the optimal stocking level X*. If the mean demand is 100, then X* a. is less than 100 b. is equal to 100 c. cannot be determined from the information given d. is greater than 100arrow_forwardMusa's Cashmere Sweaters has authorized the following MPS for her exclusive line of cashmere sweaters. She wants to use the MPS record for promising future orders. Current order promises are included. The MPS order quantity is 60 units. Beginning Inventory is 0. Complete the following MPS record. Period 1 2 3 4 5 6 7 8 9 10 11 12 Forecast 15 15 15 15 20 20 20 20 25 25 25 25 Customer orders 12 10 8 25 40 0 15 30 30 0 0 40 Projected available Available-to-promise MPS 60arrow_forwardIrvine Consolidated Closets (ICC) builds and sells shelving for homes and offices. For a certain shelving unit, SS1, ICC has gross requirements of 500, 800, and 650 units in weeks 4, 5, and 6, respectively. The lead-time on the SS1 shelving unit is two weeks. ICC currently has 600 of the SS1 on hand and this product is ordered in lot sizes of 300, that is, the order in multiples of 300. Determine the MRP schedule for the SS1 unit over a time frame of weeks 1 through 6. When and for how many units should ICC place their orders for the SS1? A key component of the SS1 is the TT2. Each SS1 contains four TT2s. Currently TT2’s are ordered in lots of size 1000 and there are 800 on hand. TT2s have a one-week lead time. Determine the MRP schedule for the TT2 unit over a time frame of weeks 1 through 6. When and for how many units should ICC place their orders for the TT2? Suppose annual demand for the SS1 shelving unit is 32,500. ICC’s holding cost is $0.50 per week for each SS1…arrow_forward
- The table below provides demand data for 6 weeks (weeks 31-36 for the current year) for one product. Inventory is managed with a periodic review system where T = 5 weeks and M = 280. The previous order was for 120 units at the end of week 28. The lead time is a constant 4 weeks. At the beginning of week 31 the inventory level is 130 units. Orders are made at the end of a week. 1. When is the next order? end of week __________ 2. How large is the next order? ___________ Week Demand Inventory 31 30 32 40 33 45 34 30 35 30 36 30arrow_forwardPlease do not give solution in image format thanku Calculate the ending inventory at month 6 of the following aggregate plan. The initial inventory is equal to zero. Month 1 2 3 4 5 6 Forecast 2,000 2,000 3,000 4,000 5,000 2,000 Output Regular permanent 2,800 2,800 2,800 2,800 2,800 2,800 Temporary Overtime 600 500 100 100 Select one: a. 1000 b. 0 c. 500 d. None of the options provided. e. 100arrow_forwardAnticipated demands for a five-period planning horizon are 14, 3, 0, 26, 15. Current starting inventory is four units, and the inventory manager would like to have eight units on hand at the end of the planning horizon. Assume that h = 1 and K = 30. Find the optimal production schedule. (Hint: Modify the first and the last period’s demands to account for starting and ending inventories.)arrow_forward
- 2. RoadHog Inc. is a small manufacturer of motorcycle accessories. It makes muffler with fins on a linethat is also used to make a variety of other products. Because it is costly to set up the line to produce themin batches, RoadHog has an incentive them in batches. However, while customer demand is known over a6-planning horizon, it is not necessarily constant from week to week. The unit cost, fixed setup cost andmonthly holding cost are given in the table.Data for the RoadHog Dynamic Lot SizingWeek 1 2 3 4 5 6Demand 30 50 60 25 20 40Setup Cost 150 150 150 150 150 150Holding cost 3 3 3 3 3 3a. Find the production plan and the total cost for lot for lot scheduling.b. Find the production plan and the total cost for lot for the fixed order quantity (FOQ = 100)scheduling.c. Find the production plan and the total cost for the fixed order period scheduling (Use FOP = 3weeks).d. Which strategy is the best?arrow_forwardA single inventory item is ordered from an outside supplier. The anticipateddemand for this item over the next 12 months is 6, 12, 4, 8, 15, 25, 20, 5, 10, 20, 5,12. Current inventory of this item is 4, and ending inventory should be 8. Assume aholding cost of $1 per period and a setup cost of $40. Determine the order policyfor this item based onc. Part period balancingarrow_forwardWhen might a dummy column be added to a transportation table?a) When supply does not equal demandb) When overtime is greater than regular timec) When subcontracting is greater than regular timed) When subcontracting is greater than regular time plus overtimec) When production needs to spill over into a new periodarrow_forward
arrow_back_ios
SEE MORE QUESTIONS
arrow_forward_ios
Recommended textbooks for you
- Practical Management ScienceOperations ManagementISBN:9781337406659Author:WINSTON, Wayne L.Publisher:Cengage,Operations ManagementOperations ManagementISBN:9781259667473Author:William J StevensonPublisher:McGraw-Hill EducationOperations and Supply Chain Management (Mcgraw-hi...Operations ManagementISBN:9781259666100Author:F. Robert Jacobs, Richard B ChasePublisher:McGraw-Hill Education
- Purchasing and Supply Chain ManagementOperations ManagementISBN:9781285869681Author:Robert M. Monczka, Robert B. Handfield, Larry C. Giunipero, James L. PattersonPublisher:Cengage LearningProduction and Operations Analysis, Seventh Editi...Operations ManagementISBN:9781478623069Author:Steven Nahmias, Tava Lennon OlsenPublisher:Waveland Press, Inc.
Practical Management Science
Operations Management
ISBN:9781337406659
Author:WINSTON, Wayne L.
Publisher:Cengage,
Operations Management
Operations Management
ISBN:9781259667473
Author:William J Stevenson
Publisher:McGraw-Hill Education
Operations and Supply Chain Management (Mcgraw-hi...
Operations Management
ISBN:9781259666100
Author:F. Robert Jacobs, Richard B Chase
Publisher:McGraw-Hill Education
Purchasing and Supply Chain Management
Operations Management
ISBN:9781285869681
Author:Robert M. Monczka, Robert B. Handfield, Larry C. Giunipero, James L. Patterson
Publisher:Cengage Learning
Production and Operations Analysis, Seventh Editi...
Operations Management
ISBN:9781478623069
Author:Steven Nahmias, Tava Lennon Olsen
Publisher:Waveland Press, Inc.
Inventory Management | Concepts, Examples and Solved Problems; Author: Dr. Bharatendra Rai;https://www.youtube.com/watch?v=2n9NLZTIlz8;License: Standard YouTube License, CC-BY