Make-or-Buy decision process and performing financial calculations in the Lease-or-Buy example:

  • Make-or-Buy decision process is a strategic decision in the procurement function.
  • In a Make-or-Buy decision process, the organization decides to carry out certain activities to deliver services or product, within the organization or hire a third party to do the same.
  • It includes careful cost estimation for delivering a product and comparing them with the relevant cost after outsourcing this operation.
  • Consider the example of Lease-or-Buy,  if buying an equipment for a project of price $12,000, with a daily operational cost of $400, if incase we can even lease the same piece of equipment for $800 per d...

Blurred answer
Students have asked these similar questions
Create a decision table for the below case: An order will be accepted only if the product is in stock and the customer’s credit is OK. If both conditions are met, the order is accepted. Otherwise, the order is rejected. Then, the company decides that the credit manager can waive the customer’s credit requirement.
Write the business rules that are reflected in the ERD shown in Figure P2.15. (Note that the ERD reflects some simplifying assumptions. For example, each book is written by only one author. Also, remember that the ERD is always read from the “1” to the “M” side, regardless of the orientation of the ERD components.) FIGURE P2.15 THE CROW’S FOOT ERD FOR PROBLEM 15
When a customer contacts the company to ask for an estimate, the proprietormakes a note of the customer’s contact details and an outline of the proposedwork. He agrees a date with the customer to view the property in order to givean estimate of the cost for the work. When visiting the property on the agreeddate the proprietor adds more detail to the outline of the proposed work. Within3 days of visiting the property the proprietor produces a fully detailed estimateand sends it to the customer. If the customer agrees the estimate, the proprietorschedules a date to start the job (this is based on the size of the job and otherjobs that have already been scheduled).A few days before the agreed start date of a job, the proprietor contacts thecustomer to confirm the start date, and then orders the required buildingmaterials from suppliers to be delivered on the date the job starts. At theend/completion of the job the proprietor calculates the actual cost of the job toproduce an invoice which…
Knowledge Booster
Background pattern image
Computer Science
Learn more about
Need a deep-dive on the concept behind this application? Look no further. Learn more about this topic, computer-science and related others by exploring similar questions and additional content below.
Similar questions
SEE MORE QUESTIONS
Recommended textbooks for you
Text book image
Information Technology Project Management
Computer Science
ISBN:9781337101356
Author:Kathy Schwalbe
Publisher:Cengage Learning
Text book image
Np Ms Office 365/Excel 2016 I Ntermed
Computer Science
ISBN:9781337508841
Author:Carey
Publisher:Cengage
Text book image
Database Systems: Design, Implementation, & Manag...
Computer Science
ISBN:9781305627482
Author:Carlos Coronel, Steven Morris
Publisher:Cengage Learning
Text book image
Operations Research : Applications and Algorithms
Computer Science
ISBN:9780534380588
Author:Wayne L. Winston
Publisher:Brooks Cole
Text book image
COMPREHENSIVE MICROSOFT OFFICE 365 EXCE
Computer Science
ISBN:9780357392676
Author:FREUND, Steven
Publisher:CENGAGE L
Text book image
A Guide to SQL
Computer Science
ISBN:9781111527273
Author:Philip J. Pratt
Publisher:Course Technology Ptr