Textbook Question
Book Icon
Chapter 12, Problem 3P

Sequence the jobs shown below by using a Gantt chart. Assume that the move time between machines is on” hour. Sequence” the jobs in priority order 1, 2, 3, 4.

JobWork Center/Machine Hours Due Date (days)
1 A/3, B/2, C/2 3
2 C/2, A/4 2
3 B/6, A/1, C/3 4
4 C/4, A/1, B/2  3
  1. a. What is the make span?
  2. b. How much machine idle time is there?
  3. c. When is each job delivered compared with its due date?
  4. d. How much idle time (waiting time) is there for each job?
  5. e. Devise a better job sequence for processing.

a)

Expert Solution
Check Mark
Summary Introduction

To determine: The makespan.

Introduction:

Gantt chart is the tool used to allocate the resources and schedule the tasks of projects.

Answer to Problem 3P

The makespan is 18 hours.

Explanation of Solution

Given information:

Moving time between the machines is one hour and sequence is given as 1, 2, 3, and 4. In addition to this, the information is given below:

OPERATIONS MANAGEMENT IN THE SUPPLY CHAIN: DECISIONS & CASES (Mcgraw-hill Series Operations and Decision Sciences), Chapter 12, Problem 3P , additional homework tip  1

Construct the Gantt chart:

OPERATIONS MANAGEMENT IN THE SUPPLY CHAIN: DECISIONS & CASES (Mcgraw-hill Series Operations and Decision Sciences), Chapter 12, Problem 3P , additional homework tip  2

Hence, the total makespan is 18 hours (refer the Gantt chart).

b)

Expert Solution
Check Mark
Summary Introduction

To determine: The machine idle time.

Introduction:

Gantt chart is the tool used to allocate the resources and schedule the tasks of projects.

Answer to Problem 3P

The machine idle time is 24 hours.

Explanation of Solution

Given information:

Moving time between the machines is one hour and sequence is given as 1, 2, 3, and 4. In addition to this, the information is given below:

OPERATIONS MANAGEMENT IN THE SUPPLY CHAIN: DECISIONS & CASES (Mcgraw-hill Series Operations and Decision Sciences), Chapter 12, Problem 3P , additional homework tip  3

Construct Gantt chart:

OPERATIONS MANAGEMENT IN THE SUPPLY CHAIN: DECISIONS & CASES (Mcgraw-hill Series Operations and Decision Sciences), Chapter 12, Problem 3P , additional homework tip  4

Determine the idle time for Machine A:

It can be determined that subtracting the sum of machine hours from the total makespan.

Idle time=Total makespanTotal machine hours=18(3+4+1+1)=189=9 hours

Determine the idle time for Machine B:

It can be determined that subtracting the sum of machine hours from the total makespan.

Idle time=Total makespanTotal machine hours=18(2+6+2)=1810=8 hours

Determine the idle time for Machine C:

It can be determined that the subtracting the sum of machine hours from the total makespan.

Idle time=Total makespanTotal machine hours=18(2+2+3+4)=1811=7 hours

Determine the machine idle time:

It can be calculated by adding the idle time of Machine A, Machine B, and Machine C.

Machine idle time=Idle time of Machine A+Idle time of Machine B+Idle time of Machine C=9+8+7=24 hours

Hence, the total machine idle time is 24 hours.

c)

Expert Solution
Check Mark
Summary Introduction

To determine: The delivery time of each job compared to due dates.

Introduction:

Gantt chart is the tool used to allocate the resources and schedule the tasks of projects.

Answer to Problem 3P

The delivery time does not exist due date.

Explanation of Solution

Given information:

Moving time between the machines is one hour and sequence is given as 1, 2, 3, and 4. In addition to this, the information is given below:

OPERATIONS MANAGEMENT IN THE SUPPLY CHAIN: DECISIONS & CASES (Mcgraw-hill Series Operations and Decision Sciences), Chapter 12, Problem 3P , additional homework tip  5

Construct Gantt chart:

OPERATIONS MANAGEMENT IN THE SUPPLY CHAIN: DECISIONS & CASES (Mcgraw-hill Series Operations and Decision Sciences), Chapter 12, Problem 3P , additional homework tip  6

Determine the delivery time:

Due date is given in days. It must be converted to hours by considering working hours per day is 8 hours.

Job Due date (hours) Delivery time (hours)
1 24 9
2 16 7
3 32 18
4 24 14

Delivery time is taken from the Gantt chart. Example: Job 1 is on its 9th hour at last. After that there is no Job 1.

d)

Expert Solution
Check Mark
Summary Introduction

To determine: The idle time of the jobs.

Introduction:

Gantt chart is the tool used to allocate the resources and schedule the tasks of projects.

Answer to Problem 3P

The job idle time is 11 hours.

Explanation of Solution

Given information:

Moving time between the machines is one hour and sequence is given as 1, 2, 3, and 4. In addition to this, the information is given below:

OPERATIONS MANAGEMENT IN THE SUPPLY CHAIN: DECISIONS & CASES (Mcgraw-hill Series Operations and Decision Sciences), Chapter 12, Problem 3P , additional homework tip  7

Construct Gantt chart:

OPERATIONS MANAGEMENT IN THE SUPPLY CHAIN: DECISIONS & CASES (Mcgraw-hill Series Operations and Decision Sciences), Chapter 12, Problem 3P , additional homework tip  8

Determine the idle time of the jobs

There is no idle time for Job 1 and Job 2. However, Job 3 has the idle time of 6 hours in Machine C from 9th hour to 15th hour (Refer Gantt chart). Job 4 has the idle time of 5 hours in Machine A from 8th hour to 13th hour (Refer Gantt chart).

Hence, the total idle time is 11 hours.

e)

Expert Solution
Check Mark
Summary Introduction

To determine: The better sequence for processing.

Introduction:

Gantt chart is the tool used to allocate the resources and schedule the tasks of projects.

Answer to Problem 3P

The makespan is 14 hours and the better sequence is 3, 2, 4, and 1.

Explanation of Solution

Given information:

Moving time between the machines is one hour and sequence is given as 1, 2, 3, and 4. In addition to this, the information is given below:

OPERATIONS MANAGEMENT IN THE SUPPLY CHAIN: DECISIONS & CASES (Mcgraw-hill Series Operations and Decision Sciences), Chapter 12, Problem 3P , additional homework tip  9

Construct the Gantt chart:

OPERATIONS MANAGEMENT IN THE SUPPLY CHAIN: DECISIONS & CASES (Mcgraw-hill Series Operations and Decision Sciences), Chapter 12, Problem 3P , additional homework tip  10

Hence, the total makespan is 14 hours (refer the Gantt chart).

Determine the idle time for Machine A:

It can be determined that subtracting the sum of machine hours from the total makespan.

Idle time=Total makespanTotal machine hours=14(3+4+1+1)=149=5 hours

Determine the idle time for Machine B:

It can be determined that subtracting the sum of machine hours from the total makespan.

Idle time=Total makespanTotal machine hours=14(2+6+2)=1410=4 hours

Determine the idle time for Machine C:

It can be determined that subtracting the sum of machine hours from the total makespan.

Idle time=Total makespanTotal machine hours=14(2+2+3+4)=1411=3 hours

Determine the machine idle time:

It can be calculated by adding the idle time of Machine A, Machine B, and Machine C.

Machine idle time=Idle time of Machine A+Idle time of Machine B+Idle time of Machine C=5+4+3=12 hours

Hence, the total machine idle time is 12 hours.

Determine the delivery time:

Due date is given in days. It must be converted to hours by considering the working hours per day as 8 hours.

Job Due date (hours) Delivery time (hours)
1 24 14
2 16 7
3 32 12
4 24 12

Delivery time is taken from the Gantt chart. Example: Job 2 is on its 7th hour at last. After that there is no Job 2.

Hence, the sequence 3, 2, 4, and 1 is better in makespan and idle time.

Want to see more full solutions like this?

Subscribe now to access step-by-step solutions to millions of textbook problems written by subject matter experts!
Students have asked these similar questions
Ron Satter field's excavation company uses bothGantt scheduling charts and Gantt load charts.a) Today, which is the end of day 7, Ron is reviewing the Ganttchart depicting these schedules:• Job # 151 was scheduled to begin on day 3 and to ta ke6 days. As of now, it is I day ahead of schedule.• Job# 177 was scheduled to begin on day J and take 4 days.It is currently on time.• Job #1 79 was scheduled to start on day 7 and take 2 days. Itactually got started on day 6 and is progressing according toplan.• Job #211 was scheduled to begin on day 5, but missingequipment delayed it until day 6. It is progressing asexpected and should take 3 days.• Job #215 was scheduled to begin on day 4 and take 5 days.It got sta rted on time but has since fallen behind 2 days.Draw the Gantt scheduling chart for the activities described.b) Ron now wants to use a Ga ntt load chart to see how muchwork is scheduled in each of his three work teams: Able,Baker, and Charlie. Five jobs constitute the current…
The following jobs are waiting to be processed at a small machine center:                                             AU dates are specified as manufacturing planning calendar days.Assume that all jobs arrived on day 210 (yesterday) in the ordershown but are not scheduled to begin until day 211 (today).a) Sequence the jobs according to LPT.b) What is the average completion (flow) time?c) What is the average job la teness?d) What is the average number of jobs in the system?
The following table contains information regarding jobs that are to be scheduled through one machine: Job Processing Time (Days) Due date A 4 20 B 12 30 C 2 15 D 11 16 E 10 18 F 3 5 G 6 9 Qus 1: Find the FCFS Schedule? Qus 2: Find the SOT Schedule? Qus 3:Find the DDate Schedule? Qus 4: What are the mean flow time and average lateness for each of the schedule above? Qus 5: Which priority rule is appropriate for job scheduling? Justify your answer.
Knowledge Booster
Background pattern image
Operations Management
Learn more about
Need a deep-dive on the concept behind this application? Look no further. Learn more about this topic, operations-management and related others by exploring similar questions and additional content below.
Similar questions
SEE MORE QUESTIONS
Recommended textbooks for you
Text book image
Practical Management Science
Operations Management
ISBN:9781337406659
Author:WINSTON, Wayne L.
Publisher:Cengage,
Text book image
Operations Management
Operations Management
ISBN:9781259667473
Author:William J Stevenson
Publisher:McGraw-Hill Education
Text book image
Operations and Supply Chain Management (Mcgraw-hi...
Operations Management
ISBN:9781259666100
Author:F. Robert Jacobs, Richard B Chase
Publisher:McGraw-Hill Education
Text book image
Business in Action
Operations Management
ISBN:9780135198100
Author:BOVEE
Publisher:PEARSON CO
Text book image
Purchasing and Supply Chain Management
Operations Management
ISBN:9781285869681
Author:Robert M. Monczka, Robert B. Handfield, Larry C. Giunipero, James L. Patterson
Publisher:Cengage Learning
Text book image
Production and Operations Analysis, Seventh Editi...
Operations Management
ISBN:9781478623069
Author:Steven Nahmias, Tava Lennon Olsen
Publisher:Waveland Press, Inc.
Inventory Management | Concepts, Examples and Solved Problems; Author: Dr. Bharatendra Rai;https://www.youtube.com/watch?v=2n9NLZTIlz8;License: Standard YouTube License, CC-BY