Program Description Answer
To get information from potential sellers for a project, a proposal document is requested by companies.
Hence, the correct answer is option “C”.
Expert Solution & Answer
Want to see the full answer?
Check out a sample textbook solutionStudents have asked these similar questions
Assignments
Lakeside Boatworks is planning to manufacture
three types of molded fiberglass recreational boats
-a fishing (bass) boat, a ski boat, and a small
speedboat. The estimated selling price and variable
cost for each type of boat are summarized in the
following table:
Boat
Variable Cost
Selling Price
Bass
$12,500
$23,000
Ski
8,500
18,000
Speed
13,700
26,000
The company has incurred fixed costs of $2,800,000
to set up its manufacturing operation and begin
production. Lakeside has also entered into
agreements with several boat dealers in the re- gion
to provide a minimum of 70 bass boats, 50 ski boats,
and 50 speedboats. Alternatively, the company is
unsure of what actual demand will be, so it has
decided to limit production to no more than 120 of
any one boat. The company wants to determine the
number of boats that it must sell to break even while
minimizing its total variable cost.
1. Formulate a linear programming model for
this problem.
2. Solve the model by using the…
A supermarket chain is considering opening a supermarket in Grenada. However, to receive funding from the Grenada Development Bank (GDB), the plan must be approved and construction ready to start within the next 26 weeks. One complicating factor is that the Physical Planning Unit must see an initial design of the supermarket before it will approve the building permit. The architectural planning section of the supermarket chain has determined the following list of activities necessary to receive approval from the GDB. Included are the predecessor relationships and some estimates for the activity completion times (estimates are in weeks).
Draw the project network diagram.
Calculate the expected duration and variance of all activities.
Determine the earliest start (ES), latest start (LS), earliest finish (EF), and latest finish times (LF) for each activity.
A supermarket chain is considering opening a supermarket in Grenada. However, to receive funding from the Grenada Development Bank (GDB), the plan must be approved and construction ready to start within the next 26 weeks. One complicating factor is that the Physical Planning Unit must see an initial design of the supermarket before it will approve the building permit. The architectural planning section of the supermarket chain has determined the following list of activities necessary to receive approval from the GDB. Included are the predecessor relationships and some estimates for the activity completion times (estimates are in weeks)
Draw the project network diagram.
Calculate the expected duration and variance of all activities.
Determine the earliest start (ES), latest start (LS), earliest finish (EF), and latest finish times (LF) for each activity.
Calculate the slacks and determine all critical paths and critical activities
What is the probability that the project will be…
Chapter 12 Solutions
INFORMATION TECHNOLOGY PROJECT MANAGEME
Knowledge Booster
Learn more about
Need a deep-dive on the concept behind this application? Look no further. Learn more about this topic, computer-science and related others by exploring similar questions and additional content below.Similar questions
- Question 30 Select the appropriate response What is a good rule to use for the minimum bending radius for drop cable? roughly 10 times the cable's diameter roughly 5 times the cable's radius roughly 2 inches O depends on the location and type of drop Submit Responsearrow_forwardWhat determines the amount of effort that goes into a feasibility study? Explain the statement above.arrow_forwardQuestion One (1) You participated in an evaluation of proposals for consulting services. At the end of the Technical Evaluation which required a minimum of 70 points, you got the following results: CONSULTANTS KANYIHAMPA MUSANGILA Technical Score 75.17 76.17 Amount USD475,000.00 USD625,000.00 The lowest evaluated financial proposal (Fm) is given the maximum financial score of 100. The formula for determining the financial score is as follows: SF = 100 x Fm /F in which SF is the financial score, Fm is the lowest price and F is the price of the proposal under consideration. The weights given to the Technical and Financial proposals are 80 and 20 respectively. Calculate for each consultant below (a – c): Weighted Technical score. Financial score Combined weighted Technical and weighted Financial score Indicate the best evaluated bidder and their pointsarrow_forward
- Following a tendering process your firm has recently been appointed external auditor of Dazzle Ltd (Dazzle) for the year ending 31 July 20X1. The audit engagement letter is still to be signed. The previous auditor did not seek reappointment. Your firm has also been invited to provide tax planning and compliance work for the company. All of the shares of Dazzle are owned by two sisters: Ruby and Amber Dazzle. They are the only directors and spend on average three days a week managing Dazzle as they have other business interests. The company employs a full-time qualified accountant but does not have a Finance Director. Dazzle manufactures and sells high quality mirrors and light fittings, which are produced in the company’s workshop, in the North East of England. At peak times the company uses subcontractors to help with the manufacture of light fittings as they lack sufficient staff in this area. Due to changes in working practices as a result of covid-19 fewer people are permitted in…arrow_forwardThe main idea and purpose of MODAF Strategical point of view. Answer:arrow_forwardA company specializing in custom-engineered equipment is planning to submit a proposal to the National 5. Aeronautics and Space Administration (NASA) to build an assembled component for a new space station that NASA plans to launch into orbit. The winning proposal will be selected on the basis of both cost and timely delivery. Also, there will be a penalty clause in the NASA contract for late delivery. The company has developed the schedule of activities that are required to produce the assembled component. The activities and precedence requirements are presented in the table below. Three time estimates (in weeks) are given for each activity: optimistic time, most likely time, and pessimistic time. (a) What completion time should the company specify in its proposal in order to be 85% sure that it will complete the project on time? ij Activity Immediate predecessor Optimistic time (weeks) a b d. h b e, d d e,f f,g h, i a a a 15 8 10 20 17 4 10 Most likely time (weeks) 24 16 10 14 26 23…arrow_forward
- How does one go about assessing a request for proposal (RFP)?arrow_forwardCase Study: Wish You Wood is a toy boutique located in the main shopping strip of a resort town near Piney Lake. People who own cabins near the lake or come to visit the local state park enjoy browsing through the town’s stores, where they pick up pottery, paintings, and Wish You Wood’s beautifully crafted wooden toys. For these shoppers, Wish You Wood is more than a store; it is a destination they associate with family and fun. The store’s owners, Russell and Vanessa Harris, personally select the toys from craftspeople around the world. They enjoy their regular customers but believe selling mostly to vacationers has limited the company’s growth. They decided that the lowest-cost way to expand would be to sell toys online. However, after several years of trying, traffic to the store’s website was still unimpressive. They were able to drive some business to their site using social media, but the site never took off in the way they had hoped. Russell and Vanessa concluded that the…arrow_forwardQUESTION 1 The OMCA club operations When members join OMCA health club, they pay a fee for a certain length of time. Most memberships are for 1 year, but memberships for short periods are available. Due to various promotions throughout the year, it is common for members to pay different amounts for the same length of membership. The club wants to e-mail reminders to members to ask them to renew their memberships one month before their memberships expire. Some members have been angry with staff when asked to renew at a much higher rate than their original membership contract. So, the club needs staff to keep track of the price paid so that the managers can override the regular prices with special prices when members are asked to renew. The system must keep track of these new prices so that renewals can be processed accurately. One of the problems in the health club industry is the high turnover rate of members. Although some members remain active for many years, about half of the…arrow_forward
- The Bright Light Academy The Bright Light Academy is a high school that is located in Midrand. The school opened its doors for enrolment of students in 2018. They enrol from Grade R to Grade 12. As of the last quarter of 2020, the school’s enrolment has grown tremendously to 400 students and they are anticipating that their enrolment will increase further. Since its inception, the school has been using Pastel Accounting to administer its finances. The school board of trustees has made a decision to develop an in-house integrated school management system. The school is hoping that the system will help in its blended learning strategy in the beginning of the second quarter of 2021. Source: Maodza, B. (2021)Question 4You have been hired as the Lead Architect of the school. Model a detailed use case diagram for the proposed integrated school management system.arrow_forwardDetailed solution please.arrow_forwardThe formulation and recording of functional requirements is a part of the bidding process. Rationale for using this approach to the purchase of ERP software even when soliciting bids is not requiredarrow_forward
arrow_back_ios
SEE MORE QUESTIONS
arrow_forward_ios
Recommended textbooks for you
- Information Technology Project ManagementComputer ScienceISBN:9781337101356Author:Kathy SchwalbePublisher:Cengage LearningPrinciples of Information Systems (MindTap Course...Computer ScienceISBN:9781285867168Author:Ralph Stair, George ReynoldsPublisher:Cengage LearningPrinciples of Information Systems (MindTap Course...Computer ScienceISBN:9781305971776Author:Ralph Stair, George ReynoldsPublisher:Cengage Learning
- Fundamentals of Information SystemsComputer ScienceISBN:9781305082168Author:Ralph Stair, George ReynoldsPublisher:Cengage LearningOperations Research : Applications and AlgorithmsComputer ScienceISBN:9780534380588Author:Wayne L. WinstonPublisher:Brooks ColeInformation Technology Project ManagementComputer ScienceISBN:9781285452340Author:Kathy SchwalbePublisher:Cengage Learning
Information Technology Project Management
Computer Science
ISBN:9781337101356
Author:Kathy Schwalbe
Publisher:Cengage Learning
Principles of Information Systems (MindTap Course...
Computer Science
ISBN:9781285867168
Author:Ralph Stair, George Reynolds
Publisher:Cengage Learning
Principles of Information Systems (MindTap Course...
Computer Science
ISBN:9781305971776
Author:Ralph Stair, George Reynolds
Publisher:Cengage Learning
Fundamentals of Information Systems
Computer Science
ISBN:9781305082168
Author:Ralph Stair, George Reynolds
Publisher:Cengage Learning
Operations Research : Applications and Algorithms
Computer Science
ISBN:9780534380588
Author:Wayne L. Winston
Publisher:Brooks Cole
Information Technology Project Management
Computer Science
ISBN:9781285452340
Author:Kathy Schwalbe
Publisher:Cengage Learning